The Oaks South Subdivision No 7 DEQ Approval Letter��E/N
DIAN>--
January 09, 2018
Mr. Aaron Scheff
IDEQ Boise Regional Administrator
1445 N. Orchard Street
Boise, Idaho 83706
Re: Project Approval - Oaks South Subdivision No 7
Mayor Tammy de Weerd
City Council Members:
Keith Bird Joe Borton
Luke Cavener Genesis Milam
Ty Palmer Anne Little Roberts
Per the provisions in Idaho Code § 39-118(2)(d), the City of Meridian has retained the services of
Keller associates .as its Qualified Licensed Professional Engineer (QLPE), to verify that the plans and
specifications proposed for the above -referenced project comply with the IDEQ Facility and Design
Standards (IDAPA 58.01.16 and 58.01.08) and the applicable Meridian standards, and to approve the
project for construction. By virtue of their attached letter, they have reviewed and approved the
above referenced plans and specifications as complying with the Facility and Design Standards, and
Engineering Standards of Care as it relates to the reviewed elements. This approval shall expire one
year from the date of this letter. If construction has not commenced by the expiration date, plans must
be resubmitted for review and approval before construction may proceed.
The above referenced project complies with the City of 's current Wastewater Facility Plan, and
Sewer Master Plan, and our system has adequate capacity to accept sewage wastes for treatment.
These determinations have been made by use of computer models developed for our Sewer Master
Plan. This project is also within the City's urban service planning boundary. Our Domestic Water
distribution system can provide water service and the minimum required fire flow (1000 GPM) and
the minimum required residual pressure of 20 PSI. These determinations have been made by use of
computer models developed for our Water Master Plan.
The City of Meridian will own and operate the wastewater collection and domestic water distribution
systems within this project upon final inspection and acknowledgement by formal acceptance letter.
In essence, the City of Meridian "Will Serve" the project.
Attached for your records is a complete and accurate copy of the plans and specifications reviewed in
connection herewith, stamped "Approved for Construction."
Sincerely,
Warren Stewart, P.E.
Engineering Manager
Public Works Department . 33 E. Broadway Avenue, Suite 200 . , ID 83642
Phone 208-898-5500. Fax 208-898-9551 . www.meridiancity.org