PZ - Applicant Response to Staff Report - 12/1Bill and Josh,
Thanks for taking the time to prepare the staff report for the project.
We appreciate the thought and effort that went into the report.
Based on our review we are in agreement with the staff report with a
couple of clarifications:
1. The address of the applicant on Page 1 should be:
PO Box 2579
Eagle, ID 83616
2. Also we wanted to clarify that the landscape buffer along the
westerly property line would be 25’ with the current residential use.
However, when the property to the west is developed by others by
construction of a road adjacent to our westerly property line, the
landscape buffer could be potentially be narrower.
Thank you,
Lance Warnick, P.E.
Principal Engineer
Aspen Engineers
485 W. Main St, Suite B ▪ PO Box 205 ▪ Kuna, Idaho 83634
Phone (208) 466-8181 ▪ Cell (208) 989-4531 ▪ lance@AspenEngineers.com
From: Bill Parsons [mailto:bparsons@meridiancity.org]
Sent: Monday, November 30, 2015 5:01 PM
To: Machelle Hill <mhill@meridiancity.org>; Jacy Jones
<jjones@meridiancity.org>; Jaycee Holman <jholman@meridiancity.org>
Cc: Joshua Beach <jbeach@meridiancity.org>; lance@AspenEngineers.com
Subject: Settlers Square Staff Report for 12/03/15 P/Z MTG
Machelle,
Attached is the Settlers Square staff report for the December 3rd P/Z
hearing. I have also included a draft staff report from ACHD.
Lance - Please email us with comments regarding the staff report.
Thanks,
Bill Parsons, AICP
Planning Supervisor
Community Development Department
33 E. Broadway Avenue
Meridian, Idaho 83642
PHONE: (208) 884-5533
FAX: (208) 888-6854
bparsons@meridiancity.org <mailto:parsonsb@meridiancity.org>