Task Order No 10083 heroes parkPURCHASING AGENT
33 E. Broadway Ave, Meridian, ID 83642
Phone: (208) 888-4433 x 417
Fax: (208) 887-4813
TASK ORDER NO. 10083
Between
CITY OF MERIDIAN
AND
DC Engineering
This Task Order is issued by City and accepted by the Engineer pursuant to the mutual promises,
covenant and conditions contained in the Master Agreement between the above mentioned parties
dated January, 2007.
Heroes Park Water Quality Analyzer Relocation
SCOPE OF SERVICES
Provide services required to move the existing Heroes Park water quality analyzer from the Meridian
Waste Water Treatment Plant to the Heroes Park pond. DC Engineering will sub -contract the
installation to JC Constructors and Peak Electric to fast track this project.
• Provide PLC control panel.
• Program the PLC and Radio at Heroes Park and the Waste Water Treatment Plant.
• Develop daily flow and water quality report in Wonderware Historian.
• Relocate the existing water quality analyzer.
TIME OF PERFORMANCE
DC Engineering has a capable staff that can start immediately.
COMPENSATION
DC Engineering Community Service
JC Constructors (see attachT Proposal) $3,167.47
Peak Electric (see attached Proposal) less metering pump $8,018.00
Total $11,185.00
CITY OF MERIDIAN
BY:
TAMMY de WEERD, MAYOR
Dated: _ j
Approved by City Council: N%
Attest:
JAYCEE L. HOL�", CITY CLEIAK
Approved as to Cont
BY:
KEITH WATTS. PukaMWG AGENT
Dated: 'r
DC Engineering
Dated: 6/3/09
TITLE:
Dated: CA /09
*C%VHANGE PROPOSAL REQUEST
I.PROJECT
2.CONTRACTOR
JC CONSTRUCTORS
3.PROJECT NO.
5.CONTRACT NO:
Change Proposal #
6.131ROPOSAL DATE
26 -Ma ±9
DESCRIPTION OF CHANGE
Remove panel and mount at new location at Heros Park
Trench from shed to pipe at west side
Install conduit and poly tubing
Install saddle tap and bushing
Backfill trench and clean up
COST SUMMARY
A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR
1. Direct labor wl labor fringes (Attach supporting detail estimates with man-hours and rates)
$
949.78
2. Insurance and Labor Taxes
$
226.34
3. Materials and Equipment. Detailed quantities attached.
$
1,537.50
4. Overhead & Fee @ 15%
$
407.04
Time Extention ReWested 0 working day JC Constructors' Cost $
3,120.66
B. For work to be performed by subcontractors, per proposals and detailed breakdowns
TOTAL SUBCONTRACTOR AMOUNT (INCLUDING $US, OH&P):
3
CONTRACTORS COMMISSION ON TOTAL- SUBCONTRACTOR AMOUNT 0 5 PERCENT: $
CONTRACTORS BOND COST O &01811000 $ 46.81
C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (A5+B5) S 3.167.47
JC CONSTRUCTORS, INC.
CONTRACTOR NAME
Jim Cox
PRINTED NAME ON PROPOSAL
R. M. M
SIGNAWREIDATE
/o=DCEngineering/ou=Exchange Administrative Group
(FYDIBOH F23SPDL7)/cn=Recipients/cn=lhuddieston
From: Peak Electric [office@peak-electric.net]
Sent: Tuesday, June 02, 2009 2:46 PM
To: Lane Huddleston
Cc: aj.lehman@peak-eiectric.net
Subject: Meterina Panel.
Lane, Here it is, please call with any questions.
AJ
PO Box 217 — Star
208-585-9424 , !ToU Free. 877-585-9424
To:
Lane Huddleston
Date:
June 2, 2009
From:
A] Lehman
Re:
Metering Panel
Lane,
Here is the breakdown in cost for the Metering Panel and Neptune PZ pump.
Metering Panel $ 4,918.00
Charge to Expedite $ 600.00
Lahr and Material to Install $ 2,500.00
Neptune PZ Pump $ 1.691.00
Total $ 9,709.00
Please feel free to contact me @ 941-5870 If you have any questions.
Thank you,
A] Lehman
Peak Electric, Inc.
6/3/2009