TASK ORDER NO. 10193
Between
CITY OF MERIDIAN
AND
CIVIL SURVEY CONSULTANTS, INC.
This Task Order is issued by City and accepted by the Engineer pursuant to the mutual promises,
covenant and conditions contained in the Master Agreement between the above mentioned parties
dated April 13, 2010.
SEWER MAIN REPLACEMENT
SCOPE OF SERVICES
Per the City's request, the Engineer will provide professional engineering services related to the
design of replacing or rehabilitating sections of existing 8" sanitary sewer mains in their current
locations. The locations are as follow:
Located in alley just south of Cherry Lane that is between Meridian Road and Main
Street. Manhole N14-57 to Manhole N14-58. The sewer main turns and runs north
under a building from Manhole N14-48 to Manhole N14-63 located in Cherry Lane.
The section running north will be abandoned and the main in the alley will be
extended west to Meridian Road and then north to Cherry Lane.
2. Existing main runs through the backyards of properties on the west side of NW 4t"
Street from Maple Avenue to the south. Manhole N12-320 to Manhole N12-248.
3. Existing main runs through the backyards of properties on the west side of NW 4t"
Street from Carlton Avenue to the North. Manhole N12-320 to Cleanout N12-344.
4. Located in NW 4t" Street from Washington Avenue to the North. Manhole N14-40 to
Manhole N14-55.
5. Located in alley north of State Street between NE 3~d and NE 4t" Streets. Manhole
N 14-67 to Manhole N 14-50.
6. Located in alley from Meridian Road to Main Street between Broadway Avenue and
Idaho Avenue. Manhole N14-84 to Manhole N14-28.
7. Located in alley west of Meridian Road from Broadway Avenue to Idaho Avenue.
Manhole N12-06 to Manhole N12-323.
8. Located in Bower Street from Main Street to East 2"d Street. Manhole N14-96 to
Manhole N14-97.
9. Existing main runs across private properties from Gem Street to Franklin Road
between Main Street and Meridian Road. Manhole N14-03 to Manhole N14-31. This
site will be evaluated to possibly abandon a portion of the existing main and connect
the existing main to the sewer main in Main Street.
Task 1 -Administration
1.1 This task includes duties associated with setting up the contract and submitting
monthly invoices.
Task 2 -Design Surveying
2.1 This task includes field work associated with performing topographic survey required
to complete the design. Topographic survey will cover existing utilities, irrigation,
pavement, curb, gutter, sidewalk, water meters, and any other items within the public
right-of-way required to complete the design. The City shall contact dig-line and
have the existing utilities marked. It shall be the City's responsibility to obtain
permission from property owners to complete surveying and construction activities on
private property. Engineer will assist city staff with the process of obtaining
permission.
2.2 This task includes office work associated with drafting the topographic survey and
establishing centerline control and the public right-of-way. For the purposes of this
project existing public right-of--way will be established using record of surveys and
subdivision plats recorded with Ada County along with any property corners found
during the topographic survey. Right-of-way or boundary surveys are not included in
the scope of services.
For purposes of this project it is assumed that all existing sewer mains located on
private property are located within an existing easement. Copies of all existing
easement documents will be provided by the City. If no easement documents are
found easements will be required prior to any work on private property. Obtaining
easements for existing sewer lines located on private property is not included in this
scope of work.
Task 3 -Design Sewer Replacement
3.1 This task includes work associated with reviewing the video of the existing sanitary
sewer main to determine the location of existing sewer services and plotting them
on the plans. City shall provide a video of the existing sewer main.
3.2 Determining replacement method and designing sewer replacement.
City staff shall assist the Engineer in determining the preferred method of
replacement. Pipe bursting, sliplining, and open trench methods will be evaluated
to determine the best method of replacing the existing sewer mains. The existing
sewer services will not be replaced and will be reconnected to the new
sewer main. -The existing water meters and service lines will be replaced at
locations identified by the City.
