parks commission 020911Julius M. Kleiner Memorial Park
Meridian Parks Commission- February 9, 2011
1
Construction Progress by the Numbers
3,000 concrete blocks in the 416 feet of pond walls
1,000 tons asphalt
10,500 feet of Lighting conduit
5,300 feet of Water pipe
3,350 feet of Sewer pipe
1,200 feet of Gravity Irrigation
pipe
800 yards of Concrete
72 yards of Pervious Concrete
169,246 Square Feet of liner in the North Pond
95,634 Square Feet of liner in the South Pond
Nearly 2,000 feet of concrete curb
Over
2,108 survey points calculated and staked
2
June 2010
3
July 2010
4
August 2010
5
September 2010
6
October 2010
7
November 2010
8
December 2010
9
January 2011
10
11
Grand Entrance
12
Historic Interpretative Center
13
Rock of Honor Plaza
14
Active Recreation Complex
15
Centre on the Park
16
Signage
17
Site Furnishings
Keeping it local – Design & Fabrication
Bollards
Benches
Trash Cans
Drinking Fountains
18
Art in the Park
19
Moving Forward
Grading & Utility Construction
Tiling the NMID Irrigation Canal
ROW – CenterCal Properties & Kleiner Family Trust
Anticipated Grand Opening – late 2011
20
Questions?
21