Standard Form of Agreement with Lurre Const. for Site Work, Utilities, Asphalt Paving~~~=AlA Document A132rN - 2009
Standard Form ofAgreement Between Owner and Contractor,Construction Manager as
Adviser Edifion
Bid Package No.1-Site work, Utilities and Asphalt Paving
_ ADDITIONS AND DELETIONS:
AGREEMENT made as of the Twenty-Forth day of August in the yeaz Two Thousand The author of this document has
Twelve added information needed for Its
(In words, indicate day; month and year) completion. The author may also
have revised the text of the original
BETWEEN the.Owner:- AIA standard form. An Additions and
(Name, legal status, addressand other information) De/etlons Report that notes atldetl
information as well as revisions to the
City of Meddiaa` standard form text is available from
33 East Broadway Avenue the author and should be reviewed. A
Meridian, Idaho 83642 vertical line in the left margin of this
document indicates where the author
and the Contractor: has added necessary information
(Name, legal status, address,and other information) and where the author has added to or
deleted from the original AIA text.
Lurre ConstrOCtion, InC:. This document has important legal
5306 Badiola-Street consequences. Consultation with an
Caldwell, Idaho 83605''' attorney is encouraged with respect
Telephone Number: 208-459-8624 to Its completion or modification.
FaxNumber: 208-459-9661
This document is intended to be used
for the following Project: in conjunction with AIA Documents
*"
A232
-2009, General Conditions of
(Ngme, locah'on and detailed descripu'on) the Contract for Construction,
Construction Manager as Adviser
Meridian Pazks,& Recreation Maintenance Facility Edition; B132T"-2009, Standard
.1700 East Lanark Street Form of Agreement Between Owner
IVleridian,Idaho:83642 and Architect, Construction Manager
'. as Adviser Edition; and
The ConstructionManager:.. C132Tn-2009, StantlaM Form of
(Name, legal status, address and other information) Agreement Between Owner and
Construction Manager as Adviser.
Kreizenbeck, LLC DBA Kreizenbeck Constructors,
11724 West Executive Drive AIA Document A232Ta-2009 Is
Boise
Idaho 83713 adapted in this document by
, reference. Do not use with other
Telephone Number: (208) 336-9500 general conditions unless this
Fax Number:.(208) 336-7444 document is modified.
The Architect::.
(Name, legal status, address and other information)
Insight Architects, P.A.
2238 South Broadway Avenue
Boise; Idaho 83706
.Telephone Number: (208) 338-9080
The Owner and Contractor agree as follows.
AIA Document A132*"' - 2009 rfarrnarly A701 T'"CMa -19921. Copyright ®1975, 1980, 1992 antl 2009 by The American InsStule of Arohilecls. All rights
Init. reaervetl. WARNING: This AIAm Document la protactatl by U.S. Capydght Law antl International Treatlea. Unauthodzetl reproduction or tllstrlhutlon of
this AIA® Document, or any portion of It, may result In severe civil and cdminel penalties, and will ha prosecuted to the maximum extent posalhle under
/ the law. This document was produced by AIA software et 10:06:01 on 09!29!2012 under Order No.5907428800_1 which expires on 01/17/2013, and is not for
resale.
User Notes: (1265979709)
TABLE OF ARTICLES
T:' THE CONTRACT DOCUMENTS
2 THE WORK OF THIS CONTRACT
3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
4 CONTRACT SUM
5- PAYMENTS -
'6 DISPUTE RESOLUTION
7 TERMINATION OR SUSPENSION
8 MISCELLANEOUS PROVISIONS
9 ENUMERATION'AF'CONTRACTDOCUMENTS
70 INSURANCE AND!BONDS
ARTICLE 1 THE CONTRACT DOCUMENTS
The Contract Documentsconsist ofthis Agreement, Conditions of the Contract (General, Supplementary and other
Conditions), Drawings, Specifications, Addenda issued prior to execution ofthis Agreement, other documents listed
in thisAgreementand-Modifications issued after execution ofthis Agreement, all of which form the Contract, and are
as fully a part of the Contract as,f attached to this Agreement or repeated herein. The Contract represents the entire
-and integrated agreement tietween the parties hereto and supersedes prior negotiations, representations oragreements,
either written or oral. An enumeration of the Contract Documents, other than Modifications, appears in Article 9.
ARTICLE 2 THE WORK OF THIS CONTRACT
The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in
the ConttactDocuments to be the responsibility of others.
Bid Requirements: Provide all labor, material, equipment and permits to complete the Site clearing,
Earthwork, Utilf6esand Asphalt paving as noted on the construction documents and per the following:
Section'.311000 -Site Clearing
Section 312000 - Eartli Idoving
Section 321216 -Asphalt Paving
Section 321313 -Site Concrete Paving*
Section 331100- Site Domestic Water Distribufion
Section 331300- Site Sanitary Sewer
Section 334100 -- Storm Drainage & Gravity Irrigation
**As applicable to this scope of work
This contract specifically includes but is not limited to:
• Provide all site demolition and site clearing in accordance with the construction documents. This includes saw cutting,
removal of asphalt, removal of fencing, and removal of vegetation.
Strip, remove and haul all top soil off site as required in accordance with the censtructlon documents.
• Perform all cu[ / fdl operations and bring site to proper sub grades. Provide, place and compact all structural fill as
needed. Sub grade tolerances shall be as noted in the construcfion documents (net = 0) and excess materials appropriately
disposed off -site.
• Haul all unsuitable materials off site in accordance with construction documents.
• Maintain, protect and repair existing surfaces and utilities which are to remain.
• Construct building pads to proper sub grade elevations + or - .10 (net =0).
• Provide excavation, nenching and backfill for work within this work package.
• Provide and install dewatering systems as required to complete work for this work package.
AIA Document A132Ta - 2009 formerly A101 ^"CMe-1882). Copyright®7975, 7900, 1992 and 2009 by The American Institute of Arohilects. All rights
Inlt. reserved. WARNING: Thla AIA Document la protected by U.S. Copyright Law entl Intarnallonal Treatlee. Unauthorizetl reprotluctlon or tllatrlbutlon of
thla AIA® Document, or any portion of It, may result In severe clvll antl criminal penaltlea, antl will he proaecutetl to the maximum extent poaelble antler
/ the law. This document was produced by AIA software at 10:08:01 on 00/20/2012 under Order No.5907420000_1 which expires on 01117/2013, end is not for
resale.
