Ameriprise Shell Building - DES, CZC - A-2020-0052
CERTIFICATE OF ZONING COMPLIANCE
REPORT
DATE:
March 10, 2020
TO:
Jason Tomlinson – Tomlinson Design
FROM:
Joseph Dodson, Current Associate Planner
SUBJECT:
Ameriprise Shell Building - DES, CZC (A-2020-0052)
Joe Richardson
OWNER:
DESCRIPTION OF APPLICANT'S REQUEST
The applicant, Jason Tomlinson, requests Certificate of Zoning Compliance (CZC) and Design
Review (DES) approval for a new shell building for office use in an existing business park in
the L-O zoning district on .20 acres of land.
The site is located at 413 Sw. 5th Avenue.
DECISION
The applicant's request for Certificate of Zoning Compliance and Design Review is approved
with the conditions listed in this report.
Note: This is not a building permit. Please contact Building Services at (208) 887-2211 to
verify if you need a building permit and/or inspection. If you do need a building permit, you
must complete that process before you commence the use or construction. Please contact
Building Services for additional details about building permits and inspections.
General Conditions of Approval
1. Provide a Fire Department Key Box entry system for the complex prior to occupancy as
set forth is International Fire Code, Section 506.
2. Water Modeling Review – At the time of building permit submittal, the Applicant must
show either a connection to or abandonment of the existing water stub at the southeast
corner of property. Water plan must be reviewed with building permit submittal; any
infrastructure changes must be reviewed by Public Works.
Site Conditions of Approval
1. The applicant shall construct all proposed fencing and/or any fencing required by the
UDC, consistent with the standards as set forth in UDC 11-3A-7 and 11-3A-6B.
2. Business hours of operation within the L-O and C-N districts shall be limited from 6 am
to 10 pm as set forth in UDC 11-2B-3A4.
Process Conditions of Approval
1. No signs are approved with this application. Prior to installing any signs on the property,
the applicant shall submit a sign permit application consistent with the standards in
UDC Chapter 3 Article D and receive approval for such signs.
2. The applicant shall complete all improvements related to public life, safety, and health
as set forth in UDC 11-5C-3B. A surety agreement may be accepted for other
improvements in accord with UDC 11-5C-3C.
Conditions Document
2
Ameriprise Shell Building - DES, CZC - A-2020-0052
3. Upon installation of the landscaping and prior to inspection by Planning Division staff,
the applicant shall provide a written certificate of completion as set forth in UDC 11-
3B-14A.
4. The site plan prepared by Tomlinson Design on January 20, 2020, labeled Site Plan, is
approved by the City of Meridian Planning Division as shown in Exhibit B.
5. The landscape plan prepared by Tomlinson Design on January 20, 2020, labeled
Landscape Plan, is approved by the City of Meridian Planning Division as shown in
Exhibit C.
6. The elevations prepared by Tomlinson Design on January 20, 2020, labeled Exterior
Elevations, are approved by the City of Meridian Planning Division as shown in Exhibit
D.
7. The approved site plan, landscape plan and/or elevations may not be altered without
prior written approval of the City of Meridian Planning Division.
8. The applicant shall pay any applicable impact fees prior to the issuance of a building
permit.
9. If any changes must be made to the site plan to accommodate ACHD requirements, the
applicant shall submit a new site plan to the City of Meridian Planning Division for
approval prior to issuance of the building permit.
10. The applicant shall complete all required improvements prior to issuance of a Certificate
of Occupancy. It is unlawful to use or occupy any building or structure until the
Building Official has issued a Certificate of Occupancy.
11. If applicable, The City of Meridian requires that the owner enter into a Warranty Surety
Agreement and post a Warranty Surety in the amount of 20% of the total construction
cost for all completed public sewer and water infrastructure for a duration of two years.
This surety amount will be verified by a line item final cost invoicing provided by the
owner to the City. The surety can be posted in the form of an irrevocable letter of credit,
cash deposit or bond, and must be in place prior to Certificate of Occupancy. Applicant
must file an application for surety, which can be found on the Community Development
Department website. Please contact Land Development Services for more information at
208-887-2211.
Ongoing Conditions of Approval
1. The applicant and/or assigns shall have the continuing obligation to provide irrigation
that meets the standards as set forth in UDC 11-3B-6 and to install and maintain all
landscaping as set forth in UDC 11-3B-5, UDC 11-3B-13 and UDC 11-3B-14.
2. The project is subject to all current City of Meridian ordinances and previous conditions
of approval associated with this site: PP-05-022; CUP-05-030; SHP-15-003 (Newton’s
Nook Subdivision No. 4).
3. The issuance of this CZC does not release the applicant from any previous requirements
of the other permits issued for the site.
4. The applicant and/or property owner shall have an ongoing obligation to prune all trees
to a minimum height of six feet above the ground or sidewalk surface to afford greater
visibility of the area.
5. The applicant has a continuing obligation to comply with the outdoor lighting provisions
as set forth in UDC 11-3A-11.
6. The applicant and/or property owner shall have an ongoing obligation to maintain all
landscaping and constructed features within the clear vision triangle consistent with the
standards in UDC 11-3A-3.
Conditions Document
3
Ameriprise Shell Building - DES, CZC - A-2020-0052
CITY COUNCIL REVIEW
The applicant or a party of record may request City Council review of a decision of the
Director. All requests for review shall be filed in writing with the Planning Division on or
before March 25, 2020, within fifteen (15) days after the written decision is issued, and contain
the information listed in UDC 11-5A-6B.
If City Council review of the decision is not requested, the action of the Director represents a
final decision on a land use application. You have the right to request a regulatory taking
analysis under Idaho Code 67-8003.
EXPIRATION
The Certificate of Zoning Compliance shall expire if the construction, alteration or the use has
not commenced within one year of the date of issuance of the Certificate of Zoning
Compliance.
In accord with the above provisions, the subject Certificate of Zoning Compliance is valid until
March 11, 2021.
EXHIBITS
A: Vicinity Map
B: Site Plan (dated: January 20, 2020)
C: Landscape Plan (dated: January 20, 2020)
D: Elevations (dated: January 20, 2020)
Conditions Document
4
Ameriprise Shell Building - DES, CZC - A-2020-0052
Exhibit A: Vicinity Map
Conditions Document
5
Ameriprise Shell Building - DES, CZC - A-2020-0052
Exhibit B: Site Plan (dated: January 20, 2020)
Conditions Document
6
Ameriprise Shell Building - DES, CZC - A-2020-0052
Exhibit C: Landscape Plan (dated: January 20, 2020)
Conditions Document
7
Ameriprise Shell Building - DES, CZC - A-2020-0052
Exhibit D: Elevations (dated: January 20, 2020)