Pinebridge Subdivision File #TEC-13-004BEFORE THE MERIDIAN CITY COUNCIL C/C JUNE 4, 2013 IN THE MATTER OF THE REQUEST FOR A TWO (2) YEAR TIME EXTENSION ON THE PRELIMINARY PLAT FOR PINEBRIDGE SUBDVISION IN ORDER TO OBTAIN THE CITY ENGINEER'S SIGNATURE ON THE FINAL PLAT, LOCATED IN SECTION 8, T.3N., R.lE, MERIDIAN, IDAHO CASE NO. TEC-13-004 ORDER OF CONDITIONAL APPROVAL OF TIME EXTENSION BY: BW MERIDIAN, INC. APPLICANT This matter coming on regularly before the City Council on June 4, 2013, upon the Applicant's submittal of a preliminary plat time extension application for a two (2) year extension within which to obtain the City Engineer's signature on a final plat for Pinebridge Subdivision, which preliminary plat was originally approved on November 7, 2007, as provided in Unified Development Code § 11-6B-7C, and good cause shown. Two (2) time extensions (TE- 09-015 &TEC-11-002) were previously approved for this subdivision, the last of which expired on May 7, 2013. IT IS HEREBY ORDERED THAT: The above named Applicant is granted an additional two (2) year extended period of time, until May 7, 2015, within which to obtain the City Engineer's signature on a final plat, subject to the conditions of approval as shown in the Staff Report attached as Exhibit A for the hearing date of June 4, 2013, incorporated by reference. ORDER OF CONDITIONAL APPROVAL OF TIME EXTENSION FOR PINEBRIDGE SUBDNISION (FILE #TEC-13-004) Page 1 of 2 Attached: Staff Report for the hearing date of June 4, 2013 By the action of the City Council at its regular meeting on the ~ day of 6. ~~~~ , 2013. DATED this day of , 2013 ~~ A ~'~ Mayor a y de Weerd Copy served upon the Applicant, Planning Department, Public Works Department, and City Attorney. --. ~' BY: 'J` Dated: lQ - ~ q - ~ ~~ ORDER OF CONDITIONAL APPROVAL OF TIME EXTENSION FOR PINEBRIDGE SUBDNISION (FILE #TEC-13-004) Page 2 of 2 EXHIBIT A HEARING DATE: June 4, 2013 (6:00 pm) E IDIAN~-- Marc: TO: Mayor & City Council I D A H O FROM: Sonya Wafters, Associate City Planner SUBJECT: Pinebridge Subdivision -Time Extension (File #TEC-13-004) I. APPLICATION SUMMARY The applicant, BW Meridian, Inc., requests approval of a two year time extension (TEC) on the preliminary plat for Pinebridge Subdivision in order to obtain the City Engineer's signature on a final plat. II. STAFF RECOMMENDATION Staff recommends approval of the subject time extension, until May 7, 2015, with the conditions included in Exhibit B. III. PROPOSED MOTION Approval After considering all Staff, Applicant, and public testimony, I move to approve File Number TEC-13- 004, as presented in the staff report for the hearing date of June 4, 2013. Denial After considering all Staff, Applicant, and public testimony, I move to deny File Number TEC-13- 004, as presented during the hearing on June 4, 2013 for the following reasons: (You must state specific reasons for denial and what the applicant could to do to obtain your approval in the future.) Continuance After considering all Staff, Applicant, and public testimony, I move to continue File Number TEC- 13-004 to the hearing date of (insert continued hearing date here) for the following reason(s): (you should state specific reason(s) for continuance) IV. APPLICATION AND PROPERTY FACTS A. Site Address/Location: The site is located south of E. Fairview Avenue, east of N. Locust Grove Road, west of N. Hickory Avenue, and north of E. Commercial Street, in Section 8, Township 3.N, Range R.IE. B. Owner: BW Meridian, Inc. 250 Beechwood, Ste. 120 Boise, ID 83709 C. Applicant: BW Meridian, Inc. 250 Beechwood, Ste. 120 Boise, ID 83709 D. Applicant's Statement/Justification: Please see applicant's narrative for this information. Pinebridge Sub PP TE (TEC-13-004) Page 1 EXHIBIT A V. UNIFIED DEVELOPMENT CODE (UDC) Per UDC 11-6B-7, approval of a preliminary plat shall become null and void if the applicant fails to obtain the City Engineer's signature on the final plat within two years of the approval of the preliminary plat. Where the development of the preliminary plat is made in successive phases in an orderly and reasonable manner, and conforms substantially to the approved preliminary plat, such segments, if signed by the City Engineer within successive intervals of two years, may be considered for final approval without resubmission for preliminary plat approval. Upon written request and filing by the applicant prior to the termination of the allowed time period, the City Council may authorize a time extension up to two years. With all extensions, the City Council may require the plat to comply with current provisions of the UDC. VI. PROCESS FACTS A. The subject application is for a time extension. A public hearing is required before the City Council on this matter, consistent with Meridian