Loading...
AIA Agreement with Town and Country Flooring for WWTP Maintenance Shop BP13sale SAIA Document A132T" - 2009 Standard Form of Agreement Between Owner and Contractor, Construction Manager as Adviser Edition AGREEMENT made as of the 26th day of August in the year 2014 (In words, indicate day, month and year.) ADDITIONS AND DELETIONS: The author of this document has BETWEEN the Owner: added information needed for its (Name, legal stalls, address and other information) completion. The author may also have revised the text of the original City of Meridian AIA standard form. An Additions and 33 E. Broadway Deletions Report that notes added Meridian, ID 83642 information as well as revisions tothe standard form text is available from and the Contractor: the author and should be reviewed. A (Name, legal status, address and other information) vertical line in the left margin of this document indicates where the author Town & Country Flooring (dba Wall 2 Wall Flooring) has added necessary information 5200 N. Sawyer Ave., Suite A and where the author has added to or Boise, ID 83714 deleted from the original AIA text. This document has important legal for the following Project: consequences, Consultation with an (Name, location and detailed description) attorney is encouraged with respect to its completion or modification. City of Meridian Waste Water Treatment Plant Maintenance Shop 3401 N. Ten Mile Road This document is intended to be used Meridian, ID 83642 in conjunction with AIA Documents A232"-2009, General Conditions of the Contract for Construction, The Construction Manager: Construction Manager as Adviser (Name, legal status, address and other information) Edition; B132ie-2009. Standard Form of Agreement Between Owner Beniton Construction Co., Inc. and Architect, Construction Manager P.O. Box 838 as Adviser Edition; and Meridian, ID 83680 C1321a-2009, Standard Form of Agreement Between Owner and The Architect: Construction Manager as Adviser. (Name, legal status, address and other information) AIA Document A2321 —2009 is CTA, Inc, adopted in this document by reference. Do not use with other 800 West Main Street, Suite 800 general conditions unless this Boise, ID 83702 document is modified. The Owner and Contractor agree as follows. InI4 AIA Document A132--2009 Voeneriy A101-CMa-1992). Copyright ® 1975, 1960, 1992 and 2009 by The Amencan Institute of Architects. All rights reserved. WARNING: This AIA Document is protected by U.S. Copyright Lawand International Treaties. Unauthorized reproduction ordistribution of this AIA° Document, or any portion of a, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 13.13:44 on 06/29/2014 under Order No. 5637907229_1 which expires an 01/06/2015, and is not for resale. User Notes: (1513116723) TABLE OF ARTICLES 1 THE CONTRACT DOCUMENTS 2 THE WORK OF THIS CONTRACT 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION 4 CONTRACT SUM 5 PAYMENTS 6 DISPUTE RESOLUTION 7 TERMINATION OR SUSPENSION 8 MISCELLANEOUS PROVISIONS 9 ENUMERATION OF CONTRACT DOCUMENTS 10 INSURANCE AND BONDS ARTICLE 1 THE CONTRACT DOCUMENTS The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. An enumeration of the Contract Documents, other than Modifications, appears in Article 9. ARTICLE 2 THE WORK OF THIS CONTRACT The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others. Bid Package #13: Flooring & Tile —Provide all labor, materials, tools and equipment necessary to complete the Flooring & Tile in accordance with Project Plans, Specifications, Addendum No. 1, and the Bid Form for BP #13. Note: All required forms, information and insurances must be completed and submitted to Beniton Construction before commencement of any work including but not limited to the Request for Contract Information, MSDS, safety program, a list of suppliers and subcontractors, and any additional forms as requested in the specifications. Provide submittals electronically if available, or one (1) clean copy (able to scan); some exceptions may apply. Samples and color charts must be provided separately. Contractor shall provide (2) full size copies of approved shop drawings to Beniton. Contractor is responsible to pay all applicable taxes, which are included in the contract price. Contractor is required to provide three (3) hard copies and one (1) electronic copy of closeout information (O&M Manuals, Warranties, etc.) and one (1) complete set of Record Drawings, as requested prior to substantial completion. ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION § 3.1 The date of commencement of the Work shall be the date of this Agreement unless a different date is stated below or provision is made for the date to be fixed in a notice to proceed issued by the Owner. (Insert the date ofcommencement, ifit dijjersfrom the date of this Agreement or, ifapplicable, state that the date will be fixed in a notice to proceed) If, prior to the commencement of the Work, the Owner requires time to file mortgages, mechanics' liens and other security interests, the Owner's time requirement shall be as follows: N/A Init. reserved. WARNING: Thla AIA} Document Is protected by U.S. Cc this AIA, Document, or any portion of It, may result in severe civil t the law. This document was produced by AIA software at 13:13:44 on resale. User Notes: ght Law and International Treaties. Unauthorized reproduction or distribution of 2 criminal penalties, and will be prosecuted to the maximum extent possible under 912014 under Order No. 56379072291 which expires on 01106/2015, and is not for (1513116723) § 3.2 The Contract Time shall be