CDBG Follow-UpCDBG Follow-Up
Meridian City Council
March 24, 2009
Agenda Item 7.B.1
Last Week’s Priorities
Centennial Park
Façade Improvements
Five Mile Creek Pathway
Community Center
McFadden Market
Sidewalks
Proposed Direction
CDBG Stimulus Funds ($64,584)
Centennial Park Improvements
Requires Survey for Eligibility
Timeline:
Survey: Complete by mid-August
Project: Mid-late Fall, 2009
Proposed Direction
“Left-Over” Funds from 2007 ($84,342)
Five Mile Creek Pathway Design
Total Design Cost: $40,000
Timeline: Target Fall for Design Completion
Community Center, ADA Upgrades
Total Cost: $20,000
Timeline: Target End of July for Completion
Public Services
Total Expenditure: $24,000
Services: CATCH, Backpacks for Kids, Food Bank
Proposed Direction
Program Year 2009 Allocation ($240,000)
Five Mile Creek Pathway Construction
Construction Cost: $150,000 - $350,000
Possible Phased Construction (if necessary)
Façade Improvements
Total Amount: TBD
Others
Public Services, LMI Emphasis
2009 Action Plan Complete in July
Funds Available in October, 2009
Proposed Direction
April 7: Public Hearing Comment Periods
2007 Action Plan Amendment
For Pathway Design, ADA Upgrades, & Public Services
2008 Action Plan Amendment
For Centennial Park Improvements
April – June: Staff Drafts 2009 Action Plan
July: City Adopts 2009 Action Plan
August: City Forwards 09’ Plan to HUD