HomeMy WebLinkAboutChange Order No 1 with Ewing Company for WWTP Thickener PROJECT CHANGE ORDER No.J Citv of Meridian WWTP. Dissolved Air Flotation Thickener Project EFFECTIVE DATE Aul!ust 27. 2003 DATE OF ISSUANCE Aul!ust 27.2003 OWNER Citv of Merdian OWNER=s Contract No. CONTRACTOR Ewinl! Companv ENGINEER Carollo Enl!ineers You are directed to make the following changes in the Contract Documents. Description: Remove underground diesel tank per WCD No. 03. Provide miscellaneous utility surveying as requested with yard piping modification in Field Order No.5 Reason for Change Order: Unforeseen underground utility conditions at the time of design and bidding. Attachments: Price quotation letter from Ewing Company dated August 5, 2003. CHANGE IN CONTRACT PRICE: Original Contract Price $ 809.500.00 CHANGE IN CONTRACT TIMES: Original Contract Times Substantial Completion: 270 Davs - November 21 2003 Ready for final payment: 300 Davs - December 26 2003 d","""", Net Cbanges from previous Cbange Orders No- .lL to No. ..Q $ 0 Net Changes from previous Change Orders No- ~ to No. ~ 0 Contract Price prior to this Change Order Contract Times prior to this Change order $ 809.500.00 Net Increase (decrease of this Change Order) $ 21.820.61 D'" Substantial Completion: 270 Davs - November 21 2003 Ready for final payment: 300 Days - Decemver 26 2003 d","""", Net Increase (decrease of this Change Order) 0 Calendar Davs "'" Contract Price with all approved Change Orders $ 831.320.61 Date: Contract Times with all approved Change Orders Substantial Completion: 270 Davs - November 21. 2003 Ready for final payment: 300 Days - December 26 2003 d",",d"" "'~/"'{/~"'.E ~~: 25 2~83761481 ~ '- EWING CO August 5, 2003 Carollo Engineers 12952 W. Explorer Dr., Suite 200 Boise, ID 83713 Atm: William Benko Re: Dissolved Air Flotation Thickner Asphalt patch Remove diesel tank Install new 2" black iron fuel line Install new tank & concrete curb also survey for pipes in ground These are the Items we are addressing. Pump & Clear tank Ramove tank Soli Test New tank Unload & Sellank spur containment curb New 2" black iron line Survey for pipe as built of existing Attachments ,-..- Terra-West Terra-Wes! Terra-West 181 The Ewing Co., Inc. The Ewing Co., lnc, Lacy Mechanical Not to exceed The Ewing Co., Inc, OH & Pfofit $ 360.00 $ 4,862.00 $ 1,836.00 $ 4.300.42 $ 700.aO $ 328.11 $ 1,395.00 $700000 $20,781.53 S 103908 $21,820.61 PAGE 02