measured from the date of commencement. § 3.3 The Contractor shall achieve Substantial Completion of the entire Work not later than ( ) days from the date of commencement, or as follows: (Insert number of calendar days. Alternatively, a calendar date may be used when coordinated with the date of commencement. If appropriate, insert requirements for earlier Substantial Completion ofcertain portions of the Work.) I Per Exhibit "C" Portion of the Work Substantial Completion Date BP #13: Flooring & Tile March 27, 2015 , subject to adjustments of this Contract Time as provided in the Contract Documents. (Insert provisions, ifany, for liquidated damages relating tofailure to achieve Substantial Completion on time orfor bomrs payments for early completion of the Work.) Per Supplementary Conditions ARTICLE 4 CONTRACT SUM § 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor's performance of the Contract. The Contract Sum shall be one of the following: (Check the appropriate box.) [ X ] Stipulated Sum, in accordance with Section 4.2 below [ ] Cost of the Work plus the Contractor's Fee without a Guaranteed Maximum Price, in accordance with Section 4.3 below [ ] Cost of the Work plus the Contractor's Fee with a Guaranteed Maximum Price, in accordance with Section 4.4 below (Based on the selection above, complete Section 4.2, 4.3 a• 4.4 below. Based on the selection above, also complete either Section 5.1.4, 5.1.5 or 5.1.6 below.) § 4.2 Stipulated Sum § 4.2.1 The Stipulated Sum shall be Five Thousand Seven Hundred Seventy Three and No/100 Dollars ($ 5,773.00 subject to additions and deletions as provided in the Contract Documents. § 4.2.2 The Stipulated Sum is based on the following alternates, if any, which are described in the Contract Documents and are hereby accepted by the Owner: (State the numbers or other ideMifrcation of accepted alternates. Ifthe bidding of- proposal documents permit the Owner to accept other alternates subsequent to the execution of this Agreement, attach a schedule of such other alternates showing the amount for each and the date when that amount expires.) I N/A § 4.2.3 Unit prices, if any: (Idents and state the unit price, and state the quantity limitations, ifany, to which the unit price will be applicable.) Item NIA Units and Limitations Price per Unit ($0.00) § 4.2.4 Allowances included in the Stipulated Sum, if any: (Identify allowance and state exclusions ifaW from the allowance price.) AIA Document A172--2009 Iformerly A101 TMCNIa-1992). Copyright ®1975, 1980, 1992 and 2009 by The American Inshlute of Architects. All rights Inst reserved. WARNING: This AIA! Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA' Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under I the law. This document was produced by AIA software at 13:13'44 on 08/292014 under Order No.5637907229_1 which expires on 011062015, and Is not for resale User Notes: (1513116723) Item N/A Allowance § 4.3 Cost of the Work Plus Contractor's Fee without a Guaranteed Maximum Price This section has been deleted as it does not apply to this "Stipulated Sum" contract (See Paragraph 4.2) (Paragraph deleted) (Table deleted) (Paragraphs deleted) § 4.4 Cost of the Work Plus Contractor's Fee with a Guaranteed Maximum Price This section has been deleted as it does not apply to this "Stipulated Sum" contract (See Paragraph 4.2) (Paragraphs deleted) (Table deleted) (Paragraphs deleted) (Table deleted) (Paragraphs deleted) ARTICLE 5 PAYMENTS § 5.1 Progress Payments § 5.1.1 Based upon Applications for Payment submitted to the Construction Manager by the Contractor, and upon certification oftheProject Application and Project Certificate for Payment or Application for Payment and Certificate for Payment by the Construction Manager and Architectand issuance by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents. § 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month. § 5.1.3 Provided that an Application for Payment is received by the Construction Manager not later than the 25th day of a month, the Owner shall make payment of the certified amount in the Application for Payment to the Contractor not later than the 30th day of the following month. If an Application for Payment is received by the Construction Manager after the application date fixed above, payment shall be made by the Owner not later than sixty ( 60 ) days after the Construction Manager receives the Application for Payment. (Federal, state or local lmvs may require payment within a certain period of time) § 5.1.4 Progress Payments Where the Contract Sum is Based on a Stipulated Sum § 5.1.4.1 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work and be prepared in such form and supported by such data to substantiate its accuracy as the Construction Manager and Architect may require. This schedule, unless objected to by the Construction Manager or Architect, shall be used as a basis for reviewing the Contractor's Applications for Payment. § 5.1.4.2 Applications for Payment shall show the percentage of completion of each portion of the Work as ofthe end of the period covered by the Application for Payment. § 5.1.4.3 Subject to the provisions ofthe Contract Documents, the amount of each progress payment shall be computed as follows: .1 Take that portion of the Contract Sum properly allocable to completed Work as determined by multiplying the percentage completion of each portion of the Work by the share of the total Contract Sum allocated to that portion of the Work in the schedule of values, less retainage of five percent ( 5 %). Pending final determination of