Loading...
HomeMy WebLinkAboutTask Order No. 10008A with DC Engineering, Inc. for Tertiary Filter and DAFT Retrofit SCADA~~i~E IDIAN~ Public IDAHO Works Department TO: Mayor Tammy de Weerd Members of the City Council FROM: Clint Dolsby, Assistant City Engineer DATE: 10/29/09 Mayor Tammy de Weerd C~v Ceanail Mem6erq Keith Bird Brad Hoaglun Charles Rountree Datiid Zaremba SUBJECT: TASK ORDER 10008A FOR TERTIARY FILTER AND DAFT RETROFIT SCADA PROGRAMMING I. RECOMMENDED ACTION A. Move to: 1. Approve Task Order 10008A with DC Engineering, Inc for the Tertiary Filter and DAFT Retrofit SCADA Programming pursuant to the Master Agreement executed December 12, 2006 for anot-to-exceed cost of $22,000. 2. Authorize the Mayor to sign the agreement. II. DEPARTMENT CONTACT PERSONS Place names, titles, and phone numbers of the Persons involved in Descending Order: Tom Barry, Director of Public Works 489-0372 Warren Stewart, PW Engineering Manager 489-0350 Clint Dolsby, Asst. City Engineer (Project Manager) 489-0341 III. DESCRIPTION A. Background The Wastewater Division of the Public Works Department has made an effort over the last several years to automate operations at the wastewater plant and in the collection system. This has resulted in more efficient ope tions at the Pagel of3 - ~ ~ --- K: / v wastewater treatment plant and early identification of issues at the plant and in the collection system. B. Proposed Project This task order will provide programming for the Tertiary Filter and DAFT Retrofit projects in order to automate operations of those components of the wastewater treatment plant. C. Consultant Selection The consultant selected for this project chosen due to their familiarity with the projects and SCADA system at the wastewater treatment plant. IV. IMPACT A. Strateig c Im acct: This activity aligns with our department's vision of having our information centralized and our processes streamlined and automated. B. Service/Delivery_pact: This task order will automate the operation and add alarms for the Tertiary Filters and DAFT Retrofit projects at the wastewater treatment plant. It will increase the efficiency by which the plant staff identify issues at the plant and monitor plant operations. C. Fiscal Impact: Project Costs Consultant Agreement Time and Materials Not-to-exceed $22,000 Total Time and Materials Not-to-exceed $22,000 Project Funding Project will be funded from WWTP Consulting (3500-55103) $22,000 V. ALTERNATIVES A. The City could choose not to approve this task order to complete the SCADA Programming for the Tertiary Filter and DAFT Retrofit projects. This would result in a lack of automation for these components of the wastewater treatment plant and may require the addition of operators to the graveyard shift. Page 2 of 3 B. The City could put out an RFP for these services to select a consultant for the SCADA programming for the Tertiary Filter and DAFT Retrofit Projects. This may be more costly since DC Engineering is familiar with these projects and has been involved in the design and office services for both jobs and would delay the task order a couple of months. VI. TIME CONSTRAINTS Council's approval will allow the wastewater treatment plant to remain automated which enables the plant to be unmanned during the graveyard shift. VII. LIST OF ATTACHMENTS A. Task Order 10008A with DC Engineering, Inc Tertiary Filter and DAFT Retrofit SCADA Programming Approved for Council Agenda: Tom Barry, Director of Public Works Date Page 3 of 3 -,~..-w ~E IDI~ IAN-- ~J PURCHASING AGENT 33 E. Broadway Ave, Meridian, ID 83642 Phone: (208) 888-4433 x 417 Fax: (208) 887-4813 TASK ORDER NO. 10008A Between CITY OF MERIDIAN AND DC Engineering This Task Order is issued by City and accepted by the Engineer pursuant to the mutual promises, covenant and conditions contained in the Master Agreement between the above mentioned parties dated December 12, 2006. Tertiary Filter Project SCADA Programming Task Order SCOPE OF SERVICES Project Understanding This project will include the programming of the PLC, WonderWare and SQL Server to support the Tertiary Filter Upgrade project at the Meridian Waste Water Treatment Plant. Programming will be completed as described on the P&ID's that were developed during the design phase of this project. Also included is the programming of the PLC, WonderWare and SQL Server to support the Chemical feed, and DAFT Retrofit projects. Services Provided • Meet with plant staff to determine SCADA screen requirements. • Coordinate PLC interface with new equipment suppliers. • Complete the PLC programming as required. • Factory Acceptance test of the PLC and Remote I/O Panels as required. • Complete the WonderWare and SQL Server programming. • Commissioning of the new equipment as construction is completed. • Provide SCADA training for plant staff upon completion of project. Deliverables • Electronic copies of all PLC and WonderWare programs used for the project. • Hard copies of all PLC programs used for the project. ~~ ,,1. MIME OF PERFORMANCE DC Engineering has a capable staff that can start immediately. The project is expected to be completed by May 1, 2010, however the actual completion date is dependant on the substantial completion of the Tertiary filter construction project. COMPENSATION The project will be performed on time and material basis not to exceed $22,000 (Twenty Two Thousand Dollars). CITY OF MERIDIAN BY TAMMY de W RD, MAYOR DC Engineering BY: Dated: ~ ~ ~ o~~ " ~~ ,,,, Dated: 10/28/09 Approved by City Council: Attest: JA1'tOEEQ.! HOLMAN. CITY ~,+u u~ri,~~ ,y ~ ~ o~ ~~io,`'%,,, ~~ ~'i '~• ` T '; F O ~~ ~ 9 ~~®~ O Approved as to C ntent /~~~'~,,9 C'pU~ . ~~`~~artment Approval BY: KEITf~ATTS, PU14CH/~TNG AGENT ~ _ ~ ~, Dated: ~ ~ ' ~ ~ ~ ~~ TITLE: SS~`~ta ~~J,~,ina~tr Dated: »~3v~e~