User Notes: (1265970700)
• Provide excavation and backfill for all site concrete. Include backfill to proper sub grades around all site concrete
including but not limited to sidewalks and trash enclosure.
•' `Provide and place aggregate base for all site concrete and asphalt paving as indicated by consrtuction documents.
.Aggregate base under concrete shall be + or - .10 (net =0).
• Provide excavation and backfill for all building concrete. This includes the trash enclosure.
• Provide and place aggregate base for all building sUUClures wncrete slab on grades as indicated by the construction
documents. Aggregate base under concrete shall be + or - .10 (net = 0).
• Provide imported topsoil, place and rough grade to specified depths. Topsoil to be+ or - .10 (nett).
• Construct temporary access pad around building. Pad shall extend 20' from exterior foundation wall around entire
perimeter of building. Access pad shall consist of 12" of 6" minus pit run. Top of 12" section shall be al sub Bade
elevations.
• Include repair and grading for all pit run azeas exposed over winter prior to landscaping (topsoil placement), asphalt
paving and concrete activities.
• Set storm drains to collect water through winter, raise when storm drains when completing'/< grading in spring.
• Provide and placepit run, aggregate base and asphalt paving per construction documents. Provide patching of existing
asphaltas necessary to. complete all work noted in this work package.
• Saw: cut clean lines for riew asphalt edges abutting soft materials.
• Placerecycled asphalt per the construction documems. (Recycled asphalt is owner furnished and currently stocked piled
on site).
• Provide final clean upof existing recycled asphalt stock pile area. (Native seeding by landscape).
- Provide and place!alI Integral curb and gutters and valley gutters as indicated on the construction dmwings including
providing and placing'/a" base gravel under curbs, gutters, valley gutters.
Provide striping for all asphalt and concrete paving as indicated. Include all painted symbols and stencils.
'. Provide and install all exterior post and panel signs. Include excavalion, backfill, concrete footings, poles and signs.
• Finnish and install a complete domestic water service line as indicated in the construction documents. Stub water service
line to witfiin Y of building. This includes, but not limited to, fire hydrants and meter setter assemblies.
•. Furnish and installs'complete sanitary sewer system as indicated inthe wnstruction documents. Smbsewer line to within
55 of buildtng.Thisincludes the 4" sewer to the Flammable Liquid Interceptor.
• Furnish andinsfalla complete storm drainage system as indicated in the construction documents. This includes roof drain
-inlet catch basins. '.
• Furnish and installa'mmplete gravity Irrigation system as indicated by the construction documents. Make all necessary
- modifications to. ezisfing gravity irrigation and surfaces to complete the installation.
• Coordinate the natural gas line and installation with Intermountain Gas Company.
• Furnish and install all concrete related to utility work in this bid package. This includes wnaete collazs.
• Provide all labor and materials for weather protection as required for this work package.
Provide and maintain all erosion and wnrtol and SWPPP requirements for this scope of work in accordance with the
construction documents. Monitor and maintain until final stabilization is in place. This includes street sweeping and dust
controlas itporlains to this scope while on site.
Contractor: toprovide all water require to complete work operations under this work package. Water is not available on
-site.
• ladludeall applicable permits and fees required to complete work within this work package, including RO. W. permits.
• Provide traffic centrol asrequired for all work within this work package.
• Civil drawing elevations are based upon sea level datum. Architectural and srtuchual drawings are based on finish floor
equal4o 100.
• Include a $25,000 allowance in the base bid to be used at the sole discretion of the Construction Manager.
• Provide all survey work required for this work package. Surveyor to be registered in the Stake of Idaho. Reference
Instructions to bidders book -Construction Facilities and Temporary Controls for survey provided by Construction
Manager.
• Scope ofthework remains the same for all buildings identified in the construction documents.
• Scopeof work--.for alternates remains the same as base bid (as applicable).
• Provide, install, maintain, and remove (I) additional stabilized construcfion entrance. Location to be determined by
canstructionmanager.
This contract specifically excludes:
• Site Furnishings
• Underslab vapor barrier and rigid insulation.
• 1500'Gallon Flammable liquid Interceptor and back side piping to build.
• Wash bay curb by others.
• Site Sidewalks.
AIA Document A132ra-2009 formedy A101r"CMa-1992). Copyright®1975,1880, 7892 end 20096y Tha American Institute of Architects. All rights
Init. reaervetl. WARNING: 7hla AIA Document Is protected by U.S. Copyright Law and International Trestles. Uneuthodzed reproduction or dletrlbutlon of
thla AIA® Document, or any portion of Il, may result in severe civil and crlminel penalties, antl will he prosecuted to the maximum extent poselhle under
/ the law. This document was produced by AIA sofhvere et 70:08:01 on 08/28/2012 under Order No.5907428900_1 which expires on 01/17/2013, antl Is notfor
resale.
User Notes: (1285978708)
ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
§ 3.1 The date of commencement of the Work shall be the date of this Agreement unless a different date is stated
- - below or provision is made for the date to be fixed in a notice to proceed issued by the Owner.
(Insert the date of commencement, if it differsfrom the date of this Agreement or, if applicable, state that the date will
be fixed in a notice to proceed.)
h' The' commencement date will be fixed in a notice to proceed.
If, prior to the commencement of the Work, the Owner requires fime to file mortgages, mechanics' liens and other
security interests, the Owner's time requirement shall be as follows:
§ 3.2 The Contract Time'shall be measured from the date of commencement.
§ 3!3 The Contractor shalladhieve Substantial Compleflon of the entire Work not later than ( )days from the date
of commencement, or as follows:
dJJ (InserGnamber of calendar days. Alternatively, a calendar date may be used when coordinated with the date of
commencement. 7f appropriate, insert requirements for earlier Substantial Completion of certain portions of the
Work)
The Contractor shttll'actiieve>Substantial Completion of the entire Work not later than May 3Q, 2013.
(Table deleted)°;'"
subjectlto adjustments of this Contract Time as provided in the Contract Documents.