cost to the Owner of changes in the Work, amounts not in dispute may be included as provided in Section 7.3.9 of the General Conditions; .2 Add that portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction (or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing), less retainage of five percent ( 5 %); .3 Subtract the aggregate of previous payments made by the Owner; and Ink. AIA Document A132-- 2009 Vormarly A101'n`iCN s —1992). Ccpyright C 1975, 1960, 1992 and 2009 by The American Institute of Architects. All rights reserved. WARNING: This AIA Document Is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA` Document, or any portion of it, may result In severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under l the law. This document was produced by AIA software at 13:13:44 on 0 512 912 01 4 under Order No,5637907229 1 which expires on 0110612015. and is not for resale. User Notes: (1513116723) .4 Subtract amounts, if any, for which the Construction Manager or Architect has withheld or nullified a Certificate for Payment as provided in Section 9.5 of the General Conditions. § 5.1.4.4 The progress payment amount determined in accordance with Section 5.1.4.3 shall be further modified under the following circumstances: .1 Add, upon Substantial Completion of the Work, a sum sufficient to increase the total payments to ninety-five percent ( 95 %) of the Contract Sum, less such amounts as the Construction Manager recommends and the Architect determines for incomplete Work and unsettled claims; and .2 Add, if final completion of the Work is thereafter materially delayed through no fault ofthe Contractor, any additional amounts payable in accordance with Section 9.10.3 of the General Conditions. § 5.1.4.5 Reduction or limitation of retainage, if any, shall be as follows: (If it is intended, prior to Substantial Completion ofthe entire Work, to reduce or limit the retainage resultingfrom the percentages inserted in Sections 5.1.4.3.1 and 5.1.4.3.1 above, and this is not explained elsewhere in the Contract Documents, insert here provisions for such reduction or limitation.) N/A § 5.1.5 Progress Payments Where the Contract Sum is Based on the Cost of the Work without a Guaranteed Maximum Price This section has been deleted as it does not apply to this "Stipulated Sum" contract (See Paragraph 5.1.4) (Paragraphs deleted) § 5.1.6 Progress Payments Where the Contract Sum is Based on the Cost of the Work with a Guaranteed Maximum Price This section has been deleted as it does not apply to this "Stipulated Sum" contract (See Paragraph 5.1.4) (Paragraphs deleted) § 5.2 Final Payment § 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the Contractor when .1 the Contractor has fully performed the Contract except for the Contractor's responsibility to correct Work as provided in Section 12.2 of AIA Document A232-2009, and to satisfy other requirements, if any, which extend beyond final payment; .2 the Contractor has submitted a final accounting for the Cost of the Work, pursuant to Exhibit A, Determination of the Cost of the Work when payment is on the basis of the Cost of the Work, with or without a Guaranteed Maximum payment; and .3 a final Certificate for Payment or Project Certificate for Payment has been issued by the Architect; such final payment shall be made by the Owner not more than 30 days after the issuance of the final Certificate for Payment or Project Certificate for Payment, or as follows: ARTICLE 6 DISPUTE RESOLUTION § 6.1 Initial Decision Maker The Architect will serve as Initial Decision Maker pursuant to Section 15.2 of AIA Document A232-2009, unless the parries appoint below another individual, not a party to this Agreement, to serve as Initial Decision Maker. (If the parties mutually agree, insert the name, address and other contact information ofthe Initial Decision Maker, if other than the Architect) § 6.2 Binding Dispute Resolution For any Claim subject to, but not resolved by, mediation pursuant to Section 15.3 of AIA Document A232-2009, the method of binding dispute resolution shall be as follows: (Check the appropriate box. If the Owner and Contractor do not select a method ofbinding dispute resolution below, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims will be resolved by litigation in a court of competent jurisdiction) AIA Document A132-- 2009 formerly A101-CMa —1992). Copyright ®1975, 1990, 1992 and 2009 by The American Institute of Architects. All rights Ina. reserved. WARNING: This AIA Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA` Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under y the law. This document was produced by AIA software at 13:13:44 on 09/29/2014 under Order No.5537907229_1 which expires on 0110612015, and is not for resale. User Notes: (1513116723) [ ] Arbitration pursuant to Section 15.4 of AIA Document A232-2009. [ X ] Litigation in a court of competent jurisdiction. [ ] Other: (Specify) ARTICLE 7 TERMINATION OR SUSPENSION § 7.1 Where the Contract Sum is a Stipulated Sum § 7.1.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document A232-2009. § 7.1.