April 7, 2022
Mr. Warren Stewart, PE
City of Meridian
33 E. Broadway Ave.
Meridian, ID 83642
RE: Aviator Springs Subdivision
Street Centerline Elevation Certification PN 120194
Dear Mr. Stewart:
As required by the City's final plat application requirements, please accept this statement certifying that
all street finish centerline elevations are set a minimum of three (3)feet above the highest established
normal groundwater elevation.
According to the initial test pit investigations and recent groundwater monitoring,the groundwater
within this project was not encountered within a depth of three (3)feet of the existing ground.
Based on the above information, I certify that groundwater would be greater than three (3)feet below
the designed finished street centerline elevations throughout the project.
Sincerely, ,OVAL EN
THE LAND GROUP, INC. ��5G\S G
James W. Gute, PE ,
Principal, Project Civil Engineer 68
04/07/2022