HomeMy WebLinkAboutChange Order No 4&5 with Golis Construction for Settlers Park RestroomContract Administration
G701 Change Order
Distribution List:
Owner
Archilect
Contractor
Field
Other
PROJECT (Name and address):
Settler's Park Restroom
CHANGE ORDER NUMBER:.@
DATE: August 28 2003
TO CONTRACTOR (Name and address):
Golis Construction PO Box 2559 Eagle
1083616
ARCHITECT'S PROJECT NUMBER: 02180
CONTRACT DATE:ADriI28 2003
CONTRACT FOR: Restroom Building
THE CONTRACT IS CHANGED AS FOLLOWS:
(tndude, where applicable, any undisputed amount attributable to previously executed Construction Change Directives)
C.O. #4 Revised ceiling finish - see attached letter from Golis Construction 8-10-03.
C.O. #5 Apply a penetrant and two coats of water based epoxy 10 lower vaoor transmission in concrete slab.
The original (Contract Sum) (GI,/aranleeà ~1axim1,Jm Price) was
The net change by previously authorized Change Orders
The (Contract Sum) (Guarantees MaJdml,/m Prke) prior to this Change Order was
The (Contract Sum) (Guarantees MaJ(imum Price) will be (increased) (decreased) (unchanged)
by this Change Order in the amount of
The new (Contract Sum) (Guarantees ~1aJ:iml,/m Prke) including this Change Order will be
The Contract Time will be (increased) (decreases) (uRd'laRgeà) by four (1 ) days.
The date of Substantial Completion as of the date of this Change Order therefore is Auausl 30 2003
$ 199664.00
$ 1.754.00
$201418.00
$2249.00
$203667.00
NOTE: This Change Order does not include changes in the Contrad Sum, Contract Time or Guaranteed Maximum Price which have
been authorized by Construction Diredive until the cost and time have been agreed upon by both the Owner and Contractor, in
which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
ARCHITECT (Firm name)
THE LAND GROUP INC.
ADDRE S
1 SE G
@ AlA Document G7C1 Change Order ElectronIC Format @ 20Cl The American Institute at Architects' www.ala.org . WARNING: Unlicensed
photocopying violates U.S. copyright laws and will subject the violator to legal prosecution. To report copyright violations of AlA Contract
Documents, e-mail The American Institute of Architects' iegai counsel. copyright@aia.org. This document was electronically produced with
permission of the AlA and can be reproduced without violation until the dale of expiration as noted below. expiration as noted below. expiration
as noted below. expiration as noted below. User Document: changeorder4.aia -. 8/28/2003. AlA license Number 111686S, which expires on
12131/1004.
Electronic Format G701 - 2001
1
CONSTRUCTION MANAGERS. GENERAL CONTRACTORS
GaLlS
CONSTRUCTION. INc.
August 12,2003
David Koga
The Land Group, Inc.
128 South Eagle Road
Eagle ID 83616
Project; Meridian Settler's Restroom
Re; Change Order Request No.5
Dear David,
Attached is a report 1Ì'om Epoxy Systems on the vapor transmission through the floor slab on the
project. As explained in this report the vapor transmission is higher than the manufacturer
recommends, or will warrant. We propose to apply a penetrant and two coats of water based
epoxy to lower the vapor transmission through the slab to below the 3 pound threshold. Our
price to do this work is $1849.00. There will be a one day impact to the critical path of the
project; therefore we request a one day extension of the substantial completion date.
Please issue a change order to our contract for this amount, or forward a waiver instructing us to
proceed with the epoxy floor installation even with the higher vapor transmission rate.
Sincerely,
Golis Construction, Inc.
/4ø¿p/ 4. Ao?
Thomas B. Golis
President
Telephone 208-938-4202 . Fax 208-938-4204 . P,O. Box 2559 . Eagle, Idaho 83616
GaLlS
CONSTRUCTION. INc.
RECEiVED
CONSTRUCTION MANAGERS. GENERAL CONTRACTORS
AIJG 1 221m3
August 10, 2003
David Koga
The Land Group, Inc.
128 South Eagle Road
Eagle ID 83616
Project; Meridian Settler's Restroom
Re: Change Order Request No.4
Dear David,
Golis Construction Inc. proposes to install a 7/8" "hat channel" at the bottom chord of the
wooden trusses and delete one of the two layers of 5/8" gypsum board. This was required to
reduce the wooden top plate reveal by W'. Our lump sum price to accomplish this work is
$400.00. There has been a one day impact to the critical path of the project; therefore we request
a one day extension of the substantial completion date.
Please issue a change order to our contract as detailed above and if you have any questions please
call me.
Sincerely,
Golis Construction, Inc.
~. 17 ~¿,.
Thomas B. Golis, CM
President
Telephone 208-938-4202 . Fax 208-938-4204 . P,O. Box 2559 . Eagle, Idaho 83616