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A232-2009. § 7.2Where the Contract Sum is Based on the Cost of the Work with or without a Guaranteed Maximum Price This section has been deleted as it does not apply to this "Stipulated Sum" contract (See Paragraph 7.1) (Paragraphs deleted) ARTICLE 8 MISCELLANEOUS PROVISIONS § 8.1 Where reference is made in this Agreement to a provision of AIA Document A232-2009 or another Contract Document, the reference refers to that provision as amended or supplemented by other provisions ofthe Contract Documents. § 8.2 Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated below, or in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located. (Insert rate of interest agreed upon, if arty.) (Paragraph deleted) § 8.3 The Owner's representative: (Name, address and other information) Beniton Construction Co., Inc. Bryce Parker P.O. Box 838 Meridian, ID 83680 § 8.4 The Contractor's representative: (Name, address and other information) Town & Country Flooring (dba Wall 2 Wall Flooring) Dennis Zollinger 5200 N. Sawyer Ave., Suite A Boise, ID 83714 § 8.5 Neither the Owner's nor the Contractor's representative shall be changed without ten days written notice to the other party. § 8.6 Other provisions: N/A ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS § 9.1 The Contract Documents, except for Modifications issued after execution of this Agreement, are enumerated in the sections below. § 9.1.1 The Agreement is this executed AIA Document Al 32-2009, Standard Form of Agreement Between Owner and Contractor, Construction Manager as Adviser Edition. AIA Document A132-- 200fo 9 rmerly At 01 TMCMa —1992). Copyright ®1975, 1950, 1992 and 2009 by The American Institute of Architects. All rights Init reserved. WARNING: This AIA Document is protected by U.S. Copyright Law and Intemational Treaties. Unauthorized reproduction or distribution of this AIA` Document, or any portion of It, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under 1 the law. This document was produced by AIA software at 13 13:44 on 081292014 under Order No.5637907229 1 which expires on 0110612015, and is not for resale User Nates: (1513116723) § 9.1.2 The General Conditions are, AIA Document A232-2009, General Conditions of the Contract for Construction, Construction Manager as Adviser Edition. § 9.1.3 The Supplementary and other Conditions of the Contract are those contained in the Project Manual, per attached Exhibit "A". (Table deleted) § 9.1.47heSpecifications: (Either list the Specifications here or refer to an exhibit attached to this Agreement.) Per Exhibit "A" (Table deleted) § 9.1.5 The Drawings: (Either list the Drawings here or refer to an exhibit attached to this Agreement.) Per Exhibit "B" (Table deleted) § 9.1.6 The Addenda, if any: Number Date Pages Per Exhibit "A" Portions of Addenda relating to bidding requirements are not part of the Contract Documents unless the bidding requirements are also enumerated in this Article 9. § 9.1.7 Additional documents, if any, forming part of the Contract Documents are: .1 (Paragraphs deleted) Other documents, if any, listed below: (List here any additional documents which are intended to form part ofthe Contract Documents. AIA Document A232-2009 provides that bidding requirements such as advertisement or invitation to bid, Instructions to Bidders, sample forms and the Contractor's bid are not part of the Contract Documents unless enumerated in this Agreement. They should be listed here only if intended to be part of the Contract Documents.) * Exhibit "1" and Sample Certificate—Insurance Requirements * Request for Contract Information * WH -5 Form * Affidavit Concerning Taxes * Application for Payment and Schedule of Values ARTICLE 10 INSURANCE AND BONDS The Contractor shall purchase and maintain insurance and provide bonds as set forth in Article 1 I of AIA Document A232-2009. (State bonding requirements, ii and limits of liability for insurance required in Article 11 of AIA Document A232-2009) Type of Insurance or Bond Limit of Liability or Bond Amount Insurance per attached Exhibit "I" Payment & Performance Bonds 100% of the Contract Amount (see Supplementary Instructions to Bidders for delivery requirement) AIA Document A132-- 2009 formerly A101—CMa —1992). Copyright 01975, 1980, 1992 and 2009 by The American Institute of Architects. All rights Init. reserved. WARNING: This AIA Document is protected by U.S. Copyright Law and International Trestles. Unauthorized reproduction or distribution of this AIA` Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under I the law. This document was produced by AIA software at 13:1344 on 0 812 912 01 4 under Order No,5537907229 1 which expires on 01/06/2015, and is not for resale. User Notes: (1513116723) This Agreement is entered into as of the day and year first written above OW R (Si re) mM A ��I / (Printed name an atle) � �1 CONTRAC R (Signatur A I5� Pr OAC li (Printed name and title) Init. Vorrnerly A101—CMa —1992). Copyright © 1975, 1980, 1992 and 2009 by The American Institute of Architects. All rights reserved. WARNING: This AIA Document is protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under 8 / the law. This document was produced by AIA software at 13:13:44 on 08/29/2014 under Order No.5637907229 1 which expires on 01/06/2015, and is not for resale. _ User Notes: (1513116723) Meridian Wastewater Treatment Plant (MW WTP) Maintenance Facility EXHIBIT "A" BIDDING INSTRUCTIONS Invitationto Bid................................................................................................ Noticeto Bidders............................................................................................. AIA A701 Instructions to Bidders...................................................................... Supplemental Instructions to Bidders.............................................................. Bid Form Table of Contents............................................................................. BidForms........................................................................................................ ProjectSchedule............................................................................................. AIA A132 Standard Form of Agreement Between Owner and Contractor........ Supplement to Agreement............................................................................... AIA A232 General Conditions of the Contract .................................................. SupplementaryConditions............................................................................... Exhibit I — Insurance Requirements................................................................ Contractor's Affidavit Concerning Taxes.......................................................... Public Works Contract Tax Report (WH -5) ...................................................... SPECIFICATIONS DIVISION 01— GENERAL REQUIREMENTS 011000 SUMMARY OF WORK ............................................ 012300 ALTERNATES......................................................... 012900 PRICE AND PAYMENT PROCEDURES ................. 013100 PROJECT MANAGEMENT AND COORDINATION. 013300 SUBMITTAL PROCEDURES ................................... 014200 REFERENCES........................................................ 014500 QUALITY CONTROL ............................................... 015000 TEMPORARY FACILITIES AND CONTROLS......... 016000 PRODUCT REQUIREMENTS ................................. FORM SUBSTITUTION REQUEST FORM ......................... 017300 EXECUTION............................................................ 017320 CUTTING AND PATCHING ..................................... 017700 CLOSEOUT PROCEDURES ................................... DIVISION 02 — EXISTING CONDITIONS 024116 STRUCTURE DEMOLITION.. 5/14 ............ 1-1 ............1-4 ............1-6 ............1-4 ............1-1 ..........1-40 ............1-3 ............1-8 ............1-2 ..........1-43 ............1-5 ............1-1 ............1-1 ............1-2 DIVISION 03 — CONCRETE 033000 CAST -IN-PLACE CONCRETE....................................................................... 033543 POLISHED CONCRETE FINISHING............................................................. DIVISION 04 — MASONRY 042200 CONCRETE UNIT MASONRY ............................. TABLE OF CONTENTS 1-5 1-12 ..1-2 1-13 Meridian Wastewater Treatment Plant (MW WTP) Maintenance Facility DIVISION 05 — METALS 051200 STRUCTURAL STEEL FRAMING ......... 052100 STEEL JOIST FRAMING ....................... 053100 STEEL DECKING .................................. 054000 COLD -FORMED METAL FRAMING...... 055000 METAL FABRICATIONS ....................... 055119 METAL GRATING STAIRS .................... 055213 PIPE AND TUBE RAILINGS .................. 5/14 DIVISION 06 —WOOD, PLASTICS, AND COMPOSITES 061053 MISCELLANEOUS ROUGH CARPENTRY.........................................................1-2 DIVISION 07 — THERMAL AND MOISTURE PROTECTION 071113 BITUMINOUS DAMPROOFING...........................................................................1-3 072100 THERMAL INSULATION.....................................................................................1-4 074113.16 STANDING -SEAM METAL ROOF PANELS........................................................1-7 074213.53 METAL SOFFIT PANELS....................................................................................1-5 077253 SNOW GUARDS.................................................................................................1-2 079200 JOINT SEALANTS...............................................................................................1-7 DIVISION 08 —OPENINGS 081113 HOLLOW METAL DOORS AND FRAMES..........................................................1-7 083113 ACCESS DOORS AND FRAMES........................................................................1-3 083323 OVERHEAD COILING DOORS...........................................................................1-6 086200 UNIT SKYLIGHTS...............................................................................................1-3 087111 DOOR HARDWARE (DESCRIPTIVE SPECIFICATION)..................................1-12 088000 GLAZING.............................................................................................................1-7 DIVISION 09 — FINISHES 092216 NON-STRUCTURAL METAL FRAMING..............................................................1-5 092900 GYPSUM BOARD...............................................................................................1-3 093013 SF CERAMIC TILING.................................................................................1-7 095123 ACOUSTICAL TILE CEILINGS............................................................................1-3 096513 RESILIENT BASE AND ACCESSORIES.............................................................1-3 099113 EXTERIOR PAINTING.........................................................................................1-3 099123 INTERIOR PAINTING..........................................................................................1-4 DIVISION 10 —SPECIALTIES 102600 WALL AND DOOR PROTECTION.......................................................................1-2 102800 TOILET, BATH, AND LAUNDRY ACCESSORIES...............................................1-3 104416 FIRE EXTINGUISHERS......................................................................................1-3 105113 METAL LOCKERS...............................................................................................1-5 DIVISION 11 — EQUIPMENT NOT USED DIVISION 12 — FURNISHINGS 122113 