Agency Comments PZy
RICHARD DURRANT
CHAIRMAN OF THE BOARD
$OISE PROJECT BOARD OF CONTROL
GRAHAM PATERSON
VICE CHAIRMAN OF THE BOARD (FORMERLY BOISE U.S. RECLAMATION PROJECT)
TIMOTHY M. PAGE 2465 OVERLAND ROAD
PROJECT MANAGER BOISE, IDAHO 83705-3155
ROBERT D. CARTER
ASSISTANT PROJECT MANAGER
APRYL GARDNER
SECRETARY-TREASURER
JERRIFLOYD
ASSISTANT SECRETARY-
TREASURER
17 March 2014
City of Meridian
City Clerk's Office
33 E. Broadway Avenue,
Meridian, Idaho 83642
RE: L.C. Development - Biltmore Subdivision File No. PP 14-004
S. of W. Victory Rd. & W. of S. Meridian Rd.
New York Irrigation District NY-109-001-00
Boise- Kuna Irrigation District BK- 88
Sundell Lateral 49+70, 51+50, 51+60
Tumbler Latera130+00
Sec. 25, T3N, R1 W, B.M.
Jaycee HQ"1mai~,~City Clerk:
OPERATING AGENCY FOR 167,000
ACRES FOR THE FOLLOWING
IRRIGATION DISTRICTS
NAMPA-MERIDIAN DISTRICT
BOISE-KUNA DISTRICT
WILDER DISTRICT
NEW YORK DISTRICT
BIG BEND DISTRICT
TEL: (208)344-1141
FAX: (208)344-1437
The United States' Sundell Lateral and the United States' Tumbler Lateral lie within the
boundary of the above-mentioned location. The easements for these laterals are held in
the name of the United States through the Bureau of Reclamation under the authority of
the Act of August 30, 1890. (26 Stat. 391; 43 U.S.C. 945)
The Boise Project Board of Control is contracted to operate and maintain these laterals.
We assert a federal easement 20' northerly and 18' southerly of the Sundell Lateral
centerline and we assert a federal easement 12' each direction of the Tumbler Lateral
centerline. Whereas these areas are for the operation and maintenance of our facilities, no
activity should hinder our ability to do so.
Fencing (as may be required) must be constructed just off of Boise Project facilities, to
insure public safety and prevent encroachments.
Wording on the preliminary and final recorded plat needs to be noted that this
development must adhere to Idaho Statutes, Title 42-1209.
The Boise Project does not approve landscaping (other than grass) within its easements,
as this will certainly increase our cost of maintenance.
Project facilities and/or easements that parallel, and are within and/or intended to be
within road right-of--ways due to any development of this property must be relocated
outside of road right-of--ways. The easements of Boise Project facilities will remain the
same unless agreed upon and/or approved with written permission from Boise Project
Board of Control.
Crossing agreements must be secured and signed by all parties prior to March 1St of each
year. A time schedule for the construction to be done during the non-irrigation season
must be approved by Boise Project prior to any activity within Project easements. No
construction will be allowed within the easement boundaries of the Boise Project Board
of Control facilities after March 15th of each year. However, on a case by case basis,
overhead utilities and utilities boring underneath a Project facility may be allowed after
March 15th if reviewed and approved by the Boise Project.
Whereas this property lies within the New York Irrigation District and the Boise-Kung
Irrigation District, it is important that representatives of this development contact the
NYID and the BKID offices as soon as possible to discuss the pressure system prior to
any costly design work. If applicable, the irrigation system will have to be built to
specific specifications as set by the District /Project.
Written response from the New York Irrigation District and the Boise-Kung Irrigation
District is required.
Storm Drainage and/or Street Runoff must be retained on site.
Local irrigation/drainage ditches that cross this property, in order to serve neighboring
properties, must remain unobstructed and protected by an appropriate easement.
This development is subject to Idaho Code 31-3805, in accordance, this office is
requesting a copy of the irrigation and drainage plans.
If you have any further questions or comments regarding this matter, please do not
hesitate to contact me at (208) 344-1141.
Sincerely,
,~ '
Bob Carter
Assistant Project Manager BPBC
bdc/bc
cc: Phil Comegys
Velta Harwood
Lauren Boehlke
File
Watermaster, Div; 2 BPBC
Secretary -Treasurer, NYID
Secretary-Treasurer, BKID
CENTRAL
•• DISTRICT
~THEALTH
DEPARTMENT
Rezone #
Conditional Use #
CENTRAL DISTRICT HEALTH DEPARTMENT
Environmental Health Division
~~
Preliminary /Final /Short Plate 1~" Ct~'~
1~ ;Y\U`~
Return to:
^ ACZ
^ Boise
^ Eagle
^ Garden City
^ Kuna
Meridian
^ Star
^ 1. We have No Objections to this Proposal.
^ 2. We recommend Denial of this Proposal.
^ 3. Specific knowledge as to the exact type of use must be provided before we can comment on this Proposal.
^ 4. We will require more data concerning soil conditions on this Proposal before we can comment.
^ 5. Before we can comment concerning individual sewage disposal, we will require more data concerning the depth of:
^ high seasonal ground water ^ waste flow characteristics
^ bedrock from original grade ^ other
^ 6. This office may require a study to assess the impact of nutrients and pathogens to receiving ground waters and
surface waters.
^ 7. This project shall be reviewed by the Idaho Department of Water Resources concerning well construction and
water availability.
C~ 8. After written approval from appropriate entities are submitted, we can approve this proposal for:
f _ "t~ central sewage ^ community sewage system ^ community water well
^ interim sewage t~entral water
^ individual sewage ^ individual water
~/9. The following plan(s) must be submitted to and approved by the Idaho Department of Environmental Quality:
>~ central sewage ^ community sewage system ^ community water
^ sewage dry lines °E~central water
^ 10. This Department would recommend deferral until high seasonal ground water can be determined if other
considerations indicate approval.