City Code Title 11, Chapter 5. B. Newspaper notifications published on: May 13, and 27, 2013 C. Radius notices mailed to properties within 300 feet on: May 10, 2013 D. Applicant posted notice on site by: May 23, 2013 VII. HISTORY OF PREVIOUS ACTIONS: • This property received preliminary plat (PP-07-008) approval from City Council on November 7, 2007. The preliminary plat consists of 61 building lots and 21 common other lots on 170 +/- acres of land. • An 18-month time extension (TE-09-015) on the preliminary plat to obtain the City Engineer's signature on a final plat was approved by the Director on October 16, 2009. This approval extended the time period in which the applicant had to obtain the City Engineer's signature until May 7, 2011. • A second time extension (TEC-11-002), for 2 years, on the preliminary plat was approved by City Council on May 3, 2011. The approval extended the time period in which the applicant had to obtain the City Engineer's signature until May 7, 2013. VIII. STAFF ANALYSIS This is the third time extension requested for the subject preliminary plat. No final plats have been approved by City Council for this site. Approval of the subject time extension will allow the applicant to proceed with the platting process. If the subject time extension is not granted, the entire property would need to be resubmitted for preliminary plat approval. Since the preliminary plat was approved, some changes have been made to the City's Unified Development Code (UDC) that effect the development of this site as follows: 1) street light standards have changed; 2) a performance surety in the amount of 125% of the total construction cost for all incomplete sewer, water and reuse infrastructure is required to be submitted prior to final plat signature; and 3) a warranty surety in the amount of 20% of the total construction cost for all completed sewer, water and reuse infrastructure for a duration of two years is required. Staff has included new conditions of approval in Exhibit B for the subject time extension based on the above-noted changes to the UDC. All previous conditions for this project are also still in effect. Pinebridge Sub PP TE (TEC-13-004) Page 2 EXHIBIT A V. EXHIBITS A. Drawings 1. Vicinity Map 2. Approved Preliminary Plat B. Conditions of Approval Pinebridge Sub PP TE (TEC-13-004) Page 3 EXHIBIT A Exhibit A.1- Vicinity Map d r a k ~ I` ~ 1, #a~hw~lrrn Pinebridge Sub PP TE (TEC-13-004) Page 4 EXHIBIT A Exhibit A.2 -Approved Preliminary Plat _ _ _ r w ~.:.:~~ ..e. ~~...5~ ~~ Er ~.rr C=£:J ~~~ I~ ~7a! o, Pinebridge Sub PP TE (TEC-13-004) Page 5 EXHIBIT A Exhibit B -Conditions of Approval 1. The applicant is to meet all terms of the approved annexation (AZ-07-006), development agreement (instrument #108022893), rezone (RZ-07-010), preliminary plat (PP-07-008), variance (VAR-07-007), time extensions (TE-09-019; TEC-11-002), and property boundary adjustment (PBA-10-005) for this development. 2. 100 Watt and 250 Watt, high-pressure sodium street lights shall be required on all public roadways per the City of Meridian Improvement Standards for Street Lighting. All street lights shall be installed at developer's expense. Final design shall be submitted as part of the development plan set for approval, which must include the location of any existing street lights. Street lighting is required at intersections, corners, cul-de-sacs, and at a spacing that does not exceed that outlined in the Standards. The contractor's work and materials shall conform to the ISPWC and the City of Meridian Supplemental Specifications to the ISPWC. 3. The City of Meridian requires that the owner post to the City a performance surety in the amount of 125% of the total construction cost for all incomplete sewer, water and reuse infrastructure prior to final plat signature .This surety will be verified by a line item cost estimate provided by the owner to the City. The surety can be posted in the form of an irrevocable letter of credit, cash deposit or bond. Please contact Land Development Service for more information at 887-2211. 4. The City of Meridian requires that the owner post to the City a warranty surety in the amount of 20% of the total construction cost for all completed sewer, water and reuse infrastructure for duration of two years. This surety will be verified by a line item cost estimate provided by the owner to the City. The surety can be posted in the form of an irrevocable letter of credit, cash deposit or bond. Please contact Land Development Service for more information at 887-2211. 5. The applicant shall obtain the City Engineer's signature on a final plat for Pinebridge Subdivision or apply for a time extension in accord with UDC 11-6B-7 prior to May 7, 2015. Pinebridge Sub PP TE (TEC-13-004) Page 6