HomeMy WebLinkAbout2009 06-29 Joint ACHDMeridian Citv Council Special Joint Meeting June 29. 2009
The Meridian City Council special meeting was called to order at 10 a.m. on
Monday, June 29, 2009, by Mayor Tammy de Weerd.
Members Present: Keith Bird, David Zaremba, Charlie Rountree and Brad
Hoaglun.
City Staff: Staff Present: Jaycee Holman, Brent Bjornson, Tom Barry, Anna
Canning, Matt Ellsworth, Bill Nary.
ACHD Commissioners Present: John Franden, Sherry Huber, Rebecca Arnold,
Sara Baker, Carol McKee.
ACHD Staff: J. Schweitzer, Steve Price, Sally Goodell, Mike Brokaw, Bruce
Mills, Gary Inselman, Christy Little, Adam Zaragoza, Susan Slaughter.
Roll-call Attendance:
Roll call.
X David Zaremba X Brad Hoaglun
X Charlie Rountree X Keith Bird
X Mayor Tammy de Weerd
Item 1. ACHD's Cost Share Policy:
Goodell: Mayor and Council Members, Commissioners I am trying to run through
this with a Power Point presentation - in the fall last year when we were going
through kind of from joint meeting to joint meeting and the alliance meetings
doing an overview, there were issues more pressing from your perspective, so
this particular -the overview portion of this did not get put on a joint agenda, but
I will try to go through it pretty quickly. Your staff has been looking at this for a
long time. What I would like to do is stress the things that Caleb gave me, which
is how the cost share would work in the project process and some specific
questions that were in that memo. We started this exercise back in January or
no July 24, 2008 when we provided the first draft to the local governments. The
purpose of the interagency cost share policy is to set up a policy that is
consistent with our statutory authorities. It is really striving to establish some
equity among the cities. So what we provide from community to community is
reasonably consistent. We have several recent projects that we use as a model
for how to sort of structure this effort and it is important to emphasize that it
primarily focuses on ACHD's projects -those projects that we are going to
construct. It is an entirely different scenario when you have developers building.
Generally what the cost sharing policy does is it breaks the world up into
transportation components and non transportation components for a road project.
ACHD is responsible for roadway, for basic bike lanes, basic pedestrian zones
and safety medians and I will talk about what that basic pedestrian zone is in a
minute in a little more detail. The city or county would be responsible for
landscaping installation, maintenance, enhanced bicycle and pedestrian facilities
that you might seek because of the special land or unique land use situation,
aesthetic treatments in medians or other aesthetic amenities. The basic
pedestrian facility that ACRD would provide would be a two and one half foot
hardscaped pedestrian (inaudible) outside the curb and then a five foot sidewalk.
That can be configured in any variety of ways, but in all cases we would provide
that. Or, if the city is interested in installing landscape, ACHD has offered to
purchase up to six feet of right of way for the buffer. So, ACHD would purchase
that extra 3'/z feet and then install the 5 foot sidewalk behind that and the thing
that ACHD is seeking is for the partner, city or county or whatever the
circumstances is to both install landscape and very important to maintain it
because that is not sort of within our area of expertise if you will. I know the City
of Meridian does a lot with development in terms of where to set the sidewalks
and how to create setbacks and we can certainly work with you all around that in
terms of what your specific interests are in any particular road. We did take look
at landscaping and hardscaping and what the costs typically are for kind of a full
treatment if you will - we use the Meridian Split Corridor - we used the Hill Road
extension and we looked at I think it was Five Mile, Ustick to Linder where we
have done -excuse me, Five Mile (inaudible) where we have done a little bit of
estimating and if you do kind of a full treatment for a mile and that includes
signage and lighting and landscaping and whatnot it could go up to about
$650,000 a mile. In order to talk about how this works in the project process I
just want to introduce a little bit of language in the way that we use it -projects
start out in the planning phase in our capital improvement plan, in the five year
work plan or through community planning programs or other sources. Most
projects go into the five year work plan before we start working on them. While
they are in the five year work plan, we go out and do scoping and scoping is a
point where we just take a hard look at the project and try and define what is this
project really going to look like, what is it going to be and come up with a cost
estimate. A lot of times we have to establish assumptions that is based just on
existing information and those assumptions change when we get into design.
That sculpting sets the base line from which we start to evaluate as we go
forward. The next step we take is now concept design. Concept design may be
a separate phase of the project for complex projects or we may just have a
design step that gives them concept design. Either way concept design is where
the opportunity is to really look at what it is that the city or other entities are
interested in and factor them into a project already in that effort. Once that is all
settled and I will talk a little bit more about our relationship there, we move into
the design process, wrap up design, acquire right of way, go through the
construction phase and close out the project. So coming back to those steps and
talking a little bit more about the cities' opportunities to be a little bit more
engaged in that. During the five year work plan and now that we sort of
reorganized the capital improvements citizens advisory committee, you now have
two representatives on that and one of them is your City Planning Director or
designee and the other one is a local citizen that you recommended. They will
be the one involved in the five year work plan on a routine basis. So you should
have staff who are well aware of where we are with this project and how they are
coming through the cue. We are really hoping that will be a real improvement in
communication. (Inaudible) a fine job of coordinating, but this gives a better
opportunity. When a project is in the five year work plan and at a certain point it
hits our budget year and that is when we start work on it. We actually, though,
we start work before the budget year, the immediately proceeding year and that
is when we do project initiation. At that point, that is the point when we will be
contacting the project manager who is assigned to the project and will be getting
in touch with the city to talk about appropriate participation and whether or not
the city has interest in additional features beyond the basic road that we would
build. This should happen, in my best of all possible worlds will happen during
the project initiation process before the dollars have even hit the budget process
because we need to know how to work together. Participation can vary pretty
widely. On big projects you have staff that actually sit on our project team. Both
Matt and Caleb are part of participating on project teams. But on smaller projects
that probably is not a great use of staff time - if it is just a little bridge
replacement or filling in a sidewalk gap, you know that - we will figure out what is
appropriate way to communicate about what is proposed and make sure your
staff has plenty of opportunity to give your input and review plans and all of those
things, but they may not find it a good use of time to sit on a project team. The
expression of interest in additional features is really an opportunity to say this is a
place where we know we want to have additional sidewalk. Maybe it is a
downtown and your plan calls fora 12 foot deep sidewalk -you know in an
intense pedestrian area. Or perhaps you are in a gateway and your plan calls for
special treatments at a gateway, this is the opportunity to really talk about that.
There are others which I will talk about as we go on. We will initiate concept
design and the first thing that we will do is negotiate a plan for design. Now that
could be our in house design or could be a consultant design. If the city has
specific features that they are interested in having built into the design, we want
you to have the input on the plan for doing that work. A lot of that is frequently
done during concept design and in that phase that is where we have the
opportunity to really look at options. So it might be that you think you want -you
are not sure if you want to do a six foot or an eight foot buffer for example.
During that concept phase we can look at that and we can look at what the
relative costs are and look at things like what are the impacts to the adjacent
property. If it turns out that a bigger buffer means a whole lot of having to buy up
a bunch of houses that is probably not something that either we or you would be
interesting in doing. It is during the concept phase that we sort through that
together and determine what the configuration of the project should be. So that
is the identifying and evaluating alternatives. We also come up with concept
level cost estimates which is a key part for everybody making a decision as to
what the features are that they are interested in and our objective is for the city
and ACHD to concur on the preferred alternative at the close of the concept
phase. Again, that might be a separate phase that has got its own contract or
whatever or it might just be the beginning of the design exercise, but we
(inaudible) to agree on what that should like is what we are trying to accomplish.
At that point, if the city has specific requests that would be city funded under the
interagency cost share policy this is when we would develop an interagency
agreement to determine what that is, what the project is we are going to adopt,
who is responsible for what? We lay that out in this interagency agreement. I
think I have got a note to this affect elsewhere, but just in case - to make sure I
don't forget, we are in the process of - we have done a couple of agreements of
this nature before the cost share policy is adopted. Ri~ht now we are working on
an interagency agreement with the City of Boise for 36 Street and that will serve
as our initial model and from that we will try to generalize it and create kind of a
model agreement that everybody could look at and go back and forth and
discuss a little bit. But our goal is to really get that agreement settled at the end
of concept design so that we are designing the right thing. It becomes expensive
if we have to redesign or if we go out and buy right of way and it turns out no,
never mind we don't want to do that, the purpose here is to make an effective
investment. During the design phase the city would be responsible for the design
of non transportation elements -what landscaping or special land that you were
interested in? The cost would be yours, but so would the design decisions. You
would make the decisions as we go through the process about what it is you
want. We have had more than one configuration on this kind of an exercise;
sometimes we have had a consultant for the roadway project who has the
capacity or subs who have the capacity to do the design for the non -like
landscaping. Other times we work with cities where they actually have their own
separate consultant or their Parks Department does the design for that element.
And that is either configuration; whatever makes sense for the project is how we
would set that up. Then of course the city would use the comments on both our
plan which is a routine plan of what we do as well as obviously having the major
design decision role with respect to those elements with the city. During the right
of way, ACHD would acquire the right of way - if there is additional right of way
involved it would presumably be involved with city financial assistance and some
of the questions that you all asked about that, they will come up a little bit later. I
will actually ask our legal folks for comment. During construction, again it can
work a couple of ways. The city -make it that ACHD bids. the transportation
elements and the city bids the other elements separately. That might make
sense with landscaping. The good part of that configuration is that you have full
control over your pieces, but we also have had quite a lot of success in the past
with jointly working on projects particularly when utilities are involved. So, a
single bid that has city elements and ACHD elements with the city reimbursing
ACHD for those portions is feasible too. We have projects configured that way.