(Insert provisions, if any, for liquidated damages relating to failure to achieve Substantial Completion on time orfor
bonus payments for early completion of the Wark)
Ixr the event the Contractor, without excuse, fails to achieve Substantial Completion within the Contract Time, the
Contractor shall pay tothe Owner as liquidated damages, and not as a penalty, the sum of One Thousand Dollars
($1,000.00) or''/a%ofthe Contract Value (whichever is greater) for each and every calendar day following the end of
the Contract Timeuntil=Substantial Completion is achieved; provided that the Contractor shall not be liable for
liquidated damages for a'day, or days of the excusable de]ay occurring during such period following the end of the
Contmcf:Time.
ARTICLE 4'1-.CONTRACT SUM
§.. 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor's performance of the
'Contract. The Contract Sum shall be one ofthe following:
(Check the appropriate box.)
[ X ] Stipulated Sum, in accordance with Section 4.2 below
[ ] Cost of the Work plus the Contractor's Fee without a Guaranteed Maximum Price, in accordance
.with Section 4.3 below
[ ]' Cost of the Work plus the Contractor's Fee with a Guaranteed Maximum Price, in accordance with
Section 4.4 below
(Based an the selection above, complete Section 4.2, 4.3 or 4.4 below. Based an the selection above, also complete
either Section 5.1.4, 5.1.5 or 5.1.6 below)
§ 4.2 Stipulated Sum
§ 4.2.1 The Stipulated Sum shall be Four Hundred Eighty-Seven Thousand Five Hundred Dollars and Zero Cents ($
487,500.00 ), subject to additions and deletions as provided in the Contract Documents.
Base Bid $487,500.00
AIA Document A132T"'-2009 formerly A101T°CMa -1992). Copyright ®1975, 1980, 1992 end 2009 by The Amedcen Institute of Architects. All rights
Init. reaervetl. WARNING: This AIA Document is protected by U.S. Copyright Lew and Intarnetlonel Traetlea. Unauthorizetl reprotluctlon or dletrlbutlon of 4
this AIA® Document, orany portion of It, may result In severe civil antl crtminal penalties, end will ba prosecuted to the maximum extent poaelhle antler
y the law. This document was produced by AIA software at 10:06:07 on OB/28/2012 under Order No.5907428600_1 which expires on 01/17/2013, and is not for
resale.
User NOtea: (126597B70B)
§ 4.2.2 The Stipulated Sum is based on the following alternates, if any, which are described in the Contract Documents
and`':are hereby accepted by the Owner:
(State thee. numbers or other idenhftcation of accepted alternates. lithe bidding orproposal documentspermitttie
Owner to accept other alternates subsequent to the execution of this Agreement, attach a schedule of such other
alternates showing the amount for each and the date when that amount expires.)
~ N/A
: § 4.2.3 Unitprices, if arty:.
(identify and state the.-untprice, and state the quantity limitations, if arty, to which the unltprice wit[ be applicable.)
Item< Units and Llmitatlons Price per Unit ($0.00)
§ 4.2.4 Allowances included iithe Stipulated Sum, if any:
(Identify allowance and state :exclusions, if arty, from the allowance price.)
Item:' Allowance
§' 4!3 Cost ofthe Work Plus Contractor's Fee without a Guaranteed Maximum Price
4:3.1 The Contract Sum is the Cost of the Work as defined in ExhibitA, Determination of the Cost of the Work, plus
the Contractor's'Fee.
§ 4.3.2 The Contractor's Fee:
(State a lump sum, percentage of Cost of the Work or other provision for determining the Contractor's Fee.J
§; :4.3.3 The method of adjustment of the Contractor's Fee for changes hr the Work:
§ 4.3.4 Limitations, if any, on a Subcontractor's overhead and profit for increases in the cost of its portion of the Work:
§ 4.3.5 Rental rates for Contractor-owned equipment shall not exceed percent ( %) of the standard rate paid at the
place of the]?roject.
§ 4.3.6 Unit prices, if any:
(Identify and state the unitprice;`state quantity limitations, if any, to which the unit price will be applicable.)
Item
Units and Limitations Price per Unit ($0.00)
§ 4.3.7 The Contractor shall prepare and submit to the Construction Manager for the Owner, in writing, a Control
Estimate withinl4 days of executing this Agreement. The Control Estimate shall include the items in Section A.1 of
Exhibit A, Determination of the Cost of the Work.
§ 4.4 Cost of 'the Work Plus Contractor's Fee with a Guaranteed Maximum Price
§' 4'.4:1 The Contract Sum is the Cost of the Work as defined in Exhibit A, Determination of the Cost of the Work, plus
the Contractor's Fee.
§ 4.4.2 The Contractor's Fee:
(State a Zump sum, percentage of Cost of the Work or other provision for determining the Contractor's Fee.)
AIA Document A102T'"-2009 formerly A707'^'CMa-1992). Copyright ®1975, 1980, 1992 and 2009 by The American Institute of Architects. All rlghta
Init. reserved. WARNING: This AIA Document la prolectetl by U.S. Copyright Law antl International Trestles. Unauthorizatl reproduction or tllatrlbutlon of
this AIA® Document, orany portion of It, may result In severe clvll and crlminal penaltlas, antl will be prosecuted to the maximum extant poaelble under
t the law. This document was producetl by AIA software a110:06:01 on 08/28/2012 under Order No.5907426800_7 which expires on 01/17/2013, end is not for
resale.
User NOtea: (1285978708)
§ 4.4.3 The method of adjustment of the Contractor's Fee for changes in the Work:
§=4:4.4 Limitations, if any, on a Subcontractor's overhead and profit for increases in the cost of its portion ofthe Work:
§ 4.4.5 Rental rates for Contractor-owned equipment shall not exceed percent ( %) of the standard rate paid at the
place of the: Project.
-.-'§-- 4:4.6 Unit Prices, if any:
(Identify and state thee. unit price, and state the quantity limitations, if arty, to which the unit price will be applicable.)
Item Units and Limitations Price per Unit ($0.00)
§ 4.4.7 Guaranteed-Maximum Price
§ 4,4.7.1 Thesum ofthe Costofthe Work and the Contractor's Fee is guaranteed by the Contractor not to exceed ($
subject to additions and deductions by changes in the Work as provided in the Contract Documents. Such maximum
sum is referred'4o in the Con&act Documents as the Guaranteed Maximum Price. Costs which would cause the
`Guaranteed Maximum Price to be exceeded shall be paid by the Contractor without reimbursement by the Owner.
