Fairbourne Subdivision Off-Site Sewer DEQ Approval LetterEIDIAN,-
IDAH_ /
February 27, 2018
Mr. Aaron Schcff'
IDEA B'on'e Regional Administrator
1445 N. Orchard Street .
Boise Idaho 83706
Re: Project Approval - Fairbourne Subdivision - OFFSITE SEWER
Mayor Tammy de Weerd
City Council Members:
Joe Borton Genesis Milam
Ty Palmer Luke Cavener
Treg Bernt Anne Little Roberts
Per the provisions in Idaho Code § 39-118(2)(d), the City of Meridian has retained the services of Keller
associates as its Qualified Licensed Professional Engineer (QLPE), to verify that the plans and
specifications proposed for the above -referenced project comply with the IDEQ Facility and Design
Standards (IDAPA 58.01.16 and 58.01.08) and the applicable Meridian standards, and to approve the
project for construction. By virture of their attached letter, they have reviewed and approved the above
referenced plans and specifications as complying with the Facility and Design Standards, and
Engineering, Standards of Care as it relates to the reviewed elements. This approval shall expire one year
from the date;of.this letter. If construction has not commenced by the expiration date, plans must be
resubmitted for review and approval before construction may proceed.
The above referenced project complies with the City of Meridian's current Wastewater Facility Plan, and
Sewer Master Plan, and our system has adequate capacity to accept sewage wastes for treatment. These
determinations have been made by use of computer models developed for our Sewer Master Plan. This
project is also within the City's urban service planning boundary. The domestic water distribution system
for this project is within the Suez service area as defined by the service agreement between the City of
Meridian and Suez dated February 19th, 2007.
The City of Meridian will own and operate the wastewater collection system within this project upon
final inspection and acknowledgement by formal acceptance letter. In essence, the City of Meridian
"Will Serve" the project.
Attached for your records is a complete and accurate copy of the plans and specifications reviewed in
connection herewith, stamped "Approved for Construction."
Warren Stewart, P.E.
Engineering Manager
Public Works Department . 33 E. Broadway Avenue, Suite 200 . , ID 83642
Dk— onQ_QOQ_rrnn _ Cov ')nQ_QQQ_0F99 - nen moriAii4v —