HORIZONTAL LOUVER BLINDS........................................................................1-3 123623.13 PLASTIC -LAMINATE -CLAD COUNTERTOPS....................................................1-4 TABLE OF CONTENTS 2 Meridian Wastewater Treatment Plant (MW WTP) 5/14 Maintenance Facility DIVISION 13 — SPECIAL CONSTRUCTION NOT USED DIVISION 14—CONVEYING EQUIPMENT NOT USED DIVISION 15 — 21 (NOT USED) VOLUME 2 OF 2 DIVISION 22 — PLUMBING 221113 FACILITY WATER DISTRIBUTION PIPING........................................................1-7 221116 DOMESTIC WATER PIPING...............................................................................1-7 221119 DOMESTIC WATER PIPING SPECIALTIES.......................................................1-8 221123 DOMESTIC WATER PUMPS..............................................................................1-4 1-4 221313 FACILITY SANITARY SEWERS..........................................................................1-5 221316 SANITARY WASTE AND VENT PIPING...........................................................1-16 221319 SANITARY WASTE PIPING SPECIALTIES........................................................1-8 221513 GENERAL -SERVICE COMPRESSED -AIR PIPING...........................................1-10 221519 GENERAL -SERVICE PACKAGED AIR COMPRESSORS AND RECEIVERS ..... 1-9 223400 FUEL -FIRED DOMESTIC WATER HEATERS.....................................................1-7 224000 PLUMBING FIXTURES.....................................................................................1-11 224500 EMERGENCY PLUMBING FIXTURES................................................................1-5 224700 DRINKING FOUNTAINS AND WATER COOLERS............................................1-5 DIVISION 23 — HVAC 230500 COMMON WORK RESULTS FOR PLUMBING AND HVAC..............................1-11 230523 GENERAL -DUTY VALVES FOR PLUMBING AND HVAC PIPING......................1-5 230549 SEISMIC CONTROLS FOR PLUMBING AND HVAC..........................................1-6 230553 IDENTIFICATION FOR PLUMBING AND HVAC PIPING AND EQUIPMENT ...... 1-4 230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC.....................................1-5 230700 HVAC INSULATION............................................................................................1-9 231123 FACILITY NATURAL-GAS PIPING....................................................................1-17 233113 METAL DUCTS.................................................................................................1-13 233300 AIR DUCT ACCESSORIES...............................................................................1-10 233423 HVAC POWER VENTILATORS...........................................................................1-6 233713 DIFFUSERS, REGISTERS, AND GRILLES.........................................................1-3 233813 COMMERCIAL -KITCHEN HOODS......................................................................1-5 234100 PARTICULATE AIR FILTRATION........................................................................1-2 235100 BREECHINGS, CHIMNEYS, AND STACKS........................................................1-3 235400 FURNACES.........................................................................................................1-6 235533 FUEL -FIRED UNIT HEATERS.............................................................................1-4 236200 PACKAGED COMPRESSOR AND CONDENSER UNITS...................................1-4 237423 PACKAGED, INDIRECT -FIRED, INDOOR, HEATING -ONLY MAKEUP -AIR UNITS................................................................................................................. 1-9 TABLE OF CONTENTS Meridian Wastewater Treatment Plant (MW WTP) 5/14 Maintenance Facility DIVISION 24 — (NOT USED) DIVISION 25 — (NOT USED) DIVISION 26 — ELECTRICAL 260500 COMMON WORK RESULTS FOR ELECTRICAL...............................................1-5 312000 EARTH MOVING.................................................................................................1-8 260519 LOW -VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES ............ 1-3 260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS ...........................1-4 321216 ASPHALT PAVING..............................................................................................1-5 260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS.............................1-4 260533 RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS................................1-10 334100 STORM UTILITY DRAINAGE PIPING.................................................................1-6 260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS...............................................1-6 ..... 1-4 260573 OVERCURRENT PROTECTIVE DEVICE COORDINATION AND ARC FLASH STUDY................................................................................................................1-7 262200 LOW -VOLTAGE TRANSFORMERS....................................................................1-4 262416 PANELBOARDS..................................................................................................1-6 262726 WIRING DEVICES...............................................................................................1-5 262813 FUSES................................................................................................................1-3 262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS.........................................1-5 262913 ENCLOSED CONTROLLERS.............................................................................1-5 