We try to think that through based on what makes most sense for the project. It
isn't in our view, important for the city to inspect and improve their own project
elements so that under either configuration you are getting what you want and
making sure that you are satisfied. We are working on a model agreement
based on the (inaudible) street. It has got to specify the assumptions based on
the concept design. That is what the model interagency agreement would do --
here is what we agreed to build and here is the cost estimates for what we are
doing. But at this point we just have cost (inaudible) level cost estimates. We
don't have full design estimates with any changes. So we are describing in that
agreement some sense of how to work through the design process so that if the
costs change how do we work together so that we can jointly make decisions and
how do we make sure that you all have the ability to control your costs?
Because it is not like we are going to go out and design something and come
back and tell you oh, there is a whole lot more money than we thought and what
are the appropriate remedies through that process? Again, we try to
accommodate development requires to achieve some of the features and this
interagency agreement will address design, right of way and construction phases
-- all three. Originally (inaudible) suggested that I go through (inaudible) as an
example (inaudible) kind of from beginning to end. I thought it just made more
sense because sometimes you look at projects and they have too many features
that are just unique to the project. So I thought it would be better to do that
overview and then talk a little bit about a couple of examples where you can see
a little bit how it is working and how the give and take works for the individual
projects. In this particular case, ACHD has started the design based on a set of
assumptions about what the project was going to look like and the city came to
us and said we are really interested at looking at revamping the land use in the
area of several blocks either way. We would like a full charrette process. So we
joined with them. They led the charrette process to do an area of specific land
use plan, but ACHD served as a partner in that and we funded the transportation
component and out of that they came out with a different concept for what they
wanted to see on the 30~h Street extension. It had more features in terms of a
landscape median -atone point the landscape median was very big, like 49 feet
wide, but eventually as they worked through it they got down to something more
typical and they were trying to get it to fit in, you know, they have got that Simplot
park going in on the river that is going to have an actual park and then the
whitewater park. We are trying to see how do we get the road, how do we get
the pedestrian crossings to all fit together with the park? Eventually what they
decided is that they were interested in having a roundabout at the park entrance
and we took a look at it and it didn't warrant -actually it didn't warrant asignal -
the traffic that was projected -- but normally in the past on a major park, we have
put signals at the entrance. So what we did was we worked out an arrangement
where the city is donating right of way and they will be paying us a little bit for
some of the incremental cost for doing the roundabout over the signal. So we
said the signal would be our baseline cost and they wanted the roundabout, so
they are contributing - of course they own property along the edge so they have
the ability to contribute right of way in this particular location that is helpful to us.
So, you know, we kind of just balanced those kinds of things through a detailed
discussion during concept design process -the city is also interested in having
landscaping in the median and they will be installing it and maintaining it at the
city's expense. It will be matched up with their park so that they get the fit and
feel that they are primarily interested in. So we are just now wrapping up the
interagency - or putting together a detailed draft of the interagency agreement on
this particular project. But, I wanted to give that as an example so that when we
get into the details and specifics of a project, we just give and take and figure out
what is a way to achieve the objectives without - with a fair distribution of
financial responsibility. The other thing that happened on this project which was
really good and it was our first concept where it happened, we really have kind of
had some different visions about what we should be doing in the roundabout and
we went off at the staff level and put a bunch of information together and let them
look at it and we sorted back and forth and at the end, the city voted unanimously
that they wanted the configuration that we thought was a good configuration too.
So at the end of the day, we both approved the same concept and had a good
project to go forward with and everybody was happy with the plan. In the case of
Five Mile, Fairview to Ustick, the city wants to have a landscape buffer. Now, we
don't have an interagency agreement on this. We did the concept design. We
really wrapped it up about 18 months ago, I think and they really wanted the cost
share discussion to reach a little more advanced stage before we looked at an
interagency agreement. So in this particular case we adopted a concept that
said if there is a cost share agreement, this is what we will build and if the city
decides not to cost share and that they are not interested in doing that then this
is what we will build. So we had two options. They do at this point think that they
want a landscaped buffer and consistent with the policy that I described earlier
ACHD offered to buy right of way up to six feet for that buffer. They took a look
at the situation and they proposed that they put four feet of buffer with like shrubs
on one side and eight feet of buffer on the other side to accommodate trees. So
they would have street trees on one side. And as far as we can see that is going
to be a fine arrangement if they choose to go ahead with that. So, again I just
wanted to give you an example that it is a give and take discussion in the context
of the individual projects. Moving onto your specific questions that were captured
in the email. What would be constructed if the city doesn't participate in cost
sharing? I kind of went through this -whatever the curb to curb condition is as
proposed to the livable street design guidelines. The decision about a median
verses a tum lane will be for safety purposes will just be based on traffic
engineering principles. We will have a five foot bike lane that does not include
the curb and gutter, so it is 5 feet of flat space and again, 2 'h feet of buffer
space, 5 feet of sidewalk and some of these things vary in response to site
specific conditions. The one that comes to mind is the Ustick project there in
front of an elementary school (inaudible) because you have such heavy
pedestrian use. That would presumably be something that ACHD would choose
to do, but I think it is 6 or 7 feet -within our normal range of activities.
De Weerd: Is there flexibility on - in light of all of the issues and conflicts
between motorists and bicyclists and is the debate of the moment. If the city
were to look at widening sidewalks to have pedestrians and bicyclists off street,
would there be flexibility to take that 5 foot bike lane and add it to a sidewalk
design - we are not talking about that one necessarily, but is that possible? I just
got back from the Netherlands and they don't have those kind of conflicts
because the bikes are not on the same road. They are on a different facility and
how would that work?
Goodell: Mayor there certainly is altematives that we can look at and in some
scenarios - I am thinking of -this might not be a great one, but the 36~h Street
extension that goes under the hills in Boise -one of the proposals is to put a 10
foot shared use pathway on one side. It is partly because of the constrained
environment, but those are certainly altematives. We just put in a shared use
pathway on Emerald for a couple of blocks tying a couple pieces of sidewalks
together as an extended curb and as our shared use space outside of that curb.
We did the same thing Helm Road. We are careful how (inaudible) because
commuter type bicyclists use the road anyway. They just prefer that and so we
try to make sure from an engineering standpoint that we are putting together
something that protects their safety as well or provides an alternative if there is
an alternative location they can go, but we can work through those types of
questions in any specific project, absolutely.
De Weerd: We have a master bike plan that we also worked with your staff and I
know that you are coming out with yours or you have and so are those in concert
with each other'?
Goodell: My understanding is they are. The staff went through them carefully,
did they not?
Canning: Yeah. Madame Mayor, Council Members and Commissioners we met
with Justin Lucas on Friday and went through in detail and we are going to get
back to him on the multi-use pathways - we are going to just look at our GIS later
and get that to them so they can incorporate that into their map. So we are
working on that issue specifically.
Goodell: One of the things - on May 27w the Commissioners adopted a livable
street design guide, the cost share policy and the complete street policy. There
is another piece to this puzzle, which is the topology and the associated
information and we went through the whole process of working with all of the
cities and their staff to determine what you want each street to look like in your
future. We are working to get that adopted this fall and we are going through a
series of workshops with your cities to put together what we are calling a master
street map that will capture not only -you know when we say this is going to be
a residential arterial or a residential collector, okay, well specifically what do we
want that to look like. Does it have -are there any special features that you
know at this time. Are there any special conditions that we are aware of? With
the goal of being able to design what the right of way footprint would be so we
would be acquiring the right of way for the right thing and that is the workshop
that Anna was referring to. I wanted to call your attention to something at the
end -that have pictures of typologies and we use these in the public information,
we use this frame and make it just a little bit helpful. The first image shows you
what a 5 foot lane road with 11 foot lanes, a bicycle lane, (inaudible) with curb
and gutter with the buffer and the sidewalk would look like and that is the basic
section that ACHD would construct. If you go to the next page, it shows you
what might be possible in the scenario where the city indicates the designer to
landscaping in the buffer strip and ACHD acquires the additional right of way
(inaudible) with a 6 foot buffer strip. The third page still has the 6 foot buffer strip,
but it also has a (inaudible) landscape median in the tum lane and this is closer
to kind of a full (inaudible) treatment. It could be more to it. It could be that you
want to have 10 foot buffers. It could be that you are in the downtown and you
wanted to have 10 foot deep sidewalks because of high pedestrian use. This is
to just give you a little bit of a sense. This would be a scenario where there
would be a little more substantial partnership. Moving on. Anything else on this
at this point?
McKee: Any questions?
(Unknown Speaker): Sally on the full TLIP section street section -there is a
couple things that are different and one is the parking -
Goodell: Oh, I missed -yes.
(Unknown Speaker): In that scenario, who would be responsible for that 7 Yz
feet?
Goodell: When the road is an arterial, ACHD would be responsible for the right
of way for the parking, but when a road is a collector or a local road is almost
always the developer -most of the work or some other entity, but we concluded
in dialogue with the Commissioners that if it is an arterial ACHD would take
responsibility for that, however the presence of parking lot arterials is pretty
limited because of the tendency to really impair or reduce capacity and safety
issues. The kind of place you would see an arterial is downtown or something
like that. How would the cost share policy be applied in the city's area of impact
but not yet annexed into the city? We would consult the city on those portions
that would be part of your city in the long haul in terms of what your interests are.