3.3 If existing irrigation facilities are found to be impacted by the project this item will
include preparing and submitting an application for a license agreement to the
appropriate irrigation district. City shall pay all fees associated with the agreement.
3.4 Correspondence and coordination with adjacent property owners regarding surveying
and construction activities on their property. It shall be the Cities responsibility to
obtain permission from property owners to complete surveying and construction
activities on private property. Engineer will assist city staff with the process of
obtaining permission.
Task 4 -Construction Document Preparation and Review
4.1 Develop plans, specifications and bid schedule that meet current design standards
and standard specifications of the City and ISPWC. One complete set of plans,
specifications, and a bid schedule will be developed for each site, except sites 2 and
3 will be combined on one set. Multiple bid schedules may be provided to allow
contractors to bid the project using different methods of replacing the sewer mains.
4.2 Submit one set plans to ACHD for review and approval prior to construction.
Includes one set of revisions per ACHD comments and then resubmitting to ACRD
for approval.
4.3 Submit 2 full size physical copies of plans and special provisions to City
Engineering for Development Services review and approval, Engineer to revise
plans as necessary and resubmit.
4.4 Submit 4 full size physical copies of plans and special provisions to City
Engineering for QLPE review and approval, Engineer to revise plans as necessary
and resubmit.
4.5 Prepare an Erosion and Sediment Control Plan (ESCP) and submit the plan to
the City and ACHD for review and approval. The ESCP will be prepared in
accordance with the City of Meridian Construction Stormwater Management
Program. All other stormwater management program requirements shall be
completed by the City or the Contractor.
4.6 Prepare final construction documents with inclusion of any addenda from the bidding
phase and provide one physical copy for City's use and 10 physical copies for
contractor's use.
Task 5 -Construction Services
5.1 Provide one set of construction stakes for the new sewer mains. A maximum of six
points will be staked at each site. Staking will be completed as requested by the
City and Contractor.
5.2 Attend pre-bid meeting.
5.3 Attend pre-construction meeting.
5.4 Answer RFI's from contractor during bidding and construction about the design.
5.5 Review material specifications submitted by contractor.
5.6 Prepare record drawings meeting the City of Meridian Acceptance of
Record/Electronic Drawings, dated August 26, 2009.
5.7 Send letters to property owners fronting project notifying them of the project and its
anticipated construction schedule. The letter will be submitted City staff for approval
prior to mailing of the letter. City will provide property owner mailing addresses as
needed. This task also includes time responding to telephone calls from property
owners.
TIME OF PERFORMANCE
Engineer will work with City staff to complete construction plans in a timely manner.
COMPENSATION
The Not-To-Exceed amount for this Task Order No. 10193 is One Hundred Twenty-Four Thousand
Seven Hundred Sixty dollars ($124,760.00). The hourly rate for services and direct expenses is
attached and by reference made part hereof.
CITY OF MERI IAN
B ~ .~~
TAMMY de RD, MAYOR
Dated: ~ - l ~ ` ?A ( 0
CIVIL RVEY CONSULTANTS, INC.
