May 2, 2008
To: Insight Architects, P.A.
2238 Broadway Ave.
Boise, ID 83706
Subject: MCZC-08-039
Aire Storage Building
2021 E. Wilson Ln.
Carol A. McKee, President
Sherry R. Huber, 1st Vice President
Dave Bivens, 2nd Vice "President
John S. Franden, Commissioner
Rebecca W. Arnold, Commissioner
~~~~IV~~
MAY 0 6 2008
EITY OF MERIDIAN
CITY CLERK OFFICE
In response to your request for comment, the Ada County Highway District (ACRD) Planning Review
staff has reviewed the submitted application and site plan for the item referenced above. It has been
determined that there are no site specific requirements for you at this time due to the fact that all
required roadway improvements currently exist.
If the site plan or use should change in the future, ACRD Planning Review will review the site plan
and may require improvements to the transportation system at that time.
Prior to final approval you will need to submit construction plans to the ACRD Development Review
Department to insure compliance with the conditions identified above or for traffic impact fee
assessment. This is a separate review process that requires direct plans submittal to the
Development Review staff at the Highway District.
A traffic impact fee will need to be assessed by ACRD and will be due prior to the issuance of a
building permit. Contact ACRD Planning 8~ Development Services at 387-6170 for information
regarding impact fees.
Prior to the construction or installation of any roadway improvements (curb, gutter, sidewalk,
pavement widening, driveways, culverts, etc), a permit or license agreement must be obtained from
ACRD.
If you have any questions, please feel free to contact me at (208) 387-6174.
Sincere
arrod
Planner I
Right-of-Way and Development Services
CC: Project file
City of Meridian
Aire Fi2NR, LLC
Ada County Highway District • 3775 Adams Street • Garden City, ID • 83714 • PH 208-387-6100 • FX 345-7650 • www.achd.ada.id.us
Development Process Checklist
~Submlt a development application to a City or to the County
®The City or the County will transmit the development application to ACHD
®The ACRD Planning Review Division will receive the development application to review
®The Planning Review Division will do one of the following:
Send a "No Review" letter to the applicant stating that there are no site specific requirements at this time.
^Send a "Comply With" letter to the applicant stating that if the development is within a platted subdivision or part of a
previous development application and that the site specific requirements from the previous development also apply to this
development application.
^Write a Staff Level report analyzing the impacts of the development on the transportation system and evaluating the
. proposal for its conformance to District Policy.
^Write a Commission Level report analyzing the impacts of the development on the transportation system and
evaluating the proposal for its conformance to District Policy.
®The Planning Review Division will hold a Technical Review meeting for all Staff and Commission Level reports.
^For ALL development applications, including those receiving a "No Review" or "Comply With" letter:
The applicant should submit one set of engineered plans directly to ACHD for review by the Development Review Division for plan
review and assessment of impact fees. (Note: if there are no site improvements required by ACHD, then architectural plans may be
submitted for purposes of impact fee calculation.)
The applicant is required to get a permit from Construction Services (ACHD) for ANY work in the right-of-way, including, but not limited to,
driveway approaches, street improvements and utility cuts.
^Pay Impact Fees prior to issuance of building permit. Impact fees cannot be paid prior to plan review approval.
DID YOU REMEMBER:
Construction (Zone)
^ Driveway or Property Approaches)
Submit a "Driveway Approach Request" form to Ada County Highway District (ACHD) Construction (for approval by Development
Services & Traffic Services). There is a one week turnaround for this approval.
^ Working in the ACHD Right-of-Way
Four business days prior to starting work have a bonded contractor submit a "Temporary Highway Use Permit Application" to ACRD
Construction -Permits along with:
Traffic Control Plan
An Erosion & Sediment Control Narrative & Plat, done by a Certified Plan Designer, if trench is >50' or you are placing >600 sf of
concrete or asphalt.
Constnrction (Subdivisions)
^ Sediment & Erosion Submittal
At least one week prior to setting up a Pre-Con an Erosion & Sediment Control Narrative & Plat, done by a Certified Plan Designer,
must be turned into ACHD Construction -Subdivision to be reviewed and approved by the ACRD Drainage Division.
^ Idaho Power Company
Vic Steelman at Idaho Power must have his IPCO approved set of subdivision utility plans prior to Pre-Con being scheduled.
^ Final Approval from Development Services
ACRD Construction -Subdivision must have received approval from Development Services prior to scheduling aPre-Con.
Ada County Highway District • 3775 Adams Street • Garden. City, ID • 83714 • PH 208-387-6100 • FX 345-7650 • www.achd.ada.id.us