The county has indicated that they don't have any interest in pursuing the
"TLIPing" if you will; but if another entity came in and was proposing something
or if you all wanted to propose something that you knew was going to be a part of
the city eventually we would consult you and work with you on that configuration.
Did that answer the question? I hope.
Rountree: I guess my question, Sally, would be you have indicated you would
consult with the city, but that results in two other questions -you will consult, but
would you follow through with the recommendation from the city and if you did
what portion would the city be responsible fog? Right now if you look at the
second bullet point that is exactly what we get when we provide input to the
county about things that are going on in the county. They have no interest in
what the city says.
Goodell: Sure. I understand and I can see how the way I responded to that
could raise that question. The participating agents, whoever makes that request
we would work with them to set up a partnership agreement and if the city
wanted "x" we would work with you through the rest of the cost share policy to set
up an agreement that tries to achieve what your objectives are. If the county did
resistance of some - I am having a little bit of trouble thinking of a reason why
they would, but if they resisted we would try to work it out.
Huber: Well, I think the flip side of why this is really important and it will be tricky
because if we follow the policy through and you would be paying for some portion
of that and you are not annexed yet, but the shocker and why that gets in my
mind tricky is I sat in a meeting and listened to a particular city say they might not
annex a piece of this county that they have even bought part ground in and so
you see where we are caught. So whether or not - I am not saying which city,
but I mean it was a shocker because it was out of the blue. It was assumed they
were going to and they come up against the wall and annexation where there
was a lot of people grumping. Maybe in the end they are going to still annex it, I
don't know, but all of sudden it was like gosh that never crossed our mind. So
that is where it is hard for us and it will be hard.
Rountree: Well, I would hope you wouldn't get a request if that was the case.
Huber: Well, you see what I am saying and that is this is an area that was kind of
a done deal I thought and then I heard the Mayor say something different.
McKee: Well, in this particular area we have gone through a transportation and
land use study with them, so yes money has been expended already. So it is
now a new question in our mind when a city says yes we will annex this portion
and actually having them do it or not do it. We can't force annexation, but we
have been spending money in areas that are not yet annexed, but at the benefit
of the city who is doing the annexing.
Huber: And we have always followed whatever they wanted.
(Speaker unknown): Madame President, the issue here is I think a little bit
different than Boise. Let's just say it is probably Boise that you guys are talking
about. If it s a TLIP project and say the City of Meridian wants to do it in there
area of impact and you want more than just the basic TLIP, which ACHD pays for
the basic TLIP, the 2 YZ buffer with the stamped concrete perhaps and the 5 foot
sidewalk and you want something different in your area of impact, it is my
understanding and correct me on this Sally, you would pay for those additional
amenities for let's say if you wanted a 6 foot landscaping then you would pay for
the landscaping and to maintain it. So I don't see a situation where there is ever
going to be - I mean the only thing that you will have to answer to is your
constituents if you say yeah we are going to do this -but that is your decision. It
would not be our decision. We would give you the basic TLIP otherwise, right?
(Speaker unknown): Or you would just wait on the project until you decide if you
want to annex then great. If you don't the options are there. Obviously you are
not going to spend money in an area that you haven't annexed. I can't imagine.
Huber: I don't know - if that has happened already.
Rountree: I guess I have a question about the TLIP, Madame Chair. All I have
seen and I probably have not paid attention, but all I have seen is typical sections
or typologies that relate to urban environment and there may be some work to be
done on those areas that never will be annexed into a city in terms of rural
sections. Your costs are going to be significantly less.
Goodell: You are absolutely correct that the livable street design guide focuses
for the most part on urbanized environments and that was based on the notion
that -probably partly just one bite of the elephant at a time, but also the notion
that the heavy pedestrian and bicycle use which so much of this emphasizes the
alternative transportations is primarily in those urbanized areas. We do have a
configuration for rural roads that includes a substantial safety shoulder, for
example, that you have reasonable safe space for bicycles. But if there is more
to do on an individual project than thinking to do we can certainly do that and I
guess if that led to another generation of the level of street design guide that
addressed another scenario that would be fine.
De Weerd: I guess I am going back to Charlie's question and what I don't think
has been answered because of some of the scenarios that are going on out
there. If the city staff works with your staff to look at some of these enter
corridors - we think they are enter corridors to what our areas of impact are and
we set an expectation for that design with the associated commitment whatever
would happen on our side, what if another city comes in and takes a chunk out of
there that could possibly upset the overall design of that roadway? Should you
not make a requirement of that arterial that it looks that way so you are not
dissecting it so that one portion looks this way and another portion looks that way
and then you are back to the original intent. How do you protect the integrity of
that transportation corridor?
Huber: So how do you make the city pay for the consistency, whoever doesn't
want to do it? I think that that is really the question.
McKee: And I think at that point we would have to revert back to the basic
roadway that the ACHD pays for on its own.
Huber: I can certainly see what you are talking about and I think this is going to
have to be something that is a case by case because all of sudden we design
something, say for Meridian and we think it is a done deal and then all of sudden
some other city comes in and says Hope, we are going to take that and then they
want an entirely different roadway. Well, who picks up the cost of that?
Speaker unknown: Won't that whole issue sort of be resolved if you go to the
county with your impact of area --? I mean there are legal avenues you could
take in that situation. I mean you could preemptively annex or work with the -
have you gone to the county within the last six months on this?
De Weerd: Yes.
McKee: Sally right now do we have any projects that are looming towards this
problem?
Goodell: Well, because anything -most of what is imminent is already designed
in terms of constructing in the next couple three years. There may be some that
there is a question about going forward and we would try to work that through
design. I will try to go back and take a look at the list and think about it a little bit.
But we can sure take that into consideration. As a hypothetical we did as a result
of the comments that we received from a lot of the cities (inaudible) case by case
consideration because there are often unique considerations and the
Commission wanted the option to really look at that on a case by case.
De Weerd: I guess for just a closing comment on that we worked with ACHD,
our staffs, with the land use and the transportation component in our planning of
our south Meridian area. Money has been expended, plans have been adopted
to those expectations of design, so I guess that cautionary when that change is
made as we contemplated the adequate public facilities and when changes are
made that cost we don't want to incur. The cost of that change needs to be
passed on and that expectation needs to be clear.
McKee: Yes, we are well aware of that.
Goodell: You know I think that is fairly consistent with the language in the cost
share policy. I will have to go back but if for some an entity came in and
requested something different when we are already well into a process, the
redesign would be at their expense. Of course we would go have a dialogue with
the entities and try and sort it out.
De Weerd: So all of the upstream, downstream effects would be passed on -the
cost of changing?
Goodell: Upstream and downstream effects is getting into a little bit different
area.
De Weerd: That is our bottom line.
Goodell: (Inaudible) wasn't designed to try and answer that. That is a larger
question and cost share policy is really just trying to say within the streetscape
that we are designing and constructing, how do the two entities work together?
The question of downstream impacts from one community to another really is, I
guess, a part of a dialogue blueprint (inaudible). The question was and this was
embedded in another question, but I will address it directly. Is the city
participation and expenditure in the right of way limited to landscaping? No. I
mean if the city has other interests or things that they would like to do, we are
certainly open to whatever we can work out that is safe. We will have concerns
around, for example, if you are putting them in a median - we will need to look at
site distance questions and safety for vehicles and whatnot, but particularly if we
get the ideas on the table during concept design that really maximizes our
opportunity to be flexible and to work into a particular project or whatever the city
or stakeholder is interested in seeing. So we just want to emphasize that. It
becomes expensive when we have already started the design process and we
have to step back and redesign or if we have already started buying right of way
and we have to go back. This is where I am going to ask our legal counsel to
address some of the questions. You have a couple related to the nature of our
authorities.
Price: Steve Price, ACHD general counsel. This issue of state statutes and
limitation of ACHD's authority on spending and the right of ways have been on
ongoing issue throughout the development of cost share policy and I think
probably the best way is to kind of give a summary for you that ACRD didn't
develop this interpretation without doing extensive research. We have looked at
it a long time and in fact we first came to this issue back in 1980 in a case - it
was an Ada County case, the Ada County Highway District verses Boise Water.
This case involved and issue of ACHD's authority under state statute and there
are a bunch of old cases in Idaho that relate to the specific authority of Highway
Districts and their purpose. I think that if you hear some of the language decided
in the case - I hate to do that to you, but I think it will help you understand better
than me explaining it. I have tried to explain it several times, but there continues
to be confusion. So I thought maybe the best way to do it was just read what this
decision was and it would help. It says cities and counties have both public -
another way to think about before I start is that cities have the ability to carry
guns, they have police power. ACHD doesn't have police power. We don't have
any guns. There is a clear distinction in terms of how power is delegated out of
the constitution and by the legislature of those two entities. Highway District's
arm is created by the constitution, cities and counties are and it is that power
difference that is where we are today and the legislature when they delegate
powers, they delegate as a limitation, not as a general grant. The constitution as
they delegate powers to cities and counties is a general grant of power. It is
much different. So let me kind of start off by saying cities and counties have both
a public government mental role and also they have a quasi private or proprietary
role providing services for the special advantages of urban communities in their
business capacity. It is (inaudible) role verses legislative control. On the other
hand, Highway District's Idaho have ordinarily been regarded as quasi municipal
corporations; highway districts as intended by highway district law cannot be said
to correspond identically with other public corporations or county corporations or
cities, towns or villages. They are quasi municipal corporations, not political
municipalities, not created for purpose of government, but for a special purpose
namely that of improving the highways within the district. The power of highway
districts has been said to be limited to the construction, maintenance, repairs and
improvement of all highways within the district. A highway district in Idaho is not
a political municipality created -and these are cases by the way -for
governmental purposes, but its powers are specifically limited to construction of
highways for the benefit of its inhabitants. There are several cases that basically
continue with the same concept that a highway district has limited special powers
and it is only for the purpose of constructing, repairing and maintaining highways.
