HomeMy WebLinkAboutTask Order No. 10018a with CH2M Hill, Inc. for Additional Office Services and Contruction Staking~~i~E IDIAN~-
Public IDAHO
Works Department
TO: Mayor Tammy de Weerd
Members of the City Council
FROM: Clint Dolsby, Assistant City Engineer
DATE: 10/02/09
Mayor Tammy de Weerd
cnn eoonau Member
Keith Bird
Brad Hoaglun
Charles Rountree
David Zaremba
SUBJECT: TASK ORDER 10018a for ADDITIONAL OFFICE SERVICES AND
CONSTRUCTION STAKING
I. RECOMMENDED ACTION
A. Move to:
1. Approve Task Order 10018a with CH2M HILL for Additional Office
Services and Construction Staking for the Bittercreek Lift Station and
Pipelines Project, for anot-to-exceed cost of $44,300.
2. Authorize the Mayor to sign the agreement.
II. DEPARTMENT CONTACT PERSONS
Place names, titles, and phone numbers of the Persons involved in Descending Order:
Tom Barry, Director of Public Works 489-0372
Warren Stewart, PW Engineering Manager 489-0350
Clint Dolsby, Asst. City Engineer (Project Manager) 489-0341
III. DESCRIPTION
A. Background
The Bittercreek Lift Station and Pipelines Project will provide sewer service and
fire flows to the Bittercreek subdivision. This lift station is expandable to serve
additional developments in the future. The wastewater lift station is located near
the intersection of Amity and Lindy Roads adjacent to the Bitter Creek
development. The pipelines include new dual sanitary sewer force mains (6- and
~® o
Page 1 of 3
10-inch diameter), a new 21-inch diameter gravity sanitary sewer pipe and a new
16-inch potable water main.
B. Proposed Project
This task order will enable CH2M HILL to provide additional office support
services for the Bittercreek Lift Station and Pipelines Project Construction
Project. Their scope of services has increased from submittal review to include
construction staking, site visits including attendance an onsite meetings and an as-
built survey of the gravity sanitary sewer and lift station wet well.
C. Consultant Selection
The consultant selected for this project was procured for the design and office
supports services to date. This consultant was chosen due to their familiarity with
the project and quality of the work they have completed on this project.
IV. IMPACT
A. Strategic Impact:
This activity aligns with our department's mission of providing modern and
reliable facilities.
B. Service/Deliver~ acct:
Currently, the Bittercreek Subdivision utilizes a City Well for water supply and
lagoons for wastewater treatment. The well does not supply adequate fire flows
to the homes in this subdivision. The completion of the Bittercreek Lift Station
and Pipelines Project will provide City sewer services and fire flows to the
Bittercreek Subdivision.
C. Fiscal Impact:
Project Costs
Consultant Agreement Time and Materials Not-to-exceed $44,300
Total Time and Materials Not-to-exceed $44,300
Project Funding
Project will be funded from lift station construction (3590-96144) $44,300
V. ALTERNATIVES
A. The City could defer this task order which would likely result in delays in the
construction schedule and/or additional change orders for the construction
project. Outcomes of these delays could manifest in standby changes from the
Page 2 of 3
contractor, extension of contract times, demobilization and remobilization
expenses and other associated fees. This alternative would greatly limit the
ability to complete this project.
B. City staff could work with JLJ Enterprises and their selected representative,
The Land Group, to incorporate selected tasks outlined in the task order into
their scope of work. Since the Land Group was not the design engineer on this
project and has not been actively involved in the construction management to
date, this would likely result in more coordination, staff hours, and potentially
higher fees from the Land Group to perform this work since they would first
need to get up to speed with the project.
VI. TIME CONSTRAINTS
Council's approval will allow the continued office support services for the
construction project.
VII. LIST OF ATTACHMENTS
A. Task Order 10018a with CH2M HILL for Additional Office Services and
Construction Staking for the Bittercreek Lift Station and Pipelines Project.
