Loading...
Email from Applicant RE sidewalksFrom:Carpenter, John To:Sonya Allen; James Doolin Subject:Entrata Date:Tuesday, February 25, 2020 2:15:35 PM Attachments:image001.png image002.png image003.png image004.png image005.png image006.png Hi Sonya, We are going to have the site plan to you shortly. I took a harder look at the sidewalk at Franklin and Entrata - that has a gap. The sidewalk would be really steep if connected – greater than 10%. That was the reasoning for not connecting them. The sidewalk along Franklin is connected all of the way through. The sidewalks adjacent to the public streets were constructed last November – they are all in. Hope you are having a great day, John G. Carpenter, P.E. | Project Manager/Nampa Office Manager 332 N. Broadmore Way | Nampa, Idaho 83687 O 208-442-6300 | C 208-442-6300 www.to-engineers.com