BY:
Dated: ~-~3 ~' O
Approved by City Council: ~li s,.~~ l~ ~ oZOI C~ ,
;~ ~'~ ~~ M~'o~q ''-,
o~~T~ b '~,
Attest: C'G ~
- EAL
CEE . HOLMAN, CITY CLERK _ F M
Gs, 1~ ~:
~:, -9O (Is.T 1 S~ , ~~Q~ \.~~
Approved as Conten ~~'%,9 C~U~eI~(t~nt Approv
BY: ttif ii
KEITH ATTS, PURC ING AGENT /~
TITLE: ` r w ~ ~ rce ~-o ~
Dated: ~ ~~ w Dated: 7 ~ a ~' ~Q
Man-Hour And Fee Estimate
City of Meridian-Task Order #10193
Sewer Main Replacement
Site #1
Task Description Project
Mana er Chief
of Surve s Project
En ineer 2 Design
En ineer 1 Survey
Crew Total
Hours Task
Cost
Task 1 -Administration
1.1 Contract and Invoices 2 2 $190.00
Task 2 -Desi n Surve in
2.1 Topo Surve -Field
2.2 To o Surve & Control -Office
16 16 16
16 $2,160.00
$1,520.00
Task 3 -Desi n Sewer Re lacement
3.1 Sewer Video Review & Plottin 1 1 $95.00
3.2 Develo Desi n 2 16 18 $1,730.00
3.3 Irri ation License A reement 2 2 $190.00
3.4 Pro a Owner Correspondence 3 3 $285.00
Task 4 -Construction Documents
4.1 Plans, Specifications, Bid Schedule 3 32 35 $3,355.00
4.2 Plans to ACHD for Review 1 1 $95.00
4.3 Develo ment Services Review 2 2 $190.00
4.4 QLPE Review 2 2 $190.00
4.5 Erosion and Sediment Control Plan 8 8 $760.00
4.6 Final Documents 8 8 $760.00
Task 5 -Construction Services
5.1 Construction Stakin 8 8 $1,080.00
5.2 Pre-Bid Meetin 1 1 $95.00
5.3 Pre-Construction Meetin 1 1 $95.00
5.4 Answer RFI's from Contractors 2 2 $190.00
5.5 Review Material Submittals 2 2 $190.00
5.6 Record Drawin s 4 4 8 $920.00
5.7 Pro ert Owner Letters 4 4 $380.00
Total Man-Hours 5 0 107 0 28 140 $14,470.00
Classification Hours Rate Total
Pro~ect Mana er 5.00 $105.00 $525.00
Chief of Surve s 0.00 $105.00 $0.00
Pro~ect En ineer 1 0.00 $100.00 $0.00
Project En ineer 2 107.00 $95.00 $10,165.00
Desi n En ineer 1 0.00 $85.00 $0.00
Desi n En ineer 2 0.00 $80.00 $0.00
Surve Crew 28.00 $135.00 $3,780.00
Labor Subtotal 140.00 $14,470.00
Classification Each Rate Total
Misc. Printin $300.00
License A reement Fees $300.00
Direct Subtotal $600.00
Subtotal
Total Estimated Fees
$15,070.00
$15;070.00
taskorder10193.x1s
Man-Hour And Fee Estimate
City of Meridian-Task Order #10193
Sewer Main Replacement
Site #2 and #3
Task Description Project
Mana er Chief
of Surve s Project
En ineer 2 Design
En ineer 1 Survey
Crew Total
Hours Task
Cost
Task 1 -Administration
1.1 Contract and Invoices 2 2 $190.00
Task 2 -Desi n Surve in
2.1 To o Surve -Field 20 20 $2,700.00
2.2 To o Sunre & Control -Office 24 24 $2,280.00
Task 3 -Desi n Sewer Replacement
3.1 Sewer Video Review & Plottin 1 1 $95.00
3.2 Develo Desi n 2 40 42 $4,010.00
3.3 Irri ation License A reement 2 2 $190.00
3.4 Pro ert Owner Corres ondence 8 8 $760.00
Task 4 -Construction Documents
4.1 Plans, S ecifications, Bid Schedule 4 40 44 $4,220.00
4.2 Plans to ACHD for Review 1 1 $95.00
4.3 Development Services Review