(Insert specific provisions if the Contractor is to participate in arty savings.)
§ 4.4.7.2 The Guaranteed`Maximum Price is based on the following alternates, if any, which are described in the
~~~d.CoritracfDocumentsand are hereby accepted by the Owner:
§ 4.4.7.3 Allowances included in the Guaranteed Maximum Price, if any:
(Identfy and state the amounts of arty allowances, and state whether they include labor, materials, or both.)
Jtem Allowance
§ 4.4.7.4 Assumptions, if any, on which the Guaranteed Maximum Price is based:
ARTICLE''5 PAYMENTS
§ 5.1 Progress Payments
§ 5:1.1 Based upon Applications for Payment properly submitted to the Construction Manager by the Contractor, and
upon certification of the Project Application and Project Certificate for Payment or Application for Payment and
Certificate for Payment by the Construction Manager and Architect and issuance by the Architect, the Owner shall
make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the
Contract Documents.
§ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the
month, or as follows:
AIA Document A102TM- 2009 (formerly A701T'"CMa-1992). Copyrlght ®1975, 1980, 1992 antl 2009 by The Amadcen Institute of Architects. All rights
Init. reaervatl. WARNING: Thla AIA® Document la protected by U.S. Copyrlght Law and Intemetlonel Trestles. Uneuthodzed reprotluctlon or tllatrtbutlon of
thla AIA® Document, or any portion of It, may result In severe clvll antl crlminal penaltlaa, antl will be prosecuted to the mexlmum eztant poaslble antler
t the law. This document was produced by AIA software al 10:06:01 on 06/28/2012 antler Order No.5907426800 1 which expires on 01!17/2013, and is not for
resale.
User Notes: (1265976706)
§ 5.1.3 Provided that an Application for Payment is received by the Construction Manager not later than the
Twenty-fifth day of a month, the Owner shall make payment of the certified amount in the Application for Payment to
the Contractor not later than the Twenty-fifth day of the following month. If an Application for Payment is received
by the Construction Manager after the application date fixed above, payment shall be made by the Owner not later than
Thirty (30) days after the Constmction Manager receives the Application for Payment.
(Federal, slate or local laws may require payment within a certain period of rime.)
§5a:4Progress Payments Where the Contract Sum is Based on a Stipulated Sum
„§ , 5.1.4.1 Each Application for Payment shall be based on the most recent schedule of values submitted by the
'Contractor and approved. in writing by the Construction Manager and Architect in accordance with the Contract
Documents. The schedule ofvalues shall allocatethe entire Contract Sum among the various portions ofthe Work and
be prepared in such form and supported by such data to substantiate its accuracy as the Construction Manager and
.Architect may requii'e.Tliis schedule, when, and only when, approved hr writing by the Construction Manager or
Architect,: shall be usedas a basis for reviewing the Contractor's Applications for Payment.
§--:5.1.4.2 Applications for Payment shall show the percentage of completion of each porton of the Work as of the end
of the period`coveredby the Application for Payment.
`':§ 5';1'.4;3 Subject to the provisions ofthe ContractDocuments, the amount ofeach progress payment shall be computed
as follows:
~ .1 Take that portion of the Contract Sum properly allocable to completed Work as determined by
.2
.3
.4
.5
multiplying the. percentage completion of each portion of the Work by the share of the total Contract
Sum allocated to that portion of the Work in the approved schedule of values, less retainage of Five
percent (',5:00%). Pending final determination of cost to the Owner of changes in the Work, amounts
not in-.dispute may be included as provided in Section 7.3.9 of the General Conditions, as modified;
Add thatportion of the Contract Sum properly allocable to materials and equipment delivered and
suitably stored at the site for subsequent incorporation in the completed construction (or, if approved in
writing in advance by the Owner, suitably stored off the site at a location agreed upon in writing), less
retainage of Five percent (5.00 %);
Subtract the aggregate of previous payments made by the Owner;
Subtract amounts, if any, for which the Construction Manager or Architect has withheld or nullified a
Certificate for Payment as provided in Section 9.5 of the General Conditions, as modified; and
Subtract amounts, if any, being withheld by the Owner or Constmction Manager as provided in the
Contract Documents.
§ 5.1.4.4 The progress payment amount determined in accordance with Section 5.1.4.3 shall be further modified under
the following circumstances: -
.1 Add, upomSubsfahtial-Completion of the Work, a sum sufficient to inaease the total payments to
Ninety-five pei•cenf( 95.00 %) of the Contract Sum, less such amounts as the Consruction Manager
recommends and the Architect determines for incomplete or defective Work, or both and unsettled
claims; and
.2 Add, iffinal completion of the Work is thereafter materially delayed through no fault ofthe Contractor,
any additional amounts payable in accordance with Section 9.10.3 of the General Conditions, as
modified.
§ 5.1.4.5 Reduction or limitation of retainage, if any, shall be as follows:
(If it is intended, prior to Substantial Compleuion of the entire Wor/c, to reduce or limit the retainage resultingfrom the
percentages inserted in Sections 5.1.4.3.1 and 5.1.4.3.2 above, and this is not explained elsewhere in the Contract
Documents, insert here provisions for such reduction or limitation.)
No reductiorrin-retainage will be allowed prior to final completion without written approval of the Owner.
§ 5:1:4.6 A condition will be included forbidding more retainage from a contractor or supplier than retained from their
portion of the Work.
AIA Document A772T"`-2008 formerly A101 T°CMa -1992). Copyright ®7975, 7980, 1982 end 2009 by The American Institute of Architects. All rlghta
Init. reserved. WARNING: This AIA Document la protected by U.S. Copyright Lew end International Treatise. Unauthorizetl reprotlucllon or tlletdbution of
this AIA® Document, or any portion of it, may result in severe civil and criminal peneltles, and will be proaecutad to the maximum extent possible under
y the law. This document was producetl by AIA software at 10:06:01 on 08/20/2072 under Order No.5907426600_1 which expires on 01/77/2073, and is not for
resale.