^ 11. If restroom facilities are to be installed, then a sewage system MUST be installed to meet Idaho State
Sewage Regulations.
^ 12. We will require plans be submitted for a plan review for any:
^ food establishment ^ swimming pools or spas ^ child care center
^ beverage establishment ^ grocery store
I~`13. Infiltration beds for storm water disposal are considered shallow injection wells. An application and fee must be
submitted to CDHD.
^ 14.
Reviewed By
1
Dater/~/~
Review Sheet
15726-001EH1111
,~ 13
City of Meridian
City Clerk's Office
33 E Broadway Avenue, Suite 102
Meridian, ID 83642-2619
RE: PP 14-004/Biltmore Sub
Dear Jaycee:
1503 FIRST STREET SOUTH NAMPA, IDAHO 83651-4395
FAX #208-463-0092 nmid.org
OFFICE: Nampa 208-466-7861
SHOP: Nampa 208-466-0663
If all storm drainage is retained on-site there will be no impact on Nampa & Meridian.
Irrigation District (NMID) and no further review will be required.
However, if any surface drainage leaves the site, Nampa & Meridian Irrigation District
(NMID) requires a Land Use Change Application be filed for review; prior to final platting.
Please contact Suzy Hewlett at 466-7861 for further information.
All laterals and waste ways must be protected. The developer must comply with Idaho Code
31-3805. It is recommended that irrigation water be made available to all developments
within the Nampa & Meridian Irrigation District (NMID).
Sincerely, ~ 1
~ 1..~-~
Greg G. Curtis
Water Superintendent
Nampa & Meridian Irrigation District
GGC/dbg
PC: Office,'File
.,.
APPROXIMATE IRRIGABLE ACRES
RIVER FLOW RIGHTS - 23,000
BOISE PROJECT RIGHTS - 40,000
Enginr3ering Solutions, LLP
1029 N. Rosario Street, Suite 100
Meridian, ID-83642
1503 FIRST STREET SOUTH
FAX #208-463-0092
NAMPA, IDAHO 83651-4395
nmid.org
OFFICE: Nampa 208-466-7861
SHOP: Nampa 208-466-0663
RE: Land Use Change Application - Biltmore Subdivision
Please note the District now requires three (31 sets of plans
To Whom It May Concern:
Enclosed please find a Land Use Change Application for your use to file with the Irrigation
District for its review on the above-referenced development. If this development is under a
"rush" to be finalized, I would recommend that you submit a cashier's check, money order or
cash as payment of the fees in order to speed the process up. If you submit a company or
personal check, it must clear the bank before processing the application.
Should this development be planning a pressure urban irrigation system that will be owned,
operated and maintained by the Irrigation District, I strongly urge you to coordinate with Greg G.
Curtis, Water Superintendent for the Irrigation District, concerning the installation of the
pressure system. Enclosed is a questionnaire that you must fill out and return in order to initiate
the process of contractual agreements between the owner or developer and the Irrigation
District for the ownership, operation and maintenance of the pressure urban irrigation system.
If you have any questions concerning this matter, please feel free to call on me at the District's
office, or Greg G. Curtis, at the District's shop.
Sincerely,
Suzette G. Hewlett, Asst. Secretary/Treasurer
NAMPA & MERIDIAN IRRIGATION DISTRICT
SGH/cmg
cc: File
Water Superintendent
City Clerk's Office, City of Meridian
L.C. Development, Inc., P.O. Box 518, Meridian, ID 83642
Becky McKay, 1029 N. Rosario Street, Suite 100, Meridian, ID 83642
enc.
~Oo G'~
APPROXIMATE IRRIGABLE ACRES
RIVER FLOW RIGHTS - 23,000
BOISE PROJECT RIGHTS -40,000
Machelle Hill
From: Mack Myers <mack@settlersirrigation.org>
Sent: Friday, March 14, 2014 2:05 PM ~1
To: clerk; Bruce Freckleton
Subject: RE: City of Meridian Dev App -Biltmore Sub PP 14-004
The proposed project doesn't impact any Settlers Irrigation District facilities.
Mack Myers
District Manager
Settlers Irrigation District
P.O. Box 7571
Boise, ID 83707
Office 208-343 5271 Fax 208 343-1642
From: Machelle Hill [mailto:mhill@meridiancity.org]
Sent: Wednesday, March 05, 2014 12:48 PM
Subject: City of Meridian Dev App -Biltmore Sub PP 14-004
City of Meridian
~~
~j ~ ~ City Clerk's Office
33 E. Broadway Avenue
Meridian, ID 83642
~~ ~ ~ Planning and Zoning Commission
Development Application Transmittal
To: Outer A encies Comments due b :March 27, 2014
Transmittal Date: March 5, 2014 File No.: PP 14-004
Hearin D ate: A ri13, 2014
Request: Public Hearing: Preliminary Plat approval consisting of 159 single family residential
building lots and 12 common/other lots on 56.19 acres of land in an R-4 zoning
district for Biltmore Subdivision
B L.C. Develo ment, Inc.
Location of Pro a or Pro'ect: South of W. Victo Road and west of S. Meridian Road
The City of Meridian is requesting comments and recommendations on the application referenced above. To review
detailed information about the request, please click on the file number above to take you directly to the application.
We request that you submit your comments or recommendations by date specified above. When responding, please
reference the file number of the project. If responding by email, please send comments to clerkCc~meridiancitV.org.
For additional information associated with this application please contact City Clerk's Office at number below.
Thank you,
Machelle Hill