HomeMy WebLinkAboutChange Order No. 1 with Hillside Landscape for Heroes Park Phase 3 ConstructionCITY OF MERIDIAN 33 EAST BROADWAY AVE. MERIDIAN, ID 83642 CONTRACT CHANGE ORDER Change Order No.: 1 Project Number. PK-09-10078 Date: 10/30/2009 Effective Date: 10/30/2009 CONTRACTOR: Hillside Landscape Construction PROJECT: Heroes Park Phase 3 (Construction) The Contractor is hereby directed to make the following changes from the Contract Documents and Plans. Desciption: Amount wcD No.1) Additional 260 LF of concrete edging to the playground areas. $3,380.00 $3,380.00 Reason for Change Order: wcD No.1) To provide better support for the concrete surfacing bordering the playground surfacing. This will increase the longevity of both surfaces. Attachments: WCD No. 1. CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price: $1,054,353.60 Original Contract Completion Date: ~ ~ - I (~ - D Original Contract Completion Days: Net changes form previous C.O.'s.: Net Days change form previous C.O.'s: No. 0 to 0 No. 0 to 0 $0.00 Contract Price Prior to this C.O.: Contract Completion Date before this C.O.: $1,054,353.60 ~ " ~ ' Net Increase (decrease) of this C.O.: Net Days Increase (decrease) of this C.O.: $3,380.00 Contract Price with all Approved C.O.'s: Contract Completion Date with all Approved C.O.'s: $1,057,733.60 - ~ RECOMMENDED: (CITY CAPITAL PROJECTS MANAGER) Date: ~ ~. ACCEPTED (CITY DIVISION REPRESENTATIVE) AC P D ( RACT R) `\~~~~``~ ~ ~~,~~,`, By: '~' ~. ~' ~pqp~ By: r F ~ ~ Date: I~, a t- 0 Date: ~ ~ 0 •Q ~ .. APPROVED: (CITY PU C ING AGENT) COUNCIL APPROVAL _ ~~~~ _ By: Keith Watts ~ 7 ~ ~` ~Z~ ~•~ ~, ,~ o ~` T 1 S't • .r .~ '. ~ Date: ~ ~ _ ' -7 _ Q ` ,9 Date: ~ ~~ ~ APPROVE~ITY MAYOR) ATTEST: (CITY CLERK) ~~ii, ~~~~ By: Mayor Tammy d eerd By: City Clerk, Jaycee Holman Date: ~~ ' Z~ ~ (~ Date: 1 ~ ~Z~ - ~ I + Cl'fY OF MERIDIAN Heron Pads Phase 3 Constnretion ADA COUNTY, IDAHU WORK CHANGE DIRECTIVE No. DATE OF ISSUANCE _9-04-09 EFFECTIVE DATE 9-04-09 OWNER Cityy of Meridian CONTRAZ~tOR Hillside Landscape Construchon Contract: Heroes Park Phase 3 Project: heroes Park Phase 3 O~EI~ S Contract No. PK09-1 78 ENGINEER s Project No. ,NA You are directed to proceed promptly with the following change(s): Description; install an additional estimated 260 LF of concrete edging (per detail 8 on sheet LS-5) to the playground areas detailed on sheet LS-5. The concrete surfacing area and dimensions are to remain the same. Add the concrete edging towards the playground surfacing side of the concrete surfacing area. At the 2-S year playground area: add the concrete edging to the north, west, and east side of the playground surfacing where it meets the concrete surfacing. At the 5-12 year playground area: add the concrete edging to the north and west side of the playground surfacing where it meets the concrete surfacing. Purpose of Work Change Directive: Provide better support for the concrete surfacing bordering the playground surfacing. This will increase the longevity of both surfaces. Attachments: (List documents supporting change) Email from Hillside Landscape Construction. If OWNER or CONTRACTOR believe that the above change has affected Contract Price any Claim for a Change Order based thereon will involve one or more of the following methods as defined in the Contract Documents. Method of determining change in Contract Price: ^ Unit Prices ^ Lump Sum ^ Cost of the Work Estimated increase (decrease) in Contract Price: $$3,380.00 If the change involves an increase, the estimated amount is not to be exceeded without further authorization. Estimated increase (decrease) in Contract u Times: Substantial Completion: days; Ready for final payment: days. RECOMMENDED: OWNER (~ROJE~f-1~OT~Mi4GER) OWNLR (I~EP RTMEIVT'I2EPRE~ gy. -- S By: „~. ~ . EJCD No. 1910-&F (I 996 Edition) Prepared by the Engineers Joint Comract Docimiems Committee and endorsed by The Associated General Contiacrors of America aad iha Institute. .. Max Jensen Page 1 of 1 From: Cliff Yochum [CliffQhillsideco.com] Sent: Tuesday, September 01, 2009 3:37 PM To: paulQharvestdesign.ty; Shannon Yochum; Bob Harris Cc: Max Jensen; Elroy Huff Subject: RE: Heroes, add service proposal PR #03 PR #03: add 2fi0' linear feet of concrete edging per detail LS-5, #8 - $ 3,380.00 If you could let us know by Thursday afternoon on this we can plan our excavation accordingly. Thanks, Cliff Yochum From: Paul W. Norberg [mailto:paul@harvestdesign.ty] Sent: Tuesday, September 01, 2009 2:42 PM To: ClifF Yochum; Shannon Yochum; Bob Harris Cc: 'Max Jensen'; 'Elroy Huff Subject: Heroes, add service proposal Cliff: I reviewed the design for the playground area with Max and Elroy this morning, they are interested In obtaining a price from you to install the edging, shown in (lS-5, If8) at all of the edges where currently the 4" slab creates the edge. This would beat both sides of the playground (2-S area) and (5-12 area). I measure about 260 lineal feet. You will need to confirm that amount. We discussed a ramp and Elroy stated that he did not want one. Thanks, Paul ~f ar'/ast ~esti~s' Paul W. Morberg, Landscape Architect :?9%] E. C.oi~~~r f~ntrt! [?r. - `_~uite 1.50 hi~rtdi~n: In ~;3ii=i ~aul~harvestdesign.t_v_ www.haryestdesign.ty 9/4/2009