User NOtes: (1265978708)
§ 5.1.5 Progress Payments Where the Contract Sum is Based on the Cost of the Work without a Guaranteed
Maximum Price
§'S.1[5:1'With each Application for Payment, the Contractor shall submit the cost wntrol information required in
.Exhibit A; Determination of the Cost of the Work, along with payrolls, petty cash accounts, receipted invoices or
ihvoides'with check vouchers attached and any other evidence required by the Owner, Construction Manager or
Architect to demonstrate that cash disbursements already made by the Contractor on account of the Cost of the Work
equal or exceed (1) progress payments already received by the Contractor; less (2) that portion of those payments
attributable to the Contractor's Fee; plus (3) payrolls for the period covered by the present Applicaton for Payment.
§'--_ 5.1.5.2 Applications forPayment shall show the Cost of the Work actually incurred by the Contractor through the
end of the period coveredby the Application for Payment and for which the Contractor has made or intends to make
actualpaymentpriontothenextApplicaflonforPayment.
§ 5.1.5.3 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be
computed as follows:
.1 Take the Cost of the Work as described in Exhibit A, Determination of the Cost of the Work;
.2 Add the Conhactor's Fee, less retainage of percent ( %). The Contractor's Fee shall be computed
upon the Cost of the Work described in that Section at the rate stated in that Section; or if the
Contractor's Fee is stated as a fixed sum, an amount which bears the same ratio to that fixed-sum Fee as
the Cost of the Work bears to a reasonable estimate of the probable Cost of the Work upon its
completion;'
.3 Subtract retainage of percent ( %) from that portion of the Work that the Contractor self-performs;
.4 Subtract the aggregate of previous payments made by the Owner;
.5 Subtract the shortfall, if any, indicated by the Contractor in the documentation required by Article 5 or
resultingfrom errors subsequently discovered by the Owner's auditors in such documentation; and
.6 Subtract amounts, if ang for which the Construction Manager or Architect has withheld or withdrawn a
Certificate for,Payment as provided in Section 9.5 of AIA Document A232T"'-2009, General
Conditionsof the Contract for Construction, Construction Manager as Adviser Edition.
§'5.1.5.4 The Owner, Construction Manager and Contractor shall agree upon (1) a mutually acceptable procedure for
reviewand approval of payments to Subcontractors and (2) the percentage of retainage held on Subcontracts, and the
Contractor shall execute subcontracts inaccordance with those agreements.
§ 5.1.5.5 11t taking action on the Contractor's Applications for Payment, the Construction Manager and Architect shall
be entitled to rely ottthe accuracy and completeness of the information furnished by the Contractor and shall not be
deemed to represent that the Construction Manager and Architect have made a detailed examination, audit or
arithmefic verification of the documentation submitted in accordance with Article 5 or other supporting data; that the
'CottstructionManager and Architect have made exhaustive or continuous on-site inspections; or that the Construction
Manager and'.Architectheve madekxaminations to ascertain how or for what purposes the Contractor has used
amounts previously paid on acwunt of the Contract. Such examinations, audits and verifications, if required by the
Owner, will be performed'bythe Owner's auditors acting in the sole interest of the Owner.
§ 5.1.5.6 Except with the Owner's prior approval, the Contractor shall not make advance payments to suppliers for
materials or equipment which have not been delivered and stored at the site.
§.5.1.6Pragress Payments Where the Contract Sum is Based on the Cost of the WGrk with a Guaranteed
Maximum Price
§ 5.1.6.1 With each Application for Payment, the Contractor shall submit payrolls, petty cash accounts, receipted
invoices.. or invoices with check vouchers attached, and any other evidence required by the Owner or Architect to
demonstrate that cash disbursements already made by the Contractor on account of the Cost of the Work equal or
exceed (1) progress payments already received by the Contractor; less (2) that portion of those payments attributable
to tlteContractor's Fee; plus (3) payrolls for the period covered by the present Application for Payment.
§ 5.1.6.2 Each Application for Payment shall be based on the most recent schedule of values submitted by the
Contractor in accordance with the Contract Documents. The schedule ofvalues shall allocate the entire Contract Sum
among the various portions of the Work and be prepared in such form and supported by such data to substantiate its
AIA Document A702Ta -2008 formerly A701T°CMa-1992). Copydghl ®1975, 1980, 1892 and 2009 by The American InstiNle of Architects. All rights
Init. reserved. WARNING: This AIA Document le protected by U.S. Copydght Law antl Intarnatlanel Treatise. Uneuthodzed reproduction or dletdbution of
this AIA® Document, or any portion of It, may result In severe civil and criminal penalties, and will be prosecuted to the maximum extent poael6le antler
) the law. This document was produced by AIA software a110:06:01 on 09/28!2012 under Order No.5907428800_1 which expires on 01/17/2013, and is not For
resale.
User Notes: (1265978708)
accuracy as the Construction Manager and Architect may require. This schedule, unless objected to by the
Construction Manager or Architect, shall be used as a basis for reviewing the Contractor's Applications for Payment.
§ 5.1:6:3 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end
of the period covered by the Application for Payment. The percentage of completion shall be the lesser of (1) the
percentage of that portion of the Work which has actually been completed; or (2) the percentage obtained by dividing
(a) tlis expense that has actually been incurred by the Contractor on account of that portion of the Work for which the
- `Contractor has made or intends to make actual payment prior to the next Application for Payment by (b) the share of
the Guaranteed Maximum Price allocated to that portion of the Work in the schedule ofvalues.
§ 5.1.6.4 Subject to other provisions of the Contract Documents, the amount of each progress payment shall be
computed as;8ollows:
.1 Take that portion of the Guaranteed Maximum Price properly allocable to completed Work as
determined by multiplying the percentage of completion of each portion ofthe Work by the share of the
Guaranteed Maximum Price allocated to that portion of the Worlc in the schedule of values. Pending
final determination of cost to the Owner of changes in the Work, amounts not in dispute shall be
included as-provided in Section 7.3.10 of AIA Document A232-2009;
:2 Add that portion of the Guaranteed Maximum Price properly allocable to materials and equipment
delivered and suitably stored at the site for subsequent incorporation in the Work, or if approved in
advance by the Owner, suitably stored off the site at a location agreed upon in writing;
.3 Add the Contractor's Fee, less retainage of percent ( %). The Contractor's Fee shall be computed
upon the Cost of the Work at the rate stated in Section 4.4.2 or, if the Contractor's Fee is stated as a
fixed sum in that Section, shall be an amount that bears the same ratio to that fixed-sum fee as the Cost
of the Workbears to a reasonable estimate of the probable Cost of the Work upon its completion;
.4 : Subtract retaihage of percent ( %) from that portion of the Work that the Contractor self-performs;
.5.. Subtract the'aggregate of previous payments made by the Owner;
.6 ` Subtract'the_sltortfall, if any, indicated by the Contractor in the documentation required by Section
5:1:6.1 tosubstantiate prior Applications for Payment, or resulting from errors subsequently discovered
by the Owner's auditors in such documentation; and
',7 Subtract amounts, if any, for which the Construction Manager or Architect have withheld or nullified a
Certificate for Payment as provided in Section 9.5 of AIA Document A232-2009.