265100 INTERIOR LIGHTING..........................................................................................1-8 DIVISION 27 —COMMUNICATIONS 270500 COMMON WORK RESULTS FOR COMMUNICATIONS....................................1-4 312000 EARTH MOVING.................................................................................................1-8 271100 COMMUNICATIONS EQUIPMENT ROOM FITTINGS........................................1-5 271300 COMMUNICATIONS BACKBONE CABLING......................................................1-8 321216 ASPHALT PAVING..............................................................................................1-5 271500 COMMUNICATIONS HORIZONTAL CABLING.................................................1-10 DIVISION 28 — ELECTRONIC SAFETY AND SECURITY 334100 STORM UTILITY DRAINAGE PIPING.................................................................1-6 280500 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY ..... 1-4 283100 FIRE DETECTION AND ALARM.......................................................................1-11 DIVISION 29 — 30 (NOT USED) DIVISION 31 — EARTHWORK 311000 SITE CLEARING.................................................................................................1-4 312000 EARTH MOVING.................................................................................................1-8 312319 DEWATERING....................................................................................................1-2 DIVISION 32 — EXTERIOR IMPROVEMENTS 321216 ASPHALT PAVING..............................................................................................1-5 321313 CONCRETE PAVING..........................................................................................1-5 DIVISION 33 — UTILITIES 334100 STORM UTILITY DRAINAGE PIPING.................................................................1-6 ADDENDUM NO. 1, dated 7/31/14........................................................................................... 1-17 TABLE OF CONTENTS VWVTP Maintenance Facility 3401 N. Ten Mile, Meridian, ID 83642 Exhibit "B" CONSTRUCTION DRAWINGS SHEET # DESCRIPTION DATED Al 00 Al 00 - Wall and Horizontal Assembly Details 07/18/2014 A101 Al 01 - Floor Plan 07/18/2014 Al 02 Al 02 - Mezzanine Floor Plan 07/18/2014 A110 All 0 - Roof Plan 07/18/2014 AM Al 11 - Roof Details 07/18/2014 A201 A201 - Exterior Elevations 07/18/2014 A301 A301 - Building Sections 07/18/2014 A401 A401 - Stair Plans and Details 07/18/2014 A501 A501 - Finish Plan 07/18/2014 A601 A601 - Door and Window Schedules and Details 07/18/2014 A901 A901 - Reflected Ceiling Plan 07/18/2014 C1-101 C1-101 Site Demolition Plan 07/18/2014 C3-101 C3-101 Site Plan 07/18/2014 C7-101 C7-101 Site Plan 07/18/2014 E001 E001 - Legends & Schedules 07/18/2014 E002 E002 - One -Line Diagram 07/18/2014 E003 E003 - Panel Schedules 07/18/2014 E100 El 00 - Electrical Site Plan 07/18/2014 E201 E201 - First Floor Lighting Plan 07/18/2014 E202 E202 - Mezzanine Lighting Plan 07/18/2014 E203 E203 - Lighting Compliance Forms 07/18/2014 E301 E301 - First Floor Power Plan 07/18/2014 E302 E302 - Mezzanine Power Plan 07/18/2014 E401 E401- Special Systems Plan 07/18/2014 G101 G101 -Architectural Cover Sheet 07/18/2014 G102 G102 - Code Plan 07/18/2014 G103 G103 - Mezzanine Code Plan 07/18/2014 M001 M001 - Mechanical Schedules & Legends 07/18/2014 M100 M100 - First Floor HVAC Plan 7/18/2014 M101 M101 - Mezzanine HVAC Plan 7/18/2014 M200 M200 - Enlarged Plans and Sections 7/18/2014 M300 M300 - HVAC Details 7/18/2014 M400 M400 - Energy Compliance 7/18/2014 P00l P001 - Plumbing Schedules and Legends 7/18/2014 P100 P100 - Plumbing Waste & Vent Plans 7/18/2014 P200 P200 - Plumbing Water & Gas Plan 7/18/2014 P300 P300 - Plumbing Details 7/18/2014 S001 S001 - General Structural Notes 7/18/2014 S101 S101 - Foundation Plan 7/18/2014 S102 S102 - Mezzanine Framing Plan 7/18/2014 S103 S103 - Roof Framing Plan 7/18/2014 S201 S201 - Foundations Details 7/18/2014 S202 S202 - Wall Framing & Mezzanine Details 7/18/2014 S203 S203 - Roof Framing Details 7/18/2014 S301 IS301 - Building Sections 7/18/2014 .. wi ..................,.... ._ ... -------------- 0- to N N h c 3 (qp e Vl S r C a Q N M __ C 9 VIM 'gqq iWp p�� pp .4 C:V G c A Y C � ` pOH i c o E c a 4�2 Q N N v] Q V O Q Q< V b P V V 0 d O' m `m 4 E d d t5 t1 o t5 m o t5 v t7 t5 . g $ 8m o 0 0 0 0�1 0 0 0 0 0 0 z° 0ry O . N N m ;w ZJ O O N N N N O o 0 0 N N N N N N O ¢ ¢ Q Q r � � N I'i � � � iq �.5 �:989 NAga.9.9 9,00��� 00000zzz a" S N O O N O O O O �� 0 :0 0 0 a a 0 0 ae ae ae Qe ae ae ae 0 0 0 0 ae a eo ae ;e ae eo ae C o 0 0 0 ' 0 0 0 0 0 0 0 0 0 0 0 0 O U• O a N N N N Q CO,� iN O Qf N l7 Cl CI N N Vl Cl 1n N N (:. I� n N V m N IA U OO - �, E u� Q@1 qcq m c m L U 4 g� m oUa. U m rn o m Q 19 m Q$ a p O m U 'tq iC m c y oO' mF g b E .°� f9 N •1S w c d E o 1� @ w oago0 E' c �'aF 0w ccs �♦ > rs m�$ a. C Nm E c • 25 Ery 5 ~ `m C7 c 9c .L 3 kB c IL G O d m 0 m• 1' ° J K ° 3 7 iL t' W LL S w Y cr O _ 3 m NW C .q O O C' 0 a o 0 0 0 C a `• 0 0 0 0 0 0 0 o a o o N m m m m 2 m m 2i C c S G m E CO ¢a 0 I U d) E 16 16 i5 13 9 E--._ _ L -------- 294 O n n o a c c .n 0 3 G � U ,q U o o LL ; rc - z s bN �,o c c g - — a l ~ M �� O 5 • r -_______..__------.______ -__. ________.______..._________....._____________---_-_____.