That case law is consistent when you interpret it our title creation of a single
county highway district and when you get into the section where it says what is
the highway districts powers of the cities and that is in 40-1450, it says the
responsibilities of the single county highway district within cities and they have a
subsection and it talks about -and it specifically identifies what ACHD's role is
for constructing highways within cities and it is very specific. The one thing that
we have interpreted that gives us some flexibility to spend money in the public
right of way is when it relates to traffic and safety engineering for both motors
and pedestrian traffic and so if we have some design issue where we could
determine that the expenditure monies would enhance safety, like a buffer zone
or in some cases it will be landscaping, or traffic engineering department said
some landscaping on a round a bout will help slow down traffic then there will be
a case for that, but if we can establish from an engineering perspective that that
design could in the future will enhance safety then we will stretch the statute to
grab that. But when they developed our statute, they have a reservation of
authority for what cities can spend - if we have the general supervisory control,
the general jurisdiction over an exclusive jurisdiction over the public right of way,
then one would think that nobody else could get in there, but what this legislature
did is they had an express reservation that says within the limits of any city, the
city may expend funds for the placement, care or removal of trees, grass, shrubs
or other plants that are located within the right of way of any highway that is
within the highway district and so what that is doing is it is a further limitation of
ACHD's authority by saying, you may have exclusive jurisdiction over public right
of way, but we are pulling a piece out for the cities and when you look at the
legislation you will see what they wanted is that they didn't want a highway
district to be able to go out there and control what the aesthetic features or vision
of each community is. It is kind of like they don't want ACHD to carry guns
around either. They wanted the city to have a reservation to be able to control
within their city what their city will look like. Kuna will probably want to look
different from Meridian and it gives the city the ability to have control of the
destiny of aesthetic look of their city. There is another section that deals with that
and that is within -this is within the county and that is 40-1406 and within the
county they have the same reservation. So you have the city statute and county
statute and it says within the limits of any city, again, this is the same exact
language that is in there. So within our statute, they put it in two different spots.
Now some people have said well how does that interact with the 40-1312 and
that is that this relates back to the general highway district statute, where we also
have the same powers within that. It says the grant of powers provided in this
chapter of highway districts and their agents shall be liberally construed as a
broad and general grant of powers -- that is great so far - to the end that the
control and the administration of the districts may be official. So it says that the
broad powers to be in terms of implied powers that we shouldn't interpret that,
only for the efficient control of the administration of the district. The enumeration
of certain powers that would be implied without enumeration shall not be
construed as the design (inaudible) solution of other implied powers necessary
for free and efficient exercise of powers expressed in granting. So although you
can walk the fine interpretation if you - as a lawyer if you have any intellectual
integrity -after lots of training and lots of reading of the statutes, we have had
several lawyers look at this and as we have gone through that I have just given
you a brief summary from an analysis standpoint as to how we got there -now if
the Commission doesn't like the legal advice they could mostly ignore it, but as a
community, though, the other option is to go to the legislature to pass a law that
would change that specifically or to clarify it. Now I don't know whether that has
answered your question, but I tried to do it in kind of summary form, so if you
have any questions I would be happy to stand for those.
McKee: Yeah, let's open it up to questions and maybe Steve can answer them in
lay person's terms.
De Weerd: Steve how does all of that apply in a situation where you need the
connectivity for the safety aspect and right of way purchases and putting in
sidewalks? Where does that leave the ability to do that when that development
or that annexation is not coming in, it would be on county land and do you have
latecomer's agreements that you do in those cases that if you put in
infrastructure that typically is a part of annexation and urbanization of an area,
can you do something like that?
Price: Madame President, Mayor De Weerd that is a very good question and the
concept is that obviously if we are going to have a project that is in there that we
can show there is some sort of pedestrian safety, that we can prove our future
(inaudible), the streets map and that we can preserve corridor through that, we
can show that as a public necessity that is something as part of the community
vision. And that is part of the reason why we are going through the blueprint
TLIP processes to create a future map, which is a land use authority that when
those parcels come up that we have them identified on a map that we can see
opportunity to work with the landowner to acquire right of way for those features.
The second thing that this does is that if these design features, if the city wants
something that is outside what we believe is our statutory authority (inaudible)
that creates a power that creates an imminent domain issue as to who has the
power to exercise imminent domain for that feature. We think we could resolve
that though through this map, this corridor preservation map and we could
negotiate the purchase of that with the landowner. But again, in terms of what
ACHD can exercise its authority for are only those designs that we can show is
within our power that is a public necessity. Anything outside that then the city
can do through the development process as far as action for the development.
Now in terms of latecomer agreements, we are moving towards latecomer
agreements through our extraordinary impact fee arrangement and we will be
coming to you in the near future with the concept of extraordinary impact fees
and latecomer and the idea there is that anybody that gets the benefit within and
we can create an overlay district, anybody that would get the benefit of those
improvements that they are going to utilize those improvements that we could
charge an extraordinary impact fee to the people as that land develops and with
that we would pay the developer back that puts in those improvements and as a
form of a latecomer agreement. This is something (inaudible) two communities
in Washington and Oregon -studied that and put together programs based upon
that. Did that answer your question?
De Weerd: I think so. I will have to process it.
Price: Well, if you have any questions, feel free to contact me.
McKee: Are there any other questions? Sara?
Baker: Steve what was the case that you cited at the very beginning of your spiel
there?
Price: Ada County Highway District verses Boise (inaudible) Corporation. It is
just a district court opinion and I would be happy to get you a copy of that. It is
1980 decision.
Baker: The other thing is and obviously this is before your time, but what
rationale did the ACHD use to put landscaping on Curtis Road? It was installed
by the district but maintained by the City of Boise.
Price: I don't believe that there was any analysis done.
Baker: If you want to know the poster child for a whole list of things to not do
over again, it is Curtis Road might be it.
Price: But your point is is that we have done projects in the past where the
district has paid for landscaping and as policy the city has maintained it thereof.
Baker: But not the maintenance. The maintenance has never been done by the
district.
Price: There is no question that we have a history of that.
Baker: Except where weeds grew up in the sidewalk cracks. That is the district's
responsibility to maintain those. Like Federal Way, we just had an issue with
Federal Way having a huge bunch of weeds grow up in the cracks.
Price: That is partially true and there are other cases where the adjacent
landowner is also responsible.
Franden: Residential districts it is usually the homeowner's association.
Baker: Federal Way is an interesting issue.
(Inaudible discussion)
McKee: Okay, any other questions for Steve?
Goodell: I am fairly confident he answered this question -the question of
exercised imminent domain powers and of course that ties back to the footprint
(inaudible) street map which is what would be adopted by you, we hope, in your
future acquisitions. The last question was how flexible of a timelines outline the
policy for city participation? I think this may have come from a particular point,
but during project development, all of that will be scheduled within the five year
work plan and there is lots of opportunity to work through the issue as long as we
get involved early and keep ourselves on a reasonable schedule. I don't think
that is probably the hard part or the place that maybe triggered this question, but
just to be specific, I guess, during that process hopefully we are working through
the terms of what we think our cost share agreements should look like during the
concept design exercise so that -and hopefully we are working with a model
agency agreement that we have kind of settled the terms. It will take a few
iterations for us to get there, but that is our objective so the general terms are
settled and then there would be a period after concept where we would make
sure that we had a cost share agreement that both parties agree to. I think the
question might have come from issues related to early right of way acquisition
and when the city is interested in a particular set of features that entail cost share
and we are talking about - we have the opportunity to acquire right of way
development say that would incorporate both our property and property that the
city was interested in. If the city was not prepared to -there is a window of time
statutorily where we have the opportunity to acquire that right of way during
development. If the city was interested in participating, we would move forward
to do that and we may want to look at exactly what that would entail; however,
Steve, correct me if I am wrong, I think we have 30 days to notify the property
owner - is it 60 and then we go to negotiate an agreement? Total of 60 days. It
is relatively quick and it is defined by something that is outside of our control. If
that was just too quick and the city doesn't necessarily have the resources or
whatever to participate at that time, that doesn't preclude doing it. Working
through this as the project itself comes to life, as long as the city does not
approve a development that puts a building in the place where you would actually
like to have something else, say one half of a buffer or something, which is well
within your control then when we get to the project design phase, as long as
there is adequate setbacks, we can come back in and deal with acquisition at a
later time when we actually have the design footprint done on normal right of way
process. So, I just wanted to make sure it does refer to that early right of way
acquisition with a fairly short timeline, but if we work together to configure the
situation appropriately, that shouldn't be a failure to accomplish the city's interest
in it.
McKee: Are there any questions about that?
Baker: The previously slide, did you go over that one?
Goodell: Yes, Steve did. He talked about that.
Baker: The imminent domain?
Goodell: Yes, that was the whole compass of adopting a footprint into the master
street map and future land acquisitions for the city.
Zaremba: You have used a couple of examples - 30th and Ustick Five Mile. In
the process with the split corridor phase 1 and I am thinking specifically of the
area of Main Street between Corporate and Franklin there has been a lot of input
from our Parks Department, probably our Arts Commission and certainly our
Public Works and our Planning Department and stuff. It seems to me that that
process even though it happened before formalizing this pretty well followed what
you are telling here. Is there anything that you can think of in the split corridor
phase 1 on Main Street that would alert you that is not going to work the way this
is or this isn't going to work that happened is what I mean?
