Loading...
HomeMy WebLinkAboutChange Order No. 1 with Hydro Logic for Well 16 Test Well DesignCITY OF MERIDIAN 33 EAST BROADWAY AVENUE MERIDIAN, ID 83842 Change Order No.: 1 Project Number: 10312a Date: 5/70!2012 Effectlve Date: CONFIRMING CONTRACT CHANGE ORDER CONTRACTOR: Hydro Logic PROJECT: Well 18 -Test Well Design The Contractor is hereby directed to make the following changes from the Contract Documents and Plans. Description: 1) Design a liner In existing Production Well 16 to occlude the well's original reducer and headpipe connection. 2) provide support for procurement of liner by contacting conkactors. 3) Provide inspection of liner construction and installation in existing well and reinstallation of pump and column. 4) Aquire water samples from reconstructed well 5) Provide technical memorandum to describe the work and results that can be used as support for submittal to IDEO. 6) Deliverables: Liner design and installation inspection, water sample reports, technical memorandum. Reason for Change Order: Well 16 production well is scheduled for replacement due to exceedence of the Uranium MCL and poor condition of the well casing. During the course of design work on Well 16B test well, the consultant made some discoveries about how the original production well construction methods might be contributing to the high Uranium levels encountered. The consultant made a verbal request to the City PM to accomplish the work stated above. This work was not only potentially valuable as a temporary correction for the existing well, but also to understand the underlying sub-aquifer geochemistry which is an objective of the current Task Order. For this reason, City PM agreed and made a verbal work directive to accomplish this work under the current Task Order. Attachments: Original Task Order Scope of Work CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price: $35,000.00 Original Contract Completion Date: Original Contract Completion Days: AFTER THE FACT /CONFIRMING Nel changes form previous C.O.'s.: Net Days change form previous C.O.'s: No, 0 to 0 No. 0 to 0 $0.00 Contract Price Prior tc this C.O.: Contract Completion Dale before This C.O.: $3s,ooo.oo NeL Increase (decrease) of this C.O.: Nel Days Increase (decrease) of this C.O.: $26,000.00 Contract Price with all Approved C.O.'s: Contract Completion Dale with all Approved C.O.'s: $61,000.00 N/A WORK IS ALREADY COMPLETE RECOMMENDED: (PROJECT MANAGER) ACCEPTED (CONTRACTOR) EBy: / By: Date: ~ ~ ~Z Date: / ~ 7/*t / CLr /`~.~L APPROVED: ( ITY PURCHASI AGE T) y / COUNCIL APPROVAL /`/,'// eRp4L' / ~ AUC4 J f/ By: Keith Welts oo" Date: ~O/y~ ? ~ is ~o~~ ~~9 D l ~` r Z a e: E APPROVED. rclay) F ~~ /~~~~ ~ r u ~_ x By: Mayor Tamm eerd o~ § City Clyer Ja a Holman Date: / 't ~ ~'i6r d o Date: ~a~ ~ ~a _ /~ V•