____ Q d ' 0 Q Q v v Q a0 d ^ N NC NG Gh N ` N_ ^ N_ N ^ ' c C N Or ` W 0i 4i Ui `m y `m `d `m `m m `m n `m m `m `m `m `m O D �° '� LL o LL i LL LL LL ri LL r2 �2 �2 `6• `d � � ¢ i 2 i a N' a o m` a A J n e p m< o. Y p a s A V r P r O N S t+l N N N O N N O O N' O N O O N N CJ t7 m d d d d did d d,d Iq N^ N N ^ N^^ 1 v n wj� N N' N- N t5 b C C C b b b b R N m N • m m 0 m m m m c N' �L r' r' .b 'n N e N �o co 0 0 �n p n' [V a a m m_ o o'I,6 u> in 1n 6 a, 'N N N N O r N N N N N N N N N m N M N :N N ® m 0 O O m m m N N N N N Q d a • EN a n y w E H rn m mO m o c m � o � m c m O E F7 O� �y c TS LL N 4 ry jO O G N v U EC N M LL N m y m N A z B = E N a- Ffi _ m S9 E a U a m m LL 2 '4 T O c LL m th '^ ELp N um 3 a O a E m H E o{ o o m m F$ g D rn tn' C7 rn K O m c y 0rtrt K v?46 owE a aE �W c U ii w b L b = m m — m U n m `m p n c E m c t a N a� °� E tN t5 c m 2 o f c c m p m m o' U i Ul '' H R U d 0 w w 2 S c A c 3 3 a d n a 3 o= d LL a 0 0 x u � O O O W O O O 0 0 0 O N O N O O O N O O O N O O N O b pOj p � 0 0 m m m .O„ m m m m m m m m 'C m m m m m m m m m m m m • 3 a Ja a H 3 00 w LL LL a r o EXHIBIT ""I" INSURANCE REQUIREMENTS FOR WORKING WITH BENITON CONSTRUCTION COMPANY & CITY OF MERIDIAN Contractors and Subcontractors shall provide evidence that the following minimum coverage is provided. Commercial General Liability (ISO Form CG0001 (10/01) or Equivalent) • $2,000,000 General Aggregate • $2,000,000 Products/Completed Operations Aggregate • $1,000,000 Each Occurrence • $1,000,000 Personal Injury and Advertising Injury • $ 100,000 Fire Damage Liability • $ 5,000 Medical Expenses—Each Person o Limits must be on a "Per Project Aggregate'. o City of Meridian and Beniton Construction Company must be listed as additional insured (ISO Form CG2010 (11/85), or CG2010 (10/01) and CG2037 (10/01), or Equivalent). A copy of the endorsement adding Beniton Construction Company shall be included with the certificate of insurance. o Completed operations coverage will remain in effect for 2 years after project completion. Business Automobile Liability • $1,000,000 Each Occurrence Worker's Compensation and Employers Liability Insurance • Statutory Limits • Employers Liability o $1,000,000 Each Accident $1,000,000 Policy Limits $1,000,000 Each Employee Excess Liability • $1,000,000 For Architects, Engineers, Surveyors, & Testing Firms: Professional Liability (Errors and Omissions) — Continued for Two (2) Years After Project Completion • $1,000,000 per claim and $2,000,000 aggregate for annual claims made coverage OR • $1,000,000 project coverage ➢ Certificate of Insurance must be project specific. ➢ Please provide written documentation in regards to your insurance contract(s) cancellation terms. ➢ Insurance is to be Primary & Non -Contributory to any liability insurance carried by Beniton Construction Co., Inc. and City of Meridian. ➢ Waiver of Subrogation applies in favor of Beniton Construction Co., Inc. and City of Meridian. CERTIFICATE OF LIABILITY INSURANCE I DATE(MMIDDIYYYY) THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER. IMPORTANT: If the certificate holder Is an ADDITIONAL INSURED, the pollcy(ies) must be endorsed. If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may require an endorsement A statement on this certificate does not center rights to the certificate holder In lieu of such endomemenl(s). PRODUCER A T NAME: Producer's name and address INSURED Subcontractor name and address UMBER: THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED AEOVE F9R THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRAPT OR OTHER DOCUMENT WITH )tESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POO�LI�ICIIQES, LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. INSR TYPE OF INSURANCE IA I pIX1CY NUMBER POLICY EFFLWIDD�l EXP ---��- LAInE Beri Construction Company, Inc. GENERAL LIABILITY P.O. Box 838 AUTHORIZED REPRESENTATIVE EACHC�CCUFRENCE S 1000 00 %� COMMERCIAL GENERAL LIABILITY CLAIMS -MADE OOCCUR FT I ^ r I ^ , AM T917— PRE $IEa�o e" S 1 SEDERPpn one perm) S 10.000 109(01/2012 _ Current policy # 0910112011 *gSONAL 8 ADV INJURY E 1 00a DDO GENERAL AGGREGATE E 2,000,000 GENL AGGREGATE LIMIT APPLIES PER: - COMPAOPAGG S 2 POLICY X PRO. LOC _PRODUCTS $ AUTOMoeaa LIABILITY' ff. avids 51,000,000 BODILYINJUtY(P.rpnaon) S ANY AUTO ALLOYED SCHEDULED AU70S AUTOS HIRED AUTOS AUTOS # 1/2011 0910112012 BODILY INJURY (Per aeddent) E Pw ixeRhardl S IS X UMBRELLA LUIB X OCCUR EACH OCCURRENCE E 1,000000 AGGREGATE s 1,000;000 EXCESS LMB CINMS�AIAU Current 09101/2011 09/012012 S DEO I I REENnONE WORKERS COMPENSATION AND EMPLOYERS LL191LnY YIN ANY PROPRIETORIPARTNERIEXECUTIVE OFFICEMEMSER EXCLUDED? NI PO 09/012011 09/0112012 x A U• W E.L. EACH ACCIDENT S E.L. DISEASE. EA EMPLOYEE $ 1,000,000 (MAM.r.ry In RIO Ifw.'tl nk,ewMw DESCRIPTION OF OP E.L. DISEASE. POLICY LIMIT S 1,000,000 DESCRIPTION OF OPERATION -TIGNS IVEHN:LE81AYaeh ACOR0101, Additional RAmarlu Schedule, a men apace Is niulnd) Re: City of Meridian Waste Water Treatment Plant Maintenance Shop. City of Meridian and Beniton Construction are listed as Additional Insured perthe Commerdal General Liability coverage on a primary and non-contributory basis regarding above project provided by form CG2010 10101 and CG2037 10101 (or equivalent). Waiver of Subrogation applies in favor of the Beniton Construction Company, Inc. and ovmer (except WC). CERTIFICATE HOLDER CANCELLATION © 1988-2010 ACORD CORPORATION. All rights reserved. ACORD 25 (2010105) The ACORD name and logo are registered marks of ACORD SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN Beri Construction Company, Inc. ACCORDANCE WITH THE POLICY PROVISIONS. P.O. Box 838 AUTHORIZED REPRESENTATIVE Meridian, ID 83680 Original Signature © 1988-2010 ACORD CORPORATION. All rights reserved. ACORD 25 (2010105) The ACORD name and logo are registered marks of ACORD