Goodell: For the most part, no. I do and really all I had an opportunity to see are
some notes from Meridian Development Corporation meetings, minutes or
whatever and apparently there was some uncertainty of who was responsible for
inspecting the landscaping work and I attribute that to respective - if it was not
addressed in an interagency agreement, which it should have been that was
probably because we haven't ripened to the point of exactly what it was that we
needed to be clear about. We do think it is important for the city to inspect and
approve those elements that are there and were their responsibility and have the
power to do that. That is one area I am aware of and those are things that we
will try to work out as we develop a model interagency agreement. I think there
are others that I might not be aware of. We would really appreciate having those
called to our attention we could work through them.
McKee: Any other questions so far?
Rountree: Madame President a comment and two cautions. Having seen this
and having worked with your staff on the master street plan and our staff, I am
really pleased at the flexibility that you incorporated in this process. I think when
we first heard about it, we all went oh well what are they doing to us next? But,
just suggest, if it isn't and make sure it is emphasized in the preamble or at least
in the background information on the policy so it doesn't -the policy doesn't
become dictatorially. I think that we all agree that every transportation project,
even though we think they are all the same, they are all different and they have
different turns and twists in it and you have to be able to sit down, negotiate, give
and take and I think what you have done is great. The cautions I have with
respect to the process, Sally indicated that in design and construction there was
some mix and match possibilities of the city doing this and the Highway District
doing that with design and the same thing with construction. I would caution to
get away from that model. What you do is you set you in conflict with the people
that you have hired to do the work because they can come with extra costs
associated with their initial work saying well, contractor B didn't perform by the
timeline prescribed and therefore, I had to wait two months to finish the design
and therefore, I need "x" numbers of dollars in compensation for that delay. I can
guarantee it is going to happen. You probably have already seen it. If you
haven't I am surprised. The same thing in construction, somebody has got to be
responsibly in charge and oversee the whole thing or you will get hammered to
death with increased costs, more so than normal. I can see like in the case of
roundabout, assuming the design is done properly that the city could come in
with their own crews and probably do it and save some money, but that is when
everybody else has left town. A city crew can't be out there working with the
construction guys because the construction guys, I can guarantee is going to say
well the city got in my way and now you have got a $50,000 increase in cost and
they will do it to you every time.
Goodell: I apologize I didn't mean to imply that during the design or particularly
during the construction process that we want to be in a position where we are
making changes to what is going on the ground. The main comment that I
wanted to make particularly during design is that we go forward with an idea or
whatever it is that we want to do based on concept level costs and if for some
reason when we get into the design process, we find that there is some element
of the situation that said and I am speaking specifically with respect to city, but
also ACHD's features. If we find something that we weren't aware during
concept that blows up the cost significantly, we both need off ramps to be able to
renegotiate at that point. That is the kind of situation 1 was trying to describe.
Certainly we don't want things changing and your point is well taken about how
you coordinate construction.
McKee: Okay.
Goodell: That is all I have. Unless they have additional questions?
McKee: Okay, anything else?
Item 2. Request to Defer Impact Fees:
Freckleton: Good morning Mayor, Commission and Council. My name is Bruce
Freckleton and I am the Development Services Manager for the Ciry of Meridian.
Just to give you a little bit of background as to how we got here. Approximately
two to three months ago, we had some discussions with your staff, ACHD staff
regarding our 14 year old agreement for the impact fees cooperative process.
There were some things process wise that we wanted to discuss and streamline
and work with different methods of those processes and I am happy to say we
have checked off a big list and we have come to some terms and it has been a
pleasure to work with your staff. Paralleling that process, we had some
discussion with our Council and Mayor regarding ways to try and stimulate and
incentivize commercial development in Meridian. You may have heard recently
that we ~assed a resolution for the waiver of police and fire impact fees from
June 3` to September 30"'. It was during those discussions with the
development community that when I was vetting this to them, they said that
certainly that is a step in the right direction. One of the things that would help
them more than anything else would be to try and get impact fees deferred. So
we begin the process having some discussion with Gary and your staff to try and
explore that option to see if there are ways that we can do that. When I
researched your ordinance and also the state statutes regarding the impact fees
we didn't see a direct mechanism for the city to enter into any kind of agreement
with the District to defer those fees; but we did find that both in state statute and
in your ordinance you do have the ability to work with private developers,
commercial developers to establish the point and time at which you will collect
impact fees and so basically as an introduction what we are asking you to
consider deferring your impact fees to the point of occupancy for commercial
developments in Meridian. As we have been discussing at staff level we have
proposed you would consider it during the same period that we are waiving our
impact fees for police and fire and that would be June 3`d to September 30~'.
Gary is here too. I don't know if you have anything you want to add?
Inselman: Commissioners, Councilmen, I might just add that we have discussed
this with our staff internally with our Legal Department and while we agree that
our ordinance and statute would give us the ability to enter into these
agreements, I am not sure of our ability to enforce them. It does take away some
of our protections, I guess you would call it, you know to make sure we collect
those fees. We are being a little bit cautious and doing a little bit more research
with our Legal Department and certainly look into this further if two bodies direct
our staffs to work together. Bruce and I have kind of gone as far as we can at
our level and I think it becomes more of a legal issue of can we craft something
that gives the District protection. We need to (inaudible) to ensure collection of
those fees at that time without the city or Highway District or both pursuing legal
action to go and collect those fees if the developing party defaults on the
agreement. Having said that normally our protection that we try to ensure that
we have in most development deals is a financial guarantee, which if they are
putting up the money for the fee, they may as well pay us the fee. There
wouldn't be a huge savings so the practical matters of how we can make this
work if directed to pursue it, we need to work through. I guess that will be a little
more information perhaps a sturdier discussion amongst yourselves and anyone
to direct us to proceed. Thanks.
McKee: Are there any questions?
Zaremba: I probably should know this, but what is the lag between a building
permit and an occupancy permit? If we are asking ACHD not to waive payment,
but defer it, are we talking about six months or a year? What is the normal lag
between those two permits?
McKee: Depends on the project
Huber: Yeah, I will just go through some of the issues that I see need to be
answered that really make me nervous. While in the concept it is great. The
reality is and we all know that some developers we are more comfortable than
others, but you have to offer it to everybody. I mean, how could we discriminate
against one over the other. It would be anybody who asked and that is the first
part that bothers me. The collections agency that we talked about -but, more
important somebody needs to go through the math with me because if somebody
has a $300,000 impact fee and say you defer it for a year and the interest rates -
I don't know -it's 5 percent - I have no clue. What I am getting at is -you really
are saving them the interest is what you are saving them. So, how does - if that
makes or breaks a project, I guess, that is the answer I need and I am not
perceiving that it does and it does, maybe it is not a good project anyway. I
mean, I am just trying to work through the reality of why you do it and I am
perceiving the reason you could waive your fees and I am perceiving that you are
waiving is because you really don't need to add any capacity. They are going to
handle, during that time whatever comes up anyway because you are not really
in the building yet. So you are not -there is no need for any extra. I am just
trying -the biggest thing is the financial end of it and does that really make that
much difference and for the marginal developer it probably does; for the solid
developer it is just maybe a little extra profit. I am just trying to work through all
of this risk because I think if we take arisk - if the public takes a risk in business
then we should get a bigger payoff. I mean, you always have the higher risk the
bigger reward. I know they don't want to pay anymore impact fee at the end of it.
Probably don't want to split their profit that we are perceiving to get from the
interest. I have a lot of questions where I am just not comfortable.
Zaremba: I don't know if I speak for everybody, but my interpretation of what we
are doing to waive these fees that we want and why we would ask you to defer
some of your fees, isn't necessarily that it would make or break a project. The
project either defends itself or it doesn't. What we are hoping to do is accelerate
a few projects that weren't going to happen -maybe some developer is saying I
am going to put this off until next year or two years from now. What we are
hoping it will do is be just enough -some of them will say okay I am going to go
ahead and do this this year and stimulate the economy that surrounds that and
be more prepared when the economy does come back and like I say, I didn't see
it as a method to either break a project, just to accelerate the timing of when
somebody would do a project they were going to do anyhow.
Baker: Do you see any projects that would fit the parameters that David talked
about? Are there ones out there that would be accelerated if we did this?
Freckleton: Right off the top of my head I don't think that there is any right in the
pipeline. We did have one recently and it wasn't because of this program, but
because of our ability to sit down and kind of accelerate some timelines, their
plan was to wait until spring of 2010. When we sat down we talked about our
timelines and made some commitments to this developer and they are moving
forward with that project currently. I think it is just trying to be a little bit more
flexible with them and offer some different opportunities to them. If I could get
back to the question from Councilman Zaremba it kind of depends on the
complexity of the project as to how long it takes. Certainly there are spec
projects that we will build and will potentially sit empty for a longer period of time
than one that is custom build. It is really a tough question to answer because of
the complexity and size of the project and who the tenant is.
Baker: I have been asking around about -even before this request came in and
talking to some people in the commercial development field and its way down,
way, way down. The problem is not - well, I think the problem is financing.