Approved for Council Agenda: ~~jG ~ ~ 2 Z b
~1y1. Tom Barry, Director of Public Works Date
Page 3 of 3
TA5K ORDER NO. 10018a
UNDER THE
MASTER AGREEMENT FOR PROFESSIONAL SERVICES
BETWEEN
CITY OF MERIDIAN AND CH2M HILL, INC.
This Task Order is entered into by and between City of MERIDIAN (OWNER) and CH2M HILL,
Inc. (ENGINEER), according to the terms and conditions of the Master Agreement (AGREEMENT)
for Professional Services, dated January 1, 2007.
See Attachments A and B for the Scope and Fee for Task Order 10018a.
All other terms and conditions of the original agreement will remain in full force and effect.
IN WITNESS WHEREOF, the parties execute below:
For CH2M HILL, Inc.
dated this ~~ day of 2009.
By: /,Gl~r~~~i~;~-/
Name
For City of Meridian
dated this ~ day of
,~
By:
Tammy de~OV~erd, Mayor
~C// ,
Attest:
Ja e Ho ,City k
Approved By City Council: Iv~~~c
P ai
Public Works
Title
2009.
,,
~ ~ s
r o
~ ~'
O '~ d ~:
'--,,'9 r Est ~,r ~,.
,~
y, Zoe ~~,,,,~,,,~-~~~~ •~~'.
I Dq'
Dat
~Ig~~
Date
Task Order 10018a
Attachment A
Additional Office Services and One-Time Construction Staking
Project Understanding
The City of Meridian (City) would like CH2M HILL to perform additional office services,
initial (one-time) construction staking as requested by Eastern Oregon Construction, LLC
(Contractor), and an as-built survey of the gravity sanitary sewer and lift station wet well in
support of the Bitter Creek Lift Station and Pipelines project. The additional office services
provide for expanded support to City staff based on efforts performed to date and
anticipated future efforts. The wastewater lift station is located near the intersection of
Amity and Lindy Roads adjacent to the Bitter Creek development. The pipelines to be
staked include new dual sanitary sewer force mains (6- and 10-inch diameter), a new 21-
inch diameter gravity sanitary sewer pipe, seven (~ new sanitary sewer manholes, and a
new 16-inch potable water main. The dual sanitary sewer force mains and gravity pipe
portion originate at the new lift station, run north to Amity Road, thence east along Amity
Road to the intersection with W. Ten Mile Road, thence north along W. Ten Mile Road to
terminate at the new Overland Road re-alignment (new intersection for the Southridge
development) for a total combined length of approximately 2.7-miles. The potable water
main originates by the W. Amity Road and S. Nickel Creek Place intersection, run east along
Amity Road to the intersection with W. Ten Mile Road, thence north along W. Ten Mile
Road to terminate at the new Overland Road re-alignment (new intersection for the
Southridge development) for a total length of approximately 2.1-miles.
The additional office services, as described in the Scope of Work below, shall be added to
the original Task 2 -Office Engineering Services. The initial, one-time construction staking
and the as-built survey, as described under Scope of Work shown below, shall be added to
the original Task 3 -Field Services. Additional management of this expanded task shall be
added to the original Task 4 -Project Management.
If required, re-staking will be performed under a separate contract directly with Eastern
Oregon Construction, LLC, subject to their review and execution.
Scope of Work
CH2M HILL will perform the tasks for added office services, one-time construction staking,
and the as-built survey in support of the Bitter Creek Lift Station and Pipelines as outlined
below.
Task 1 -Office Engineering Services
CH2M HILL office personnel will provide additional contract document reproduction
services and coordination among the City, the Contractor, and the private Developer's
Project Manager based on requests and inquiries received from the aforementioned parties
outside of weekly construction progress meetings. Services include additional telephone
conference calls, project meetings, contract document research, and other related tasks.