4.4 OLPE Review 2
2 2
2 $190.00
$190.00
4.5 Erosion and Sediment Control Plan 8 8 $760.00
4.6 Final Documents 8 8 $760.00
Task 5 -Construction Services
5.1 Construction Stakin 8 8 $1,080.00
5.2 Pre-Bid Meetin 1 1 $95.00
5.3 Pre-Construction Meetin 1 1 $95.00
5.4 Answer RFI's from Contractors 2 2 $190.00
5.5 Review Material Submittals 2 2 $190.00
5.6 Record Drawin s 6 6 12 $1,380.00
5.7 Pro ert Owner Letters 4 4 $380.00
Total Man-Hours 6 0 154 0 34 194 $19,850.00
Classification Hours Rate Total
Project Mana er 6.00 $105.00 $630.00
Chief of Surve s 0.00 $105.00 $0.00
Project En ineer 1 0.00 $100.00 $0.00
Project En ineer 2 154.00 $95.00 $14,630.00
Desi n En ineer 1 0.00 $85.00 $0.00
Desi n En ineer 2 0.00 $80.00 $0.00
Surve Crew 34.00 $135.00 $4,590.00
Labor Subtotal 194.00 $19,850.00
Classification Each Rate Total
Misc. Printin $300.00
License A reement Fees $300.00
Direct Subtotal $600.00
Subtotal
Total Estimated Fees
$20,450.00
$20,450.00
taskorder10193.x1s
Man-Hour And Fee Estimate
City of Meridian-Task Order #10193
Sewer Main Replacement
Site #4
Task Description Project
Mana er Chief
of Surve s Project
En ineer 2 Design
En ineer 1 Survey
Crew Total
Hours Task
Cost
Task 1 -Administration
1.1 Contract and Invoices 2 2 $190.00
Task 2 -Desi n Surve in
2.1 Topo Surve -Field
2.2 To o Surve & Control -Office
16 12 12
16 $1,620.00
$1,520.00
Task 3 -Desi n Sewer Re lacement
3.1 Sewer Video Review & Plottin 1 1 $95.00
3.2 Develo Desi n 2 16 18 $1,730.00
3.3 Irri ation License A reement 2 2 $190.00
3.4 Propert Owner Correspondence 0 0 $0.00
Task 4 -Construction Documents
4.1 Plans, S ecifications, Bid Schedule 3 32 35 $3,355.00
4.2 Plans to ACHD for Review 1 1 $95.00
4.3 Development Services Review 2 2 $190.00
4.4 QLPE Review 2 2 $190.00
4.5 Erosion and Sediment Control Plan 8 8 $760.00
4.6 Final Documents 8 8 $760.00
Task 5 -Construction Services
5.1 Construction Stakin 8 8 $1,080.00
5.2 Pre-Bid Meetin 1 1 $95.00
5.3 Pre-Construction Meetin 1 1 $95.00
5.4 Answer RFI's from Contractors 2 2 $190.00
5.5 Review Material Submittals 2 2 $190.00
5.6 Record Drawin s 4 4 8 $920.00
5.7 Pro ert Owner Letters 4 4 $380.00
Total Man-Hours 5 0 104 0 24 133 $13,645.00
Classification Hours Rate Total
Pro~ect Mana er 5.00 @ $105.00 $525.00
Chief of Surve s 0.00 $105.00 $0.00
Pro~ect En ineer 1 0.00 $100.00 $0.00
Project En ineer 2 104.00 $95.00 $9,880.00
Desi n En ineer 1 0.00 $85.00 $0.00
Desi n En ineer 2 0.00 $80.00 $0.00
Surve Crew 24.00 $135.00 $3,240.00
Labor Subtotal 133.00 $13,645.00
Classification Each Rate Total
Misc. Printin $300.00
License A reement Fees $300.00
Direct Subtotal $600.00
Subtotal
Total Estimated Fees
$14,245.00
$14,245.00
taskorder10193.x1s
Man-Hour And Fee Estimate
City of Meridian-Task Order #10193
Sewer Main Replacement
Site #5
Task Description Project