There are projects out there that have had financing and have started and have
had to have their financing jerked. I think my concern and I agree with Sheny
that this is an interesting concept, but my personal concern is that the foregone
dollars to the Highway District. I mean we are already looking at having to redo
our budget. We cut out a lot of capital projects, a lot of -hopefully not too many
maintenance projects, but I mean the only way that I can see this being
something I could support is if and you are not going to like this, along with what
Gary was saying is if for example, the City of Meridian would indemnify ACHD
against any loss that we would not have to go out and sue the developers for
those dollars and that you would give us the dollars and then you could sue
them. I mean, that is basically the only way and I am sorry, but I just think that
the timeframe is so small that it may not amount to anything way because we are
looking at three months from today and it would take probably ACHD two weeks
or a month to just come up with the parameters of this, which would make it two
months. Chances are there is not going to be a lot of projects coming up, but I
just think that with the financing situation and the money situation from our
revenues is just too iffy.
De Weerd: Madame Chair I guess just to answer Sherry's question on does this
add any value? And would it -- I guess be incentive enough to move a project
into the pipeline and what is the cost? Right now any of our money sitting in any
kind of investment is not generating anything. That money lost until from today
verses next year is very minimal. The jobs that you create or maybe the projects
that would tip a bankers frame of mind in the financing world today, it might be
enough. If you have ever had a construction loan, you know you are paying
more for the construction in interest than when you make it a permanent -when
you transfer it over from construction to occupancy and those kinds of things.
There is a savings to the investor, the developer in having a deferral of fees to a
later date than starting up front and paying the interest on it that whole time that
you carry the construction loan part of it. So there are some advantages on the
investor side, but disadvantages is going to be answering that question on
occupancy and I think that maybe the city and the Highway District can work
together on how to facilitate that. I mean, we can hold occupancy. I just think
that those need to be answered by our staffs if they haven't already come up with
them already.
Huber: But even with that, if we came to that my concern would be and maybe
you can legally hold somebody's occupancy because they owe us money, but I
would think just right off the bat that is an issue, but I think that we kind of
glossed over what I think maybe the answer is -which is if you identify - if
somebody comes into you and you identify you really want to help that project in
anyway you can - as long as I have sat I have heard them complain about the
timelines. You need to tell us hey that is a hot project, get on it and let's figure
out how to cut that timeline down to - I mean it is slower, so it is reasonable we
could do that because we don't have as many coming at us. So that would be a
savings to them -maybe not the same dollar, I am sure it is not, but at least it
would be a help that they don't have now trying to really compress that time.
De Weerd: I guess they are very interested in the timeline, but I did hear
someone make the comment of will you expedite a timeline so I can pay my fees
even quicker.
Huber: Well, but then they have to also put the pressure on contractor that
everybody can do things faster than dragging it out and it is an opportunity for
everybody now on timeline Ithink -something that maybe took a year before
that somebody can get done in a couple of months or six months or some period
of time.
Franden: Well, in my mind there is a couple of different issues and one of them
is equity and fairness to all who are in the development area. But the other is - I
feel really open to it, but I would want other than just a blanket or going out with a
hope and a prayer, is to have developer "a", if they really have a project that they
want to do and that if the impact fee was modified in someway would really help
them get that going -bring that in and let's listen to that and talk about it and see
what we can do, if we can make some adjustments or some modifications and if
it is possible then we should consider that.
Huber: But how do you do -are you drawing the distinction then that only
commercial people get this benefit? That if some other developer who is building
lots wouldn't get it? I mean, we try so hard for consistency I am not sure really
how you can give it to one and not give it to the other and I see Steve scratching
his head -equitably, if you were on the other side - I know there is a lot of lots,
so you are saying good luck that is probably not going to happen, but whatever
the case, you can make a case for a home builder, you could make acase - it s
not the money, but it is the concept. What is your basis for not treating them
equal, I guess is the question?
De Weerd: I guess what we are trying to do is stimulate the economy and the
hope and prayer for creation of jobs.
Huber: Well, new houses create jobs just as much as -may not be as many but
as commercial goes -
De Weerd: Well, I mean on occupancy.
McKee: I think based on what Sherry said the Commission would have to look at
if we gave you this nod, we would have to do it to the entire county.
Huber: Somebody needs to tell me what the reason would be for us to give
benefit to one group and not another. I think I need to understand that.
Price: Madame President, Commissioners and Council, the issue -let me just
tell you the legal issue. We have had this in the past and the distinction between
certificate of occupancy and a building permit from a highway district's
perspective is our leverage for payment is at the building permit. You can't build
unless you pay your impact fee. Where it is tricky is that if you condition the
payment of impact fee at the certificate of occupancy then you have developed a
substantive due process claim. There is a whole bunch of case law that says
that if a developer based upon the building permit and he builds and relies upon
that and he continues to build then he gets a vested property right and a
certificate of occupancy can not deny the ability to occupy because he then has a
vested right and so we do lose all of our leverage for the payment of impact fees
at that stage. Now, having said that that is just the legal issue, but our impact fee
ordinance and statute does allow the timing of the payment and he is correct and
there is the possibility of entering into an agreement with the developer or
commercial developer that would allow for that to occur based upon some type of
conditions. Another fear that you would have is that they would pay the impact
fee and they would contest the impact fee, (inaudible) at the end of the project
and then you will be embroiled in years of litigation over the calculation of the fee.
There are some things that you can do in the agreement to provide that added
assurance for the payment. Can you do everything? No. All you would be able
to do is limit the risk to the Highway District on the payment. Another distinction
from the city's impact fee verses the Highway District's impact fee is that your
fees are much smaller. I think it would be fair to say they are in the thousands
and ours are in the hundreds of thousands and so the risk is much higher for us
do that. Now am I concerned that the Legal Department will have more job
security by filing law suits against developers? That is not the intention. We
have already received a request today, in fact, ironic timing by Winston Moore
over a big development coming to Meridian over a couple hundred thousand in
impact fees. If you would like we certainly can work on an agreement with Mr.
Moore that would do everything that we could possibly do by bringing it to limit
the risk. Happy to do that and that is a big project and that is when he struggled
in trying to get into the Meridian community. He has successfully been able to
that. We have worked with him in reducing the amount of impact fees by getting
within the proper land use category. That is up to you. I just wanted to give you
a more direct perspective on the issue from the Legal Department and the things
that we can do legally to develop and at least reduce the risk. I don't think we
can eliminate it.
Huber: Aside from aname - we don't want to use Winston as an example, but in
any development. If they get -how will we and maybe this is what you are
talking about trying to ensure the risk -how is that we got half way through -
because I am kind of thinking of a big commercial development that just seems
to me it is going slow -they must have got some money somewhere -how do
we make sure that halfway through that their financing is going to go all the way
through. We are getting in a role of making an assumption that if we did this -
how do we protect ourselves if we did this -forget about the occupancy end, but
that something -they have a big changing order or they -how do we ensure
that? We have got a big hole downtown that is kind of -keep that name out of it
because it has got to be generic?
Price: Madame President, Commissioner Huber that is a very difficult issue and
you do have to come through with the letter of credit or something like that. But
then you have got to check your bank book, but that would be something that we
would have to explore more at length and that is a very difficult issue to deal with.
We would have to have some form of security. Again, you can't eliminate all of
the risks.
De Weerd: Madame Chair, you can't eliminate all of the risk, but if the project
doesn't happen it neither does the impact. I guess you can see all sides of this,
but if the project doesn't happen and that building is not occupied, you don't have
an impact on the roads. Just another perspective.
McKee: Any other comments or questions?
De Weerd: Do you have anything else Bruce?
Freckleton: Madame Mayor, Members of the Council and Commissioners, the
only thing 1 was going to add is I agree with what your counsel indicated.
Certainly I do believe there is case law that makes it a little bit questionable on
the occupancy. I have the discussion with our legal counsel and it was their
advice that the City of Meridian would also enter into separate agreements with
the developer. That agreement would state specifically that occupancy or
whatever point of time is agreed upon, would not transpire until the impact fee is
paid. This helps to strengthen the case for the District and to payment of that
fee.
McKee: Okay. Thank you.
Item 3. Meridian Split Corridor Phase II:
Goodell: Thank you. We wanted to begin a conversation today about the
funding of the Meridian split corridor phase 2. When the Commission adopted
the downtown plan in 2005 and did get a recommendation from Meridian to make
Meridian a main entrance into the split corridor configuration. When that
happened our understanding was that the split corridor was somewhere between
3 '/2 to 4 million dollars more than a one way couplet. The motion language was
said to direct staff to work with Meridian to begin the implementation of the plan
and the split corridor option by creating and proposing innovative ways to
schedule and fund the project. We as staff went to our Commissioners last week
and said we need your direction on what your thoughts are around this and their
response was well let's begin the conversation with the city at the joint meeting.
We have had very limited conversations with the city and at this point there
hasn't been any specific proposal for cost share -Meridian Development
Corporation and the city have not made any specific proposals, nor have we.
MDC did fund the landscaping and other features for the phase 1 portion of the
split corridor and at this point the project has been a little bit delayed and that is
because of the - oh, I am sorry I left one thing out. There was an informal
conversation that we had about potential cost share back when we were doing
our early right of way acquisition. There was some properties that became
available and our right of way folks approached the city about potentially
participating in some of that acquisition and the city declined at the time. It was
parcel specific conversation. But we really haven't had anything more formal or
specific than those little bits and pieces. At this point because of the revenue
decline, the split corridor phase has been delayed one year. The corridor phase
two construction went from 2012 to 2013 and we have right of way acquisition
scheduled for 2011 and 2012. We are in the design process as your staff is well
aware. We have our most recent cost estimates and it is approximately - I
apologize and I almost have to laugh because I don't really think we have a cost
estimate down to $5.30 on the split corridor. I think somebody forgot to round
that. But, at this point the difference is somewhere estimated to be $4.7 million
range and had we built the couplet verses the split corridor. What we would like
to do is ask for the Commissioners and the Council to have the conversation or
begin the conversation and give staff some direction on how you would like to
see us proceed with the question of funding.