§ .5.1.6.5 The Owner. and the Contractor shall agree upon a (1) mutually acceptable procedure for review and approval
of payments to Subcontractors and (2) the percentage of retainage held on Subcontracts, and the Contractor shall
executesuticontracts in accordance with those agreements.
§ ,5.1.6.67In taking''action on the Contractor's Applications for Payment, the Construction Manager and Architect shall
be entitled to rely on the accuracy.. and completeness of the information furnished by the Contractor and shall not be
deemed to represent thatthe Construction Manager or Architect have made a detailed examination, audit or arithmetic
verification of the documentation submitted in accordance with Section 5.1.6.1 or other supporting data; that the
Construction Manager orArchitect have made exhaustive or continuous on-site inspections; or that the Construction
Manager or Architect havemade examinations to ascertain how or for what purposes the Contractor has used amounts
previously paid on account of the Contract. Such examinations, audits and verifications, ifrequired by the Owner, will
be performed by the Owner's auditors acting in the sole interest of the Owner.
§ 5.1.6.7 Exceptwith the Owner's prior approval, the Contractor shall not make advance payments to suppliers for
materials or equipmentwhich have not been delivered and stored at the site.
§ 5.2 Final Payment
§ 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the
Contractor when
:1 the Contractor has fully performed the Contract except for the Contractor's responsibility to correct
Work as provided in Section 12.2 of ATA Document A232-2009 as modified, and to satisfy other
requirements, if any, which extend beyond final payment;
.2 the Contractor has submitted a final accounting for the Cost of the Work, pursuant to Exhibit A,
Determination of the Cost of the Work when payment is on the basis of the Cost of the Work, with or
without a Guaranteed Maximum payment; and
AIA Document A102TM - 2008 formerly A701 T'"CMa-1882). Copydght ®1975, 1980, 7992 and 2009 by Tha Amedcen Insgtute of Architects. All rights
Init. reserved. WARNING: This AIA Document la protected by U.S. Copyright Law and International Treatlea. Unauthodzed reproduction or tlletrlbutlon of
thle AIA® Document, or any portion of It, may result In severe civil and criminal penalties, and will he prosecuted to the maximum extent poaslble under
/ the law. This document was predated by AIA software at 10:06:01 on 08/28/2012 under Order No.5907426800 1 which expires on 01/77/2019, and Is net/or
resale.
User Notes: (1285878798)
.3 a final Certificate for Payment or Project Certificate for Payment has been issued by the Architect such
final payment shall be made by the Owner not more than 30 days after (1) the Contractor has fully
performed the Contract and (2) the issuance of the final Certificate for Payment or Project Certificate
for Payment, or as follows:
ARTICLE 6 DISPUTE RESOLUTION
§ 6.1 Initial Decision Maker
The Architect will serveas Initial Decision Maker pursuant to Section 15.2 of AIA Document A232-2009 as
modified, unless the parties appoint below another individual, not a party to this Agreement, to serve as Initial
Decision Maker.
(Lf the parties mutually agree, insert the name, address and other contact informah'an of the Initial Decision Maker, if
other than the Arohitect)
§ 6.2 Binding-.Dispute Resolution
For any Claim subject to, but+not resolved by, mediation pursuant to Section 15.3 ofAIA Document A232-2009 as
modified; the method of binding dispute resolution shall be as follows:
(Check the appropriate bar. If the Owner and Contractor do not select a method of binding dispute resolution below,
or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims will be
resolved by liri'gatiodin a court of competentjurisdicticn.)
[ ].- ...Arbitration pursuant to Section 15.4 of AIA Document A232-2009.
[ X ],. Litigation irr.. a court of competent jurisdiction.
[ ] Other:: (Spec fy)
ARTICLE 7 TERMINATION OR SUSPENSION
§ 7.1 Where the ContracPSum is a Stipulated Sum
,. § .7.1.1 The Contract maybe terminated by the Owner or the Contractor as provided in Article 14 of AIA Document
' -A232-2009 as modified.
§ 71.2 They Work may be suspended by the Owner as provided in Article 14 of AIA Document A232 2009 as
modified:
§ 7.2 Where the Contract Sum is Based on the Cost of the Work with or without a Guaranteed Maximum Price
§ 7:2.1 '. Subjecftothe provisions of Section 7.2.2 below, the Contract may be terminated by the Owner or the
Contractor asprovided in-....Article 14 of AIA Document A232-2009.
§,, 7.2.2 The Contract maybe terminated by the Owner for cause as provided in Article 14 of AIA Document
'A232-2009; however, the Owner shall then only pay the Contractor an amount calculated as follows:
.7 Take the Cost of the Work incurred by the Contractor to the date of termination;
.2 Add the Contractor's Fee computed upon the Cost of the Work to the date of termination at the rate
.stated in Sections 4.3.2 or 4.4.2, as applicable, or, if the Contractor's Fee is stated as a fixed sum, an
'..amount that bears the same ratio to that fixed-sum Fee as the Cost of the Work at the time of
' termination bears to a reasonable estimate of the probable Cost of the Work upon its completion; and
.3 Subtractthe aggregate of previous payments made by the Owner.
§ 7.2.3 If the Owner terminates the Contract for cause when the Contract Sum is based on the Cost of the Work with a
Guaranteed Maximum Price, and as provided in Article 14 of AIA Document A232-2009, the amount, if any, to be
-!paid to the Contractor under Section 14.2.4 of AIA Document A232-2009 shall not cause the Guaranteed Maximum
Price to'be exceeded, nor shall it exceed the amount calculated in Section 7.2.2.