Mana er Chief
of Surve s Project
En ineer 2 Design
En ineer 1 Survey
Crew Total
Hours Task
Cost
Task 1 -Administration
1.1 Contract and Invoices 2 2 $190.00
Task 2 -Desi n Suroe in
2.1 Topo Surve -Field 8 8 $1,080.00
2.2 Topo Surve & Control -Office 12 12 $1,140.00
Task 3 -Desi n Sewer Re lacement
3.1 Sewer Video Review & Plottin 1 1 $95.00
3.2 Develo Desi n 2 16 18 $1,730.00
3.3 Irri ation License A reement 2 2 $190.00
3.4 Propert Owner Correspondence 0 0 $0.00
Task 4 -Construction Documents
4.1 Plans, S ecifications, Bid Schedule 3 32 35 $3,355.00
4.2 Plans to ACHD for Review 1 1 $95.00
4.3 Development Services Review 2 2 $190.00
4.4 QLPE Review 2 2 $190.00
4.5 Erosion and Sediment Control Plan 8 8 $760.00
4.6 Final Documents 8 8 $760.00
Task 5 -Construction Services
5.1 Construction Stakin 8 8 $1,080.00
5.2 Pre-Bid Meetin 1 1 $95.00
5.3 Pre-Construction Meetin 1 1 $95.00
5.4 Answer RFI's from Contractors 2 2 $190.00
5.5 Review Material Submittals 2 2 $190.00
5.6 Record Drawin s 4 4 8 $920.00
5.7 Propert Owner Letters 4 4 $380.00
Total Man-Hours 5 0 100 0 20 125 $12,725.00
Classification Hours Rate Total
Pro~ect Mana er 5.00 $105.00 $525.00
Chief of Surve s 0.00 $105.00 $0.00
Project En ineer 1 0.00 $100.00 $0.00
Project En ineer 2 100.00 $95.00 $9,500.00
Desi n En ineer 1 0.00 $85.00 $0.00
Desi n En ineer 2 0.00 $80.00 $0.00
Surve Crew 20.00 $135.00 $2,700.00
Labor Subtotal 125.00 $12,725.00
Classification Each Rate Total
Misc. Printin $300.00
License A reement Fees $300.00
Direct Subtotal $600.00
Subtotal
Total Estimated Fees
$13,325.00
$13,325.00
taskorder10193.x1s
Man-Hour And Fee Estimate
City of Meridian-Task Order #10193
Sewer Main Replacement
Site #6
Task Description Project
Mana er Chief
of Sunre s Project
En ineer 2 Design
En ineer 1 Survey
Crew Total
Hours Task
Cost
Task 1 -Administration
1.1 Contract and Invoices 2 2 $190.00
Task 2 -Desi n Surve in
2.1 Topo Sunre -Field
2.2 To o Sunre & Control -Office 8 8
0 $1,080.00
$0.00
Task 3 -Desi n Sewer Replacement
3.1 Sewer Video Review & Plottin 1 1 $95.00
3.2 Develo Desi n 2 16 18 $1,730.00
3.3 Irri ation License A reement 2 2 $190.00
3.4 Propert Owner Correspondence 0 0 $0.00
Task 4 -Construction Documents
4.1 Plans, S ecifications, Bid Schedule 3 32 35 $3,355.00
4.2 Plans to ACHD for Review 1 1 $95.00
4.3 Develo ment Services Review 2 2 $190.00
4.4 OLPE Review 2 2 $190.00
4.5 Erosion and Sediment Control Plan 8 8 $760.00
4.6 Final Documents 8 8 $760.00
Task 5 -Construction Services
5.1 Construction Stakin 8 8 $1,080.00
5.2 Pre-Bid Meetin 1 1 $95.00
5.3 Pre-Construction Meetin 1 1 $95.00
5.4 Answer RFI's from Contractors 2 2 $190.00
5.5 Review Material Submittals 2 2 $190.00
5.6 Record Drawin s 4 4 8 $920.00
5.7 Propert Owner Letters 4 4 $380.00
Total Man-Hours 5 0 88 0 20 113 $11,585.00