McKee: Okay, I will open the floor.
(Speaker unknown): Well, Madame Chair in my mind it is important to know
what the city wants and we met at our meeting last Wednesday and Sally
indicated that the last communication with the city is that you would prefer the
split corridor and I wonder if that is still the case or if you had a chance to think
about it.
Rountree: I guess from my position the decision has already been made. 2005
split corridor. Hopefully that is what you are proceeding with design if you have
got projects scheduled and that is what the Commission adopted. To me, that is
a moot point. The cost numbers here I think are - I don't know if they -- when
they were generated, but I think to make the one way couplet to really work and
do it total is probably going to be what is estimated here in proportion to what is
estimated in the split corridor. The (inaudible) are numbers and they are not
even valid.
Zaremba: I think the question I would have is what are the original estimates
based on? If they are based on the study that was jointly done by Meridian and
ACHD that generated the decision to go for the split corridor and there was some
big amounts missing from the one way couplet costs. The one way couplet did
not consider what to do with the northeast end and the right of way acquisition
that would have to happen if you took out the Albertson's or took out five or six to
ten businesses south of Franklin - if you are going to have all of the northbound
traffic on Main Street, there needs to be a way to cross that traffic back over to
Meridian at some point. Now the split corridor does that south of the railroad
track. The estimate that was put into that report for the one way couplet did not
answer that question and if you are using that, we all decided at the time that it
was not politically possible to even put in writing in that report that one of the
options to solving the north end of Main Street was to take out Albertson's. We
couldn't put that in there. We also couldn't put in that one of the options would
be to take out ten businesses south of Fairview in order to have a cross over that
would meet at Cherry and Meridian intersection. So, the cost of actually doing
the complete one way couplet - if you are going on the steering committee's
report that is not included in there. What I would question is if we are going to
make a comparison between the completed project and say here is what the cost
difference is, we don't have the completed costs for the one way couplet. The
one way couplet would have to include a cross over somewhere that is not
included in the cost.
Franden: Well, what you are saying David is you have got to have apples and
apples and have everything included in there. I know engineering has told us
that as far as operational is concerned that the one way couplet and that there
isn't a lot of difference between the split corridor and the one way couplet.
McKee: Rebecca you had a comment and then Sherry.
Arnold: Yeah and I understand that there may be some need to look at the
numbers and to really figure out what the real difference in the cost is, but I think
it is important for us to talk about the concept of cost sharing here because for
me it is no different from aesthetic treatments that the city wants and when we
had the conversation and made some decisions three years or so ago, from my
perspective it was done on a handshake agreement that the city was going to
participate in that incremental cost. I was pretty vocal about that in a couple of
meetings and I know the Mayor was not very happy with me over some of the
comments I made. But, my position on that hasn't changed and from my
perspective if the city wants an aesthetic treatment or a treatment for economic
development and both of those things are important to the city and they are part
of your mission, I as a Commissioner am certainly willing to work with you to
partner on a project and come up with something that works to meet either that
aesthetic goal or economic development goal, but the incremental cost for the
aesthetics or economic development has to be born by the city. I can't justify to
my constituents spending taxpayer transportation dollars for a Ferrari when a
good old Chevy will do the same transportation job. We have to have a
conversation about the concept of cost sharing on this. Just the same as we did
for landscaping and other treatments. Obviously, the numbers may need some
refinement, but in the concept we have to have that conversation.
Huber: I am going to cut to the bottom line. The reason of what we just had
outlined on our cost sharing is so important this is a classic example of why.
Now, that wasn't in affect and we know there has been dis-portionate benefits to
Boise City over exactly the same issue really. We spent more dollars than what
you needed for the road. You can debate that forever. It is done. Now we are
here and I can remember the discussions from my perspective on the
Commission -yeah, Rebecca's position has stayed consistent. Absolutely. But,
I don't believe - I think the decision was made for two. I think that is what we
were going forward. The decision was, I think, through the discussion about the
difference that occurred. I don't think it was ever resolved and in fact - I can
remember even bringing up the same topic that I am now is yeah you are right, it
is more, but we have done that before so when do you draw the line? That is
why that cost sharing is so important because we do start to draw the line going
forward. We are already from my perspective in this, decisions were made, yes
we would appreciate some money, but on the other hand you have been the only
city that has ever done that - to give some credit. Whether it is on this project or
whether it is on the Locust Grove overpass to get something done. So I think it
does get into a lot and I think the lesson for us is we should have - we have done
the design and if in fact we were that strong, we shouldn't have done the design
it was an issue that we have to take some fault for too; I think it is fault that I
understand. But, let's get real about it. We did a design based on it and then we
come back to you and say cough up; well we should have had discussion as
Sally said in the concept design, but we never came to an agreement. We never
came to an agreement so we are here. I am just saying let's go forward. The
design is done. I believe in our minds that we had hoped -there was some
discussion because everybody is tight on money, but that is not the reality of
where we are right now in my mind.
Bird: I have been involved in hearing on these things since 1998 and I was the
one that voted for the Chevrolet. The only one. I never heard anything about the
city participating in this. We were given two options -actually three options and
that is what we were to vote on to give you guys and idea of where the wanted to
go. We have been consistent on our part, but never to my knowledge and I have
never missed many meetings, I never heard where the city has offered to kick in
money. Now we did on Locust Grove and was happy to. I cannot see us doing
that on this.
Arnold: Well, you may not have been at the meeting, but I distinctly remember
getting chewed on afterwards for being pretty vocal about cost sharing at that
time and we did move forward without nailing it down, but in my mind there was a
handshake deal that there would be some contribution by the City of Meridian
towards that project.
(Speaker unknown): Not in mine.
McKee: Okay, Charlie and then I am going to make a comment.
Rountree: Okay. I too have been involved in this for way too long and seen the
city never come forward to support a one way couplet -back in 1998 they didn't
support it and the citizens didn't support it and then it went through the study
process again and cooperatively done with ACHD and the city hired a consultant
to do a downtown master plan, a transportation plan and we ended up with the
downtown Meridian transportation plan, which resulted in the preference for the
split corridor. I think we both were involved in that process. I guess the caution
is that and having worked with these kinds of things for a years is don't - if ACHD
is only going to pay for the lowest cost project and I take exceptions that there is
(inaudible for the split corridor. It is pretty fundamental. A little more right of way,
but it is pretty fundamental cost wise, if you look at construction. It is pretty much
the same. There is more right of way with the split corridor, but you can add that
to the one way couplet to make it work.
(Speaker unknown): The north end
Rountree: Yeah. But anyway, I hope you don't take that philosophy with this
cost sharing approach because sometimes a better approach if as John says it is
correct and I have heard both of these operate about the same, there is a better
approach for the community. I mean this went through the process. A lengthy
process; an extensive process. This is where we came up. So, to me and it gets
the same irritation when somebody comes to us and says well we want to
comment and you say well you are going to have to pay for it. Then don't come
and ask me. Don't involve me. Come to me with what you are going to do.
Don't ask me to spend a lot of money in the community and time and tell people
that you know we want to do this downtown, we want the old town to prosper.
We spent a little money downtown to try and make it prosper and stimulate the
growth down there. Don't do that to anybody, please. If you are going to go into
these things in partnerships, understand that you know that the best result might
cost a little more. Now, if you wanted Meridian to partner on the cost of this then
that should have been in black and white the day we inked a cooperative
agreement to do a transportation plan. That is all I have got to say. I appreciate
your position because I probably would have been in the same position. I heard
it. As opposed to Keith, I heard it.
Bird: I heard her say that, but I never heard at any time the city say that they
would participate on that cost.
Rountree: Just to finish, we have been in this for a long time and you guys have
been bringing designs and concepts to us and saying here what do you think?
And yeah, we like that and go forth and do good things and it is still nothing has
been inked and nothing has been brought up until today, well, what is the
partnership going to be?
McKee: Charlie I agree with you and I agree with Commissioner Huber. I think
that if we were going to do anything about a cost share oh this project, we should
have done it back in 2005 when we adopted the split corridor; even before that.
Now if the Commission has to do something internally to solve that problem, then
that is what we have to do, but it shouldn't be born by anybody else. The split
corridor has been in the five year work plan for years now ever since I have been
on the Commission. Every year and I have been voting for it and I have not
voted for it with an agreement from the City of Meridian that you were going to
pay for part of it. I have been voting for it and trying very hard to get it moving
forward. So, I have no intention of supporting coming out at this late date and
asking you for anything.
(Speaker unknown): It has been brought up before.
McKee: But we didn't get anything in writing, nothing inked. We didn't do the
work that we needed to do as a Commission back in - four or five years ago.
Arnold: Well, we won't make that mistake again. We will have it writing
McKee: That is what we need to move towards, but we can't go backwards for
something that we have worked on even before I remember sitting in those
meetings with Dave Wynkoop up there and I never saw so many different
corridor choices that you guys had. I sat back there thinking how are they ever
going to whittle this down to one? They just went on and on and on. So this is a
process that has been going on for years and years and if we were going to do a
cost share agreement, we needed to do it way, way before this. David and then
Sara.