§ 7.2.4 The Owner shall also pay the Contractor fair compensation, either by purchase or rental at the election of the
Owner, for any equipment owned by the Contractor that the Owner elects to retain and that is not otherwise included in
the Cost of the Work under Section 7.2.1. To the extent that the Owner elects to take legal assignment of subcontracts
and purchase orders (including rental agreements), the Contractor shall, as a wndition of receiving the payments
AIA Document A732TM-20091formerly A101T"'CMa-19921. Copyright®7975, 1960, 1992 antl 2008 by The American Instltule of Architects. All rlghta
Inrt• reserved. WARNING: This AIA& Document la protected by U.S. Copyrl0ht Law and International Treaties. Unaulhodzed reproductlan or dlatdbutlon of ~D
thla AIA® Document, or any portion of It, may result In severe clvll and crlminal penalties, antl will be prosecuted to the maximum extant poaslhle antler
t the law. This document was produced by AIA software at 10:06:01 on 09!2612012 under Order No.5907426800_1 which expires on 01/77/2013, antl is not for
resale.
User Notes: (1265979709)
referred to in this Article 7, execute and deliver all such papers and take all such steps, including the legal assignment
of such subcontracts and other contractual rights of the Contractor, as the Owner may require for the purpose of fully
vesting in'the Owner the rights and benefits of the Contractor under such subcontracts or purchase orders.
§'--T3.5 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A232-2009; in such
case„the Contract Sum and Contract Time shall be increased as provided in Section 14.3.2 of AIA Document
A232-2009, except that the term 'profit' shall be understood to mean the Contractor's Fee as described in Sections
43312 and 4.4.2 of this Agreement.
ARTICLE 8 MISCELLANEOUS PROVISIONS
§ 8:1 Whereaeference is made in this Agreement to a provision of AIA Document A232-2009 as modified or another
Contract Document, the reference refers to that provision as amended or supplemented by other provisions of the
Contract Documents.
§-8.2 Payments due and unpai8 under the Contract shall bear interest from the date payment is due at the rate stated
below, or iii_tlte absence thereof, at the legal rate prevailing from time to time at the place where the Project is located.
(Insert rate of interest agreed upon, if arry.)
3/4 of 1% per month
§ 8.3 The Owner's representative:
(Name, address and!ather information)
Keith Watts, Purchasing Manager
Ciry;ofMeridian
Purchasing Department'
33 East Broadvvay!Avenue
Meridian, Idaho'83642
§ 8.4 The Contractor's representative:
(Name, address and other information)
Kris Jensen
Lurre Construction, Inc.
306 Badiola-Street
Caldwell, IdahoS3605
Telephone Number: 208-459-8624
:Fax Number: 208-459-9661
§ 8.5 Neither the Owner's nor the Contractor's representative shall be changed without ten days written notice to the
other parry.
§ 8:6 Other provisions:
ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS
§ 9.1 The Contract Documents, except for Modifications issued after execution of this Agreement, are enumerated in
the sections below.
§ 9.1.1 The Agreement is this executed AIA Document A132-2009 as modified, Standard Form of Agreement
Between Owner and Contractor, Construction Manager as Adviser Edition.
§ 9.1.2 The General Conditions are, AIA Document A232-2009 as modified, General Conditions of the Contract for
Construction, Construction Manager as Adviser Edition.
§ 9.1.3 The Supplementary and other Conditions of the Contract:
AIA Document AL 32*a - 2009 formerly A101 T"CMa -1882). Copydghl ®1975, 1960, 1992 end 2009 by Tha Amedcen Institute of Amhllacrs. All rights
Init. reservetl. WARNING: This AIA Document la protected by U.S. Copyright Law and Internetlonel Trestles. Unauthorized reproduction or dlatrlbutlon °f 11
thla AIA® Document, or any portion of It, may result In severe clvll end cdminal peneltlee, and will he proaecutetl to the maximum extent poselble under
t the law. This document was produced by AIA software at 10:08:01 on 06/26/2012 under Order No.5907426600 1 which expires on 01/17/2013, and is not for
resale.
User Notes: (1265970706)
Document Title Date Pages
I" " Exhibit A Contract Document Schedule 8/23/2012 2
§ 9.1.4 The Specifications:
(Either list the Specifications here or refer to an exhibit attached to this Agreement)
Contract Document Schedule, Exhibit A, dated August 23, 2012
(Table deleted)
§ 9:1.5 The Drawings;,.''
(Either list the Drawings here ar refer to an exhibit attached to this Agreement)
~, ?-_ Contract Document Schedule, Exhibit A, dated August 23, 2012
(Table deleted)
§ .9:1.6 The Addenda, if any:
Number Date Pages
One 8/10/2012 24
Two 8/17/2012 432
Portions ofAddenda relating tobidding requirements are not part of the Contract Documents unless the bidding
equirements are also enumerated in this Article 9.
§':9:1.7 Additional documents, if any, forming part of the Contract Documents are:
.1 AIA Document A132TM-2009, Exhibit A, Determination of the Cost of the Work, if applicable.
.2 AIA Document E201TM-2007, Digital Data Protocol Exhibit, if completed, or the following:
~ N/A
.3 AIA Document E202TM-2008, Building Information Modeling Protocol Exhibit, if completed, or the
following:..'.
N/A
.4 Otherdocuments, if any, listed below:
(Lsthere arty additional documents which are intended to form part of the Contract Documents. AIA
Document A232 2009 provides that bidding requirements such as adverh'sement or invitation to bic~
Instructions to Bidders, sample forms and the Contractor's bid are notpart of the Conh•act Documents
unless enumerated'ih this Agreement They should be listed here only if intended to be part of the
Contract Documents.)
All bindingdocuments including the Invitation to Bid, Instructions to Bidders, Supplemental
Instructions-to Bidders, Bid Proposal Forms, and the Project Schedule are intended to be part of the
- -Contract Documents.
AIA Document A232-2009 General Conditions
ARTICLE 10 INSURANCE AND BONDS
The Contractor shall purchase and maintain insurance and provide bonds as set forth in Article 11 of AIA Document
A232-2009 as modified
Referto.Supplemental Conditions modifying AIA Document A232-2009 for changes and additions to Article 11
"Insurance and Bonds".
Contractor is required to provide 100%Payment and Performance Bonds.
(State bonding reguirements, if any, and limits of liability for insurance required in Ark'cle 11 ofA7A Document
A232-2009.)