Classification Hours Rate Total
Project Mana er 5.00 $105.00 $525.00
Chief of Surve s 0.00 $105.00 $0.00
Project En ineer 1 0.00 $100.00 $0.00
Project En ineer 2 88.00 $95.00 $8,360.00
Desi n En ineer 1 0.00 $85.00 $0.00
Desi n En ineer 2 0.00 $80.00 $0.00
Surve Crew 20.00 $135.00 $2,700.00
Labor Subtotal 113.00 $11,585.00
Classification Each Rate Total
Misc. Printin $300.00
License A reement Fees $300.00
Direct Subtotal $600.00
Subtotal
Total Estimated Fees
$12,185.00
$12,185.00
taskorder10193.x1s
Man-Hour And Fee Estimate
City of Meridian-Task Order #10193
Sewer Main Replacement
Site #7
Task Description Project
Mana er Chief
of Surve s Project
En ineer 2 Design
En ineer 1 Survey
Crew Total
Hours Task
Cost
Task 1 -Administration
1.1 Contract and Invoices 2 2 $190.00
Task 2 -Desi n Surve in
2.1 To o Surve -Field 8 8 $1,080.00
2.2 To o Surve & Control -Office 12 12 $1,140.00
Task 3 -Desi n Sewer Re lacement
3.1 Sewer Video Review & Plottin 1 1 $95.00
3.2 Develop Desi n 2 16 18 $1,730.00
3.3 Irri ation License A reement 2 2 $190.00
3.4 Propert Owner Correspondence 0 0 $0.00
Task 4 -Construction Documents
4.1 Plans, S ecifications, Bid Schedule 3 32 35 $3,355.00
4.2 Plans to ACHD for Review 1 1 $95.00
4.3 Development Services Review 2 2 $190.00
4.4 OLPE Review 2 2 $190.00
4.5 Erosion and Sediment Control Plan 8 8 $760.00
4.6 Final Documents 8 8 $760.00
Task 5 -Construction Services
5.1 Construction Stakin 8 8 $1,080.00
5.2 Pre-Bid Meetin 1 1 $95.00
5.3 Pre-Construction Meetin 1 1 $95.00
5.4 Answer RFI's from Contractors 2 2 $190.00
5.5 Review Material Submittals 2 2 $190.00
5.6 Record Drawin s 4 4 8 $920.00
5.7 Propert Owner Letters 4 4 $380.00
Total Man-Hours 5 0 100 0 20 125 $12,725.00
Classification Hours Rate Total
Project Mana er 5.00 $105.00 $525.00
Chief of Suroe s 0.00 $105.00 $0.00
Project En ineer 1 0.00 $100.00 $0.00
Project En ineer 2 100.00 $95.00 $9,500.00
Desi n En ineer 1 0.00 $85.00 $0.00
Desi n En ineer 2 0.00 $80.00 $0.00
Surve Crew 20.00 $135.00 $2,700.00
Labor Subtotal 125.00 $12,725.00
Classification Each Rate Total
Misc. Printin $300.00
License A reement Fees $300.00
Direct Subtotal $600.00
Subtotal
Total Estimated Fees
$13,325.00
$13,325.00
taskorder10193.x1s
Man-Hour And Fee Estimate
City of Meridian-Task Order #10193
Sewer Main Replacement
Site #8
Task Description Project
Mana er Chief
of Surve s Project
En ineer 2 Design
En ineer 1 Survey
Crew Total
Hours Task
Cost
Task 1 -Administration
1.1 Contract and Invoices 0 $0.00
Task 2 -Desi n Surve in
2.1 Topo Surve -Field
2.2 Topo Surve & Control -Office
16 16 16
16 $2,160.00
$1,520.00
Task 3 -Desi n Sewer Replacement
3.1 Sewer Video Review & Plottin 1 1 $95.00
3.2 Develo Desi n 2 16 18 $1,730.00
3.3 Irri ation License A reement 2 2 $190.00
3.4 Pro ert Owner Corres ondence 0 0 $0.00
Task 4 -Construction Documents