Task 2 -Field Services
2A. Additional Field Observations and Meeting Attendance
CH2M HILL personnel will make additional site visits to conduct field observations and
attend additional on-site meetings. (10 trips at 3 hours total including travel time)
2B. Construction Staking
Survey crews and office personnel will be responsible for the initial, one-time construction
staking for each major project element as outlined below:
Waterline Staking
Stake centerline and angle points using 48-inch lath & hub consisting of approximately 15
points + with offsets to centerline; placement of intermediate intervisable points along offset
line at 400-foot intervals 28 points +; placement of hydrants at centerline and on offsets of
about 18 points for a total of about 61 points. (20 crew hours estimated)
Sanity Sewer Force Main
Stake and grade centerline of trench for 11,768 linear feet of sewer force main centerline
points with offset 36 + grade breaks and 24 angle points and a m;n;mum of 10 intervisable
intermediate points. 36+ up 1 grade brakes. 140 points total. (40 crew hours estimated)
Gravity Sanitary Sewer Line
Stake and grade ~2,6701inear feet of gravity sewer line consisting of 7 manholes with swing
tie offsets cut and fill inverts in and out. 21 points with one intermediate point between
manholes, 7 points, for a total of 28 points. This also requires differential leveling. (20 crew
hours estimated)
Domestic Wastewater Lift Station
Stake and offset pump station building corners, fence corners, and valve vault. 16 to 30
points. (10 crew hours estimated)
Office Calculations and Field Pre ary ation
Prepare calculations, review plans, and office preparation. (16 office hours estimated)
Field Grading
Create cut sheets, check and review cut and fill against plans. (16 office hours estimated)
ExUenses
Miscellaneous survey supplies, paint, lath, hubs, and flagging.
2C. As-Built Survey (Partial)
The survey work described below shall be performed by a subcontractor, Critigen.
Expenses related to the surveying effort are reflected in the amount shown in Attachment B.
Survey crews and office personnel will be responsible for collecting and processing field
data to determine the horizontal and vertical as-built conditions of the gravity sanitary
sewer (7 manholes along approx. 2,7601E of pipe) and the lift station wet well. This survey
effort will be based on a one-time collection of the field data with two mobilizations
required to collect the gravity sewer and wet well data on separate trips. (24 crew hours
estimated, 8 office hours estimated)
Expenses
Travel.
Task 3 -Project Management
• Supervising project staff;
• Project documentation and coordination;
• Monitoring project progress, including work completed, work remaining, budget
expended, schedule, estimated cost of work remaining, and estimated cost at
completion;
• Monitoring project activities for potential changes, anticipate changes when possible,
and with Owner approval, modify project tasks, budgets, and approach;
• Preparing and submitting a monthly billing with backup documentation;
• Performing project quality control reviews of deliverables on this project.
Assumptions
• CH2M HILL will provide one time staking on the above items.
• CH2M HILL will be given a minimum of 24-hour notice for staking requests.
• Survey control set previously by CH2M HILL still exists.
• Duration estimates for construction staking based on nine (9) mobilizations with 10-hour
days.
• Traffic control will not be required and will not be provided by CH2M HILL.
• Offset placement will be coordinated with and approved by the Contractor.
• CH2M HILL is not responsible for replacement of damaged or removed staking under
this contract caused by Contractor, others, or vandals.
Exclusions
• Any additional as-built surveying for record drawings, not specifically described in this
Scope of Work, is not included as part of this scope and will be prepared by the
Contractor.
Attachment B
Compensation
Level of Effort
The task level of effort estimates are summarized in the following table. CH2M HILL has
developed this level of effort estimate based on the work plan presented herein and
assumptions stated previously. The fees will be billed as time and material, and will not
exceed the total amount below without prior approval by the City.
Level of Effort
Task Description Total Task
1 Office Engineering Services $3,600
2 Field Services -Additional Site Visits & Meeting Attendance $4,300
Field Services -Construction Staking $25,800
Field Services - As-built Survey (partial) $6,200
3 Project Management $4,400
Summary -All Tasks $44,300
Schedu/e
Initial staking will commence the week of August 10, 2009 as requested by the Contractor
and will continue through the duration of the project until all staking described herein has
been performed once.