AIA Document A732T"'- 20091formerly A707 T"'CMa-1992). Copyright ®1975, 1880, 1992 end 2009 by The American Ins0lule of Architects. All rights
Init. reservetl. WARNING: This AIA® Document le protected by U.S. Copyright Law antl Intarnatlonal Trestles. Unauthodzed reproduction or dlatributlon of 12
this AIA® Document, or any portion of It, may result In severe civil and criminal penaltlea, end will be proaeculetl to the maximum extant poaelhle under
t the law. This document was produced by AIA software at 10:06:01 on 08!26/2012 under Order No.5907420900_1 which expires on 01/7712013, and is not for
resale.
User Notes: (1266976706)
Type of Insurance or Bond Limit of Liability or Bond Amount ($0.00)
This Agreement is entered into as of the day and year first written above.
.' `~~,,,
~~~..~.
OWNER (Si re) T TOR (Signature)
Tammy de Weerd ,Mayor ,,~,,~~~ ~~~~~~` ~`~~~ S r •.~~~~
(P~inted name and title) (Printed name and title)
AIA Document A132T"' - 2009 formerly A101 T"'CMa -1992). Copyright ®1975,1980,1992 and 2009 by The American Institute of Architects. All rights
Init. reserve ®. WARNING: This AIA Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of 13
this AIA Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under
~ the law. This document was produced by AIA software at 10:06:01 on 08/2812012 under Order No.5907428800_1 which expires on 01/17/2013, and is not for
resale.
User Notes: (1265978708)
CONTRACT DOCUMENT SCHEDULE (EXHIBIT A)
Meridian Parks & Recreation Maintenance Facility
1700 East Lanark Street
Meridian, Idaho 83642
KC PROJECT NO. 12-021
August 23, 2012
PROJECT DOCUMENTS as issued by Insight Architects and prepared by the following project
team:
Architect -Insight Architects
Structural Engineer-AHJ Engineers
Mechanical and Plumbing Engineer -Musgrove Engineering, P.A.
Electrical Engineer- DC Engineering
Civil Engineer -Erickson Civil
Landscape Architect -South Landscape Architecture, P.C.
PROJECT MANUALS
Instructions to Bidders -Part 1, Complete -Dated July 30, 2012
Project Manual Part 2, Complete -Dated July 30, 2012
ADDENDA:
Addendum No. One dated August 10, 2012 (24 pgs)
Addendum No. Two dated August 17, 2012 (432 pgs)
DRAWINGS
COVER -Dated 713112 0 1 2
A0.1 Cover Sheet
ARCHITECTURAL SITE PLAN -Dated 7/31/2012
A1.0 Site Plan A1.1
CIVIL -Dated 7 /3 012 0 1 2
C1.0 Cover Sheet /Notes C1.1
C2.0 Grading & Drainage Plan -Overall C2.1
C2.2 Grading & Drainage Plan -Area 2 C2.3
C2.4 Roadway Plan & Profile - E. Nola Rd. C3.0
C3.1 Sewer Plan & Profile C3.2
C4.0 Site & Grading Details C4.1
C4.2 Irrigation Details C4.3
C4.4 City of Meridian Standard Details -2 C5.0
C5.1 Stormwater Pollution Prevention Plan - 2
LANDSCAPE -Dated 7/31/2012 or as indicated below
L1.0 Landscape Cover Sheet L2.0
L2.1 Landscape Plan L3.0
L3.1 Irrigation Plan (dated 7/18/2012) L4.0
ARCHITECTURAL -Dated 7/31/2012
BLD -A
A2.OA Overall Floor Plan A2.1A
A2.2A Floor Plan Shop B & C A2.3A
A3.OA Reflected Ceiling Plan A4.OA
A5.OA Exterior Elevations A6.OA
Meridian Parks & Recreation Maintenance Facility
Page 1 of 2
Site Details
Topographic & Control Survey
Grading & Drainage Plan-Area 1
Roadway Plan & Profile - E. Lanark St.
Site Utility Plan
Gravity Irrigation Plan & Profile
Site, Drainage, and Irrigation Details
City of Meridian Standard Details - 1
Stormwater Pollution Prevention Plan -1
Landscape Plan
Landscape Plan (dated 7/16/2012)
Irrigation Details (dated 7118/2012)
Floor Plan Office /Shop A
Floor Plan Shop D
Roof Plan
Building Sections
Augusl23, 2012
A6.1A Wall Sections A6.2A Wall Sections /Details
A7.OA Interior Elevations /Details A6.0 DoodWindow Schedule & Details
Ag.O Details/Energy Compliance
BLD - B
A2.OB Floor/Roof Plans A3.OB Exterior Elevations
BLD - C
A2.OC Floor/Roof Plans A3.OC Exterior Elevations /Sections
A3.1C Wall Sections /Details
BLD-D
A2.OD Floor/Roof Plans A3.OD Exterior Elevations /Sections
STRUCTURAL -Dated 713112012
51.0 Structural General Notes 51.1 Special Inspections
S2.OA Foundation Plan Bld A S2.OB Foundation Plan Bld B
S2.OC Foundation /Roof Framing Plan Bld C S2.OD Foundation /Roof Framing Plan Bld D
S3.OA Roof Framing Plan Bld A 54.0 Structural Details -Foundation
S5.0 Structural Details-Framing
MECHANICAL -Dated 7/30/2012
MG1.0 Mechanical Cover MG1.1 Mechanical Energy Compliance
M1.0 HVAC Plan -Main Building M1.1 HVAC Plan -Building C
M2.0 HVAC Details M3.0 HVAC Schedules
PLUMBING -Dated 7/30/2012
P1.0 Plumbing Plan - Building A P1.1 Plumbing Plan -Building C
P2.0 Plumbing Details P3.0 Plumbing Schedules
ELECTRICAL -Dated 7/3012012
E0.0 Electrical Cover Sheet E0.1 Site Electrical Plan
E0.2 Electrical Roof Plan E1.0 Power Plan -Building A
E1.1 Power Plans -Building B, C, & D E2.0 Lighting Plan -Building A
E2.1 Lighting Plans -Building B, C, & D E3.0 One Line Diagram and Panel Schedules
E4.0 Lighting Controls & Compliance
Meridian Parks & Recreation Maintenance Facility August 23, 2012