Direct Orthopedic Care -Sawtooth Physical Therapy - DES CZC A-2020-0213 Final
Page 1
DATE: 12/18/2020
TO: Jason Smith, AIA
FROM: Alan Tiefenbach, Associate Planner
208-884-5533
SUBJECT: A-2020-0213
Direct Orthopedic Care -Sawtooth
Physical Therapy - DES, CZC
LOCATION: 4842 N Cortona Way
I. PROJECT DESCRIPTION
Certificate of Zoning Conformance (CZC) and Design Review (DES) to construct 10,455 sq. ft.
orthopedic care building (healthcare and social service use) in the L-O Zoning District. This property
is governed by Development Agreement Inst. 108059800. Professional services are an allowed use by
the development agreement and the L-O Zone District. The proposed site plan is consistent with the
concept plan reflected on the development agreement.
II. DECISION
The applicant's request for Certificate of Zoning Compliance and Administrative Design Review
(DES) is approved with the conditions listed in this report.
Note: This is not a building permit. Please contact Building Services at (208) 887-2211 to verify if
you need a building permit and/or inspection. If you do need a building permit, you must complete
that process before you commence the use or construction. Please contact Building Services for
additional details about building permits and inspections.
Site Specific Conditions of Approval
1. The applicant shall construct all proposed fencing and/or any fencing required by the UDC,
consistent with the standards as set forth in UDC 11-3A-7 and 11-3A-6B.
2. The business hours of operation shall be limited to 6am to 10pm in the L-O district as set forth by
UDC 11-2B-3B.
CERTIFICATE OF ZONING
COMPLIANCE REPORT
COMMUNITY DEVELOPMENT DEPARTMENT
Page 2
3. No signs are approved with this application. Prior to installing any signs on the property, the
applicant shall submit a sign permit application consistent with the standards in UDC Chapter 3
Article D and receive approval for such signs.
4. The applicant shall complete all improvements related to public life, safety, and health as set forth
in UDC 11-5C-3B. A surety agreement may be accepted for other improvements in accord with
UDC 11-5C-3C.
5. All off street parking areas shall be provided with a substantial wheel restraint to prevent cars
from encroaching upon abutting private and public property or overhanging beyond the
designated parking stall dimensions as required by 11-3C-5.
6. Upon installation of the landscaping and prior to inspection by Planning Division staff, the
applicant shall provide a written certificate of completion as set forth in UDC 11-3B-14A.
7. The site plan prepared by KM Engineering on December 8, 2020, labeled Site Plan, is approved
by the City of Meridian Planning Division as shown in Exhibit A.
8. The landscape plan prepared by Office of Architecture and Design on December 8, 2020, labeled
Landscape Plan is approved by the City of Meridian Planning Division as shown in Exhibit B.
9. Existing landscaping at the west and south boundaries shall be protected and maintained during
construction activities.
10. The elevations prepared by Office of Architecture and Design on December 14, 2020, labeled
Building Elevations, are approved by the City of Meridian Planning Division as shown in Exhibit
C.
11. The approved site plan, landscape plan and/or elevations may not be altered without prior written
approval of the City of Meridian Planning Division.
12. The applicant shall pay any applicable impact fees prior to the issuance of a building permit.
13. If any changes must be made to the site plan to accommodate ACHD requirements, the applicant
shall submit a new site plan to the City of Meridian Planning Division for approval prior to
issuance of the building permit.
14. The applicant shall complete all required improvements prior to issuance of a Certificate of
Occupancy. It is unlawful to use or occupy any building or structure until the Building Official
has issued a Certificate of Occupancy.
15. The City of Meridian requires that the owner enter into a Warranty Surety Agreement and post a
Warranty Surety in the amount of 20% of the total construction cost for all completed public
sewer and water infrastructure for a duration of two years. This surety amount will be verified by
a line item final cost invoicing provided by the owner to the City. The surety can be posted in the
form of an irrevocable letter of credit, cash deposit or bond, and must be in place prior to
Certificate of Occupancy. Applicant must file an application for surety, which can be found on
the Community Development Department website. Please contact Land Development Services
for more information at 208-887-2211.
16. 100 Watt and 250 Watt, high-pressure sodium street lights shall be required on all public
roadways per the City of Meridian Improvement Standards for Street Lighting. All street lights
shall be installed at developer’s expense. Final design shall be submitted as part of the
development plan set for approval. Applicant shall also include the location of any existing street
lights in the development plan set. Street lighting is required at intersections, corners, cul-de-sacs,
and at a spacing that does not exceed that outlined in the Standards. The contractor’s work and
materials shall conform to the ISPWC and the City of Meridian Supplemental Specifications to
the ISPWC.
Page 3
General Conditions of Approval
1. The applicant and/or assigns shall have the continuing obligation to provide irrigation that meets
the standards as set forth in UDC 11-3B-6 and to install and maintain all landscaping as set forth
in UDC 11-3B-5, UDC 11-3B-13 and UDC 11-3B-14.
2. The project is subject to all current City of Meridian ordinances and previous conditions of
approval associated with this site [DA Inst. 108059800 and Verona Subdivision No 4 Plat FP-08-
010.].
3. The issuance of this CZC does not release the applicant from any previous requirements of the
other permits issued for the site.
4. The applicant and/or property owner shall have an ongoing obligation to prune all trees to a
minimum height of six feet above the ground or sidewalk surface to afford greater visibility of the
area.
5. The applicant has a continuing obligation to comply with the outdoor lighting provisions as set
forth in UDC 11-3A-11.
6. The applicant and/or property owner shall have an ongoing obligation to maintain all landscaping
and constructed features within the clear vision triangle consistent with the standards in UDC 11-
3A-3.
III. CITY COUNCIL REVIEW
The applicant or a party of record may request City Council review of a decision of the Director. All
requests for review shall be filed in writing with the Planning Division on or before January 1, 2021,
within fifteen (15) days after the written decision is issued, and contain the information listed in UDC
11-5A-6B.
If City Council review of the decision is not requested, the action of the Director represents a final
decision on a land use application. You have the right to request a regulatory taking analysis under
Idaho Code 67-8003.
IV. EXPIRATION
The Certificate of Zoning Compliance shall expire if the construction, alteration or the use has not
commenced within one year of the date of issuance of the Certificate of Zoning Compliance.
In accord with the above provisions, the subject Certificate of Zoning Compliance is valid until
December 18, 2021.
Page 4
V. EXHIBITS
A. Site Plan (date: 12/8/2020)
Page 5
B. Landscape Plan (date: 12/8/2020)
Page 6
C. Building Elevations (date: 12/14/2020)
Page 7