4.1 Plans, S ecifications, Bid Schedule 3 32 35 $3,355.00
4.2 Plans to ACHD for Review 1 1 $95.00
4.3 Development Services Review 2 2 $190.00
4.4 OLPE Review 2 2 $190.00
4.5 Erosion and Sediment Control Plan 8 8 $760.00
4.6 Final Documents 8 8 $760.00
Task 5 -Construction Services
5.1 Construction Stakin 8 8 $1,080.00
5.2 Pre-Bid Meetin 1 1 $95.00
5.3 Pre-Construction Meetin 1 1 $95.00
5.4 Answer RFI's from Contractors 2 2 $190.00
5.5 Review Material Submittals 2 2 $190.00
5.6 Record Drawin s 4 4 8 $920.00
5.7 Pro ert Owner Letters 4 4 $380.00
Total Man-Hours 5 0 102 0 28 135 $13,995.00
Classification Hours Rate Total
Project Mana er 5.00 $105.00 $525.00
Chief of Surve s 0.00 $105.00 $0.00
Project En ineer 1 0.00 $100.00 $0.00
Project En ineer 2 102.00 $95.00 $9,690.00
Desi n En ineer 1 0.00 $85.00 $0.00
Desi n En ineer 2 0.00 $80.00 $0.00
Surve Crew 28.00 $135.00 $3,780.00
Labor Subtotal 135.00 $13,995.00
Classification Each Rate Total
Misc. Printin $300.00
License A reement Fees $300.00
Direct Subtotal $600.00
Subtotal
Total Estimated Fees
$14,595.00
$14, 595.00
taskorder10193.x1s
Man-Hour And Fee Estimate
City of Meridian-Task Order #10193
Sewer Main Replacement
Site #9
Task Description Project
Mana er Chief
of Surve s Project
En ineer 2 Design
En ineer 1 Survey
Crew Total
Hours Task
Cost
Task 1 -Administration
1.1 Contract and Invoices 2 2 $190.00
Task 2 -Desi n Surve in
1 To o Surve -Field
2 16 16 $2,160.00
.
2.2 To o Suroe & Control -Office 16 16 $1,520.00
Task 3 -Desi n Sewer Re lacement
3.1 Sewer Video Review & Plottin 2 2 $190.00
3.2 Develo Desi n 4 40 44 $4,220.00
3.3 frri ation License A reement 2 2 $190.00
3.4 Pro ert Owner Corres ondence 2 2 $190.00
Task 4 -Construction Documents
4.1 Plans, S ecifications, Bid Schedule
4.2 Plans to ACRD for Review 6 64
1 70
1 $6,710.00
$95.00
4.3 Develo ment Services Review 3 3 $285.00
4.4 QLPE Review 3 3 $285.00
4.5 Erosion and Sediment Control Plan 8 8 $760.00
4.6 Final Documents 8 8 $760.00
Task 5 -Construction Services
5.1 Construction Stakin 8 8 $1,080.00
5.2 Pre-Bid Meetin 1 1 $95.00
5.3 Pre-Construction Meetin 1 1 $95.00
5.4 Answer RFI's from Contractors 2 2 $190.00
5.5 Review Material Submittals 2 2 $190.00
5.6 Record Drawin s 6 6 12 $1,380.00
5.7 Pro ert Owner Letters 4 4 $380.00
Total Man-Hours 10 0 167 0 30 207 $20,965.00
Classification Hours Rate Total
Pro~ect Mana er 10.00 $105.00 $1,050.00
Chief of Surve s 0.00 $105.00 $0.00
Project En ineer 1 0.00 $100.00 $0.00
Pro~ect En ineer 2 167.00 $95.00 $15,865.00
Desi n En ineer 1 0.00 $85.00 $0.00
Desi n En ineer 2 0.00 $80.00 $0.00
Surve Crew 30.00 $135.00 $4,050.00
Labor Subtotal 207.00 $20,965.00
Classification Each Rate Total
Misc. Printin $300.00
License A reement Fees $300.00
Direct Subtotal $600.00
Subtotal
Total Estimated Fees
$21,565.00
$21, 565.00