CC - Site Development Timeline Updated Ada County Highway District — Ustick Maintenance Facility Schedule of Improvements and Trip Generation Phase 1 - FY2021 • Start site preparation, grading, excavation of internal access roadways and installation of fencing • One (1) employee hired • No trip generation Phase 2 — FY2022 • Complete site preparation, grading, excavation of internal access roadway and installation of fencing • Deceleration lane installation on Ustick Road at Naomi Avenue • Improvement of the north leg of Naomi Avenue • Improvement of internal access roads • Installation of Ustick Road and Naomi Avenue landscape buffers • Material storage on the site • Ten (10) employees hired for a total of 11 employees • No trip generation • Design of Ustick Road widening from Ten Mile Road to Black Cat Road Phase 3 — FY2023 • Construction of Covered Decant Facility (6 months) —Approximately 4,500 S.F. • Ten (10) employees hired for a total of 21 employees; however, they will not be stationed out of the subject site. • Once the decant facility is constructed it will be utilized, and we are estimating the following: o Two to three (2-3) sweepers utilizing the decant two to three (2-3) times a day — when the units are working in the area o Two (2) Vactor drainage trucks utilizing the decant 2-3 times a day—when the units are in the area o 20 trips per day with 3 trips in the PM peak hour. These trips will become ancillary trips once crews are stationed out of the subject site. o Right-of-way acquisition for Ustick Road widening Phase 4— FY2024 • Construction of Broom Shed — 12,800 S.F. • Construct Drainage Shed —7,850 S.F. • Covered Material Storage— Salt Shed 13,800 S.F. • Covered Storage Areas—42,182 S.F. • Parking Areas • Ten (10) employees hired for a total of 31, but not all will be operating out of the subject site. • Four(4) additional sweepers will be added to the fleet • Construction of the Ustick Road widening from Ten Mile Road to Black Cat Road with completion in 2024. • Total trips generated with proposed improvements in Phase 4 — 103 trips per day with 13 trips in the PM peak hour. Operation of the above improvements will not take place until completion of the Ustick Road project. Phase 5—FY2025 • Construction of Fleet Buildings (shop, weld shop and parts warehouse) - 11,900 S.F. • Ten (10) employees hired for a total of 41 —Sweeper operators working off-site. • 59 trips per day with 8 trips in the PM peak hour Phase 6— FY2026 • Construction of the Administration Building —4,500 S.F. • Ten (10) employees hired for a total of 51, all employees will be operating out of the subject site. • 22 trips per day with 3 trips in the PM peak hour Phase 7 — FY2027 • Construct Truck Wash and Truck Bays— 1,820 S.F. • Six (6) employees hired for a total of 56— Drainage Vactor truck operators working out of the subject site. • No new trips — ancillary use Phase 8 — FY2028 • Finishing of remaining internal improvements and covered parking. • Five (5) employees hired for a total of 61 that will be operating out of the subject site.