Zaremba: Just from my perspective, the discussion we are having right now
does not threaten my support for the cost sharing policy. I view the cost sharing
policy as a thing that says if the city wants an embellishment, the city has to pay
for it. I can support a policy where we work that out -what embellishment are
we willing to pay for and don't expect ACHD to pay for it either in Meridian or in
the cities around for embellishments. I mean it is for our protection as for
anything else. The distinction I see on this one is I don't see this as an
embellishment. I think that if we work out the true cost of the one way couplet,
this is actually cheaper. Where we are making the cross over is far cheaper
property than you could have done for the cross over for the one way couplet and
there has to be a cross over somewhere which was not included in the one way
couplet. My feeling about this one is we are actually saving you money. So, that
is one of the reasons I would resist kicking in. We need to compare apples to
apples.
Baker: And that is basically - if the costs are not true, the costs need to be trued
up so that this - so we can actually see. But, it sounds to me as if the split
corridor is the way too go. So there really is no reason to talk about it anymore.
The issue that I thought that was brought to us by Sally at our last meeting was
to clarify the costs. We don't have to do that now. Probably should refine the
split corridor cost and then just move forward with that as quickly as possible and
I do think it needs to be done as quickly as possible. These projects that take
and I know it is a function of money, but these projects that take years do nothing
to provide support for the community to anybody. It is just so irritating when it is
a constant construction zone or it is half done and come back and do the rest
later. So, I think that is going to be our task and our test is to get this second
phase done as quickly as possible.
Huber: Just a follow up. Whatever the cost is they are going to get to the final
cost and it is going to relate to the budget and how we juggle the money. Do we
have to come back and say hey this is $5 million more than we thought it was
going to be just because that is why, so is there a project that you want to cut out
to keep this on track? I don't even know if that is the case, but I am just putting
out that budgeting numbers and actual numbers in order to keep a project on
track is not unusual. We do it all the time and usually if it is a real biggie we will
ask, but sometimes we shift around so I am just saying from my perspective I
think what has happened here is an example of why people get mad at each
other. I think -that is why I early on said we have got to take our hit where I
think we deserve it and move on and forget about it. I know the reasons why, so
move on. Who cares? Our policies should address it, but that would be my
caution that when we look at this and it sounds like there are at least three of us,
I am not sure where John is, but saying let's move on and let's get it done, but I
am cautioning -where the dollars is -with the budget - I mean that the only
caution is - I don't want you guys to be offended or think it is a penalty because
we came back and said you know here is where we are with money and we
might have to shift and we might not be there, I don't know, but it wouldn't
surprise me. Because that is why my favorite project keeps getting pushed over
your priorities. over mine and that is McMillan and Victory. And that is because
you guys have had things you would rather have done.
Baker: So the one way couplet is gone?
McKee: It has been gone for quite a number of years.
(Inaudible discussion)
McKee: Okay, on this piece of paper it says that these are current estimated
costs for 2009 June, which is now. So are we agreeing with that? You guys
went through the numbers and you feel that the two -
Zaremba: But that doesn't include a cross over at any place.
McKee: Just the split corridor.
Goodell: We updated the cost as we do each year so they should be up to date
costs and I actually asked Steve that earlier in the conversation and he said
Meridian intersection that might require a reconfiguration and we try and take that
under consideration and the question that you were asking about the north end -
the purpose in providing the dollars is actually - I mean if you want us to go back
and refine them and be more accurate we can if that helps the conversation that
really -
McKee: I just wanted it to mean that these are not five or six year old -that
these are current numbers. That is all I care about.
Huber: With the impression of what I am talking about -the should have, could
have, would have - I don't want it to be blamed on staff either because clearly it
goes back to the Commission didn't make it clear and that is our fault. The staff
did what they believed right. So, it is on us.
De Weerd: Yeah, I know the discussion was had and we all had our opinions
and I guess because nothing did happen, we thought a decision was made. But,
I would go back to just reiterate what Charlie has stated. If you want to include
the public with the process in the decision making that was the recommendation
that came forward. And expectations need to be cleared that that is why we
support TLIP and it does clear up those expectations and it maybe helps alleviate
any future issues like this, but our community is your community too. The public
that participated are your constituents as well as ours. So we are doing this for
our mutual constituents. It is not us against you or anything like that. We all
have a stake and making transportation systems that are efficient and that
compliment a community. I think that is what the value of this process was from
our perspective and it had a lot of public participation, a huge amount of dialogue
and a decision was reached. We appreciate - I tell you to your staff that the
comments that we have had on phase one even though it changes the obstacle
course almost everyday, they already see the efficiencies and the vision that has
been set and there is a great deal of appreciation. So, our hats off in phase one
and we look forward to moving forward on phase two where there is a
partnership and the TLIP aspects of it and we need to get to what those beyond
the basics and let's move forward.
McKee: Well said. Any other comments? Okay, staff you understand we are
good to go, right?
Item 4. Joint Meetings:
McKee: Do we need to set the date for the next one or --?
De Weerd: Madame Chair I guess I appreciate the as needed basis and there
are legitimate reasons to come together, like we have had today - a very
important dialogue and we don't want to say joint meetings are not needed
because they are. We have enough issues that come up that it is so important
that we are on the same sheet and today we reiterated the need for that.
McKee: Absolutely. I think we can get -
Franden: I agree that when we have something that is substantive and when we
really have something to talk about, but we have run into too many incidents not
with Meridian necessarily, but over the last few years we meet -and then we get
to the point where we are meeting to plan meetings to meet. I have over the
years become really quite frustrated at how inefficient government can be with its
time, not necessarily its money -
De Weerd: But our time.
Franden: Everybody's time. We are all too busy.
Rountree: I just wanted to comment that I think today's meeting is the kind of
meeting that we should have. It was very informative to me and I think we
hashed through some issues and hopefully we continue to be able to have these
frank and honest dialogues and that is the only way it is going to work. I did
want to send a kudos to your staff because last Tuesday night we had a
presentation on speed limits, was it not? And going around town the past few
days it appears that most if not all of the speed limit changes have been made,
there are lots of orange flags around town and I really appreciate the work they
did to get there and the expeditious manner they went about getting there. The
new speed limits that they have posted.
De Weerd: Avery informative presentation too and how we were educated and I
will -John we don't put things on this agenda that we can't work out with staff
and I appreciate Commissioner McKee's meeting with myself and our staff and
Jay to address something where we can deal with things offline. Certainly that is
our preference. I think it is only when it needs to be brought up to the
Commission level and Council level that we want to have these meetings.
McKee: Well, we appreciate that. We have done everything with the
Commission to cut our budget and so throwing that out with meetings on a
needed basis, they are important, but it also helps our budgeting process and
right now we all should be concerned about putting our dollars out there on the
ground and doing everything we can and limiting everything we can and so we
appreciate your time too. We did get a lot done.
(Speaker unknown): I want to throw something out here. Meridian Food Bank
talked with members of the Board and thanks to ACHD for that lease of the
dollar. That has been a great deal and now the building that has been added has
really helped our community greatly and it has been a great location and really
do appreciate it.
McKee: Well, as the Mayor said your community is our community. We are all in
this together and we are very grateful that we could do that.
Zaremba: Well I would also chime in on the thanks for the presentations that
were made and also just the consistent generosity of the Commission allowing
your staff to work with our staff, which they do all year long, everyday and we
appreciate that. I have one very minor question, if and when we do have these
meetings is Monday the best day for you guys?
McKee: Actually Wednesday is the best days.
Arnold: Only if they come here.
McKee: Yeah, then it would have to be what is the best day for you.
De Weerd: Any day is okay.
Freckleton: I would like to ask the Board for some direction. At staff level we just
kind of need some direction on which way you folks would like to move on that.
McKee: We are still in the perplexed stage and we need to have a discussion.
We will talk it over with staff and with legal. There are some questions that we
have about whether or not we can accommodate you.
Rountree: To that point, Madame President, I think there are two things. One
you mentioned the possibility of reducing the timeline in terms of - and I think
John mentioned the idea of providing some flexibility to developers based on
their business plan finances and the kinds of opportunities that you could change
the timing of that collection of that permit. That that could be more of a policy or
guidance statement in the policy that its there and we can offer -since we are
the shop they come to we could offer that to them; we can't defer it but there is
an option for you to go and make a presentation to ACHD, give them what it is
you are proposing to do and what you are agreeing to do in terms of paying that,
but maybe it is an 18 month project, we don't want to pay it when we get a
building permit. We want to pay it when we know we have got occupancy to a
level that we can open the thing up.
McKee: Developers are always welcome to come in and ask us. Our doors are
open to anybody who wants to come in and ask the Commission for an
acceptance or a variance.
De Weerd: Madame Chair our agreement with you is that we will collect it at
building permit, so we will need to - if you negotiate something with them, we
have to have that within our process too and I think that is why Bruce is asking
for clarification.
McKee: Keep doing what you are doing and if there is something different then
we will let you know. We have to figure that out.
De Weerd: We do need to update our agreement and I think we are working on
that.
Arnold: But that agreement is likely to stay the same on that it would only be
maybe if we carve out some exception, it is not going to stay that way forever. I
mean -the agreement is really the standard and if we want something different
we need to let you know. That will help that process -
McKee: All right. Thank you.
Item 5. Other:
(AUDIO ON FILE OF THESE PROCEEDINGS)
APPROVED:
~~~.n. (Z
C~IA.t.~c.l ~OUw~.R'
Counul 1.~c~r'c~-
\,.~~~y OF M 3~EC
SEAL
~,'~
':~9Q~~t tSt • l~P~~:`
`~ / z z / e~`i
DATE APPROVED
L. HOLMAN, CITY CLERK