HomeMy WebLinkAboutChange Order No 3 with Golis Construction for Settlers Park Restroom
'AlA
Contract Administration
G70l Change Order
Distribution list:
Owner
Architect
Contractor
Field
Other
PROJECT (Name and address):
Settler's Park Restroom
CHANGE ORDER NUMBER:.@
DATE: August 28 2003
TO CONTRACTOR (Name and address):
Golis Construction PO Box 2559 Eagle
1083616
ARCHITECT'S PROJECT NUMBER: 02180
CONTRACT DA TE:April 28 2003
CONTRACT FOR: Restroom Building
THE CONTRACT IS CHANGED AS FOLLOWS:
(lndude, where applicable, any undisputed amount attributable to previously executed Construction Change Directives)
C.O. #4 Revised cellino finish - see attached letter from Golis Construction 8-10-03.
C.O. #5 Applv a penetrant and two coats of water based epoXY to lower vapor transmission in concrete slab.
The original (Contract Sum) (Guarantees Ma)(imum Price) was
The net change by previously authorized Change Orders
The (Contract Sum) (Guarantees ~1a¡(imum Price) prior to this Change Order was
The (Contract Sum) (Guarantees ~1a)(imum Price) will be (increased) (secrea&es) (uncRaAges)
by this Change Order in the amount of
The new (Contract Sum) (Guarantees ~1a)(iml,/m Price) including this Change Order will be
The Contract Time will be (increased) {decreases) (I,/Achanged) by four (1 ) days.
The date of Substantial Compietion as of the date of this Change Order therefore is August 30 2003
$ 199664.00
$ 1 754.00
$201418.00
$2249.00
$203667.00
NOTE: This Change Order does not include changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have
been authorized by Construction Diredive until the cost and time have been agreed upon by both the Owner and Contrador, in
which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
CONTRACTOR (Firm name)
GOLIS CONSTRUCTION INC.
ADDRESS
~~¡,ID8~~.
BY (Sign ure BY (SIgnature) J . B ~r
-Þ4>....¿ID ~Wl.ct.S g, ~I, 9-
(Typed name) (Typed name). P 711è.,.., (Typ name)
DAVID KOGA TOM GOLIS re I MAYOR
DATE ð..z.8 '",5 DATE B/t,oh> DATE '. Á &.-. (J
r' 'or~ '1Þk4L.' ~-¡4'-""-T""
CAUTION: You should sign an original AlA Contract Document. An original assures changes Wi&t be obscured. . -
W¡P~ 6':;1 CIy°Nv...&<.b&,-2C-O$
@ AlA Document G701 Change Order Electromc Format @ 2001 The Amencan Institute at Architects' www.ala.org . WARNING: Unlicensed
photocopying violates U.S. copyright laws and will subject the violator to legal prosecution. To report copyright violations of AlA Contract
Documents, e-mail The American Institute of Architects' legal counsel. copyright@aia.org. This document was electronically produced with
permission of the AlA and can be reproduced without violation until the date of expiration as noted below. expiration as noted below. expiration
as noted below. expiration as noted below. User Document: changeorder4.ala -- 812812003. AlA License Number 1116B6S, which expires on
12/31/2004.
Electronic Format G701 - 2001
1
GaLlS
CONSTRUCTION. INc.
..
CONSTRUCTION MANAGERS. GENERAL CONTRACTORS
August 12, 2003
David Koga
The Land Group, Inc.
128 South Eagle Road
Eagle ID 83616
Project; Meridian Settler's Restroom
Re; Change Order Request No.5
Dear David,
Attached is a report trom Epoxy Systems on the vapor transmission through the floor slab on the
project. As explained in this report the vapor transmission is higher than the manufacturer
recommends, or will warrant. We propose to apply a penetrant and two ooats of water based
epoxy to lower the vapor transmission through the slab to below the 3 pound threshold. Our
price to do this work is $1849.00. There will be a one day impact to the critical path ofthe
project; therefore we request a one day extension of the substantial oompletion date.
Please issue a change order to our oontract for this amount, or forward a waiver instructing us to
proceed with the epoxy floor installation even with the higher vapor transmission rate.
Sincerely,
Golis Construction, Inc.
~..â:¿¿¿/ I~ yfo¿;'
Thomas B. Golis
President
Telephone 208-93B-4202 . Fax 208-938-4204. P,O. Box 2559. Eagle, Idaho 83616
~ ~,2!d,~
RECEiVED
CONSTRUCTION MANAGERS. GENERAL CONTRACTORS
AUG ¡ 2 2003
August 10, 2003
David Koga
The Land Group, Inc.
128 South Eagle Road
Eagle ill 83616
Project; Meridian Settler's Restroom
Re: Change Order Request No.4
Dear David,
Golis Construction Inc. proposes to install a 7/8" "hat channel" at the bottom chord of the
wooden trusses and delete one of the two layers of 5/8" gypsum board. This was required to
reduce the wooden top plate reveal by ~". Our lump sum price to accomplish this work is
$400.00. There has been a one day impact to the critical path of the project; therefore we request
a one day extension ofthe substantial completion date.
Please issue a change order to our contract as detailed above and if you have any questions please
call me.
Sincerely,
Golis Construction, Inc.
~. 17 ~d:'
Thomas B. Golis, CM
President