HomeMy WebLinkAboutBudgeted Contract Amendment No. 5 with Tri State Electric for Phase 3 Tenant Improvements New City Hall (2)CITY OF MERIDIAN
33 EAST IDAHO
MERIDIAN, ID 83642
BUDGETED CONTRACT AMENDMENT
BUDGETED CONTRACT AMENDMENT
N0.06
PROJECT NO. CH-06-001
DATE: 2/10/09
EFFECTIVE DATE:
CONTRACTOR: TRI STATE ELECTRIC
PROJECT: MERIDIAN CITY HALL -Phase 3 Tenant Improvements
The Contractor is hereby directed to make the following changes from the Contract Documents and Plans.
Description: Repaint due to trade damage
ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.
Reason for Budgeted Contract Amendment: Additional scope or revisions per listed ASI's, RFI & Changes
Attachments: Change Items description, dated 2/10/09, with contractor quotes
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price $2,749,895.00 Original Contract Times: Substantial Completion 8/28/08
Net changes form previous Budgeted Contract Amendment: Net changes form previous Budgeted Contract Amendment:
No. 01 to 04 No._ to _ (calendar days)
$141,902.74 None
Contract Price Prior to this Budgeted Contract Amendment: Contract Times prior to this Budgeted Contract Amendment:
(calendar days or date)
$2,891,797.74 si2si2oo8
Net decrease of this Budgeted Contract Amendment: Net Increase (decrease) of this Budgeted Contract Amendment:
(calendar days or date)
x$1,026.00) None
Contract Price with all Approved Budgeted Contract Contract Times with alt Approved Budgeted Contract
Amendment: Amendment:
(glendar days)
$2,890,771.74 Substantial Completion 8/28/2008
/
RECOMMENDED: (CONSTRUCTION GER ~ ACCEPTED: (CONTRACTOR)
Petra Inc. ~ Tri State Electric
~ ~
~
By: Thomas R. Coughlin By: Jay Gooden
~
Date: ~ O ~ ~ Date: ~ t 1 ~S' ~
APPROVED: (CITY PURCHASING AGENT) COUNCIL APPROVAL
By: Keith Watts
Date: Date:
APPROVED: (cn~ - ATTEST:
By: Mayor Tammy de Weerd By: City Clerk, Jaycee Holman
Date: Date:
323-4500
BOISE, IDAHO
RCE-1875
CHANGE ORDER
~~ ~ ~ ~ ~ ~~ No. 00006
~~ MAR 2 0 2009
1097 N. ROSARIO STREET • MERIDIAN, ID 83642 • PHONE: (208) 323-4500 • FAX: (208) 323-4507
TITLE: Backcharge due to trade damage DATE: 2/10/2009
PR07ECT: Meridian City Hall 70B: 060675
TO: Attn: Jay Gooden CONTRACT NO: 34
Tri State Electric
7790 Mossy Cup
Boise, I® 83709
Phone:208-362-4636 Fax:208-362-1716
RE: To: From: Number:
DESCRIPTION flF CHANf~
The following CO is for your records and reflects previously approved changes to the scope of work. Please sign and return to
our office within 3 business days.
' Tax Tax Net
Item DescriPn Qa~ntity Un#s Unit Price Rate, Amount Amount`
00001 Repaint due to trade damage -equal share of damages. 1.000 LS ($1,026.00) 0.00% $0.00 ($1,026.00)
Unit Cost: ($1,026.00)
Unit Tax: $0.00
Lump Sum: $0.00
Lump Tax: $0.00
0.0% GC markup: $0 00
Total: ($1,026.00)
The Original Contract Sum was .................................................................................................
Net Change by Previously Authorized Requests and Changes ............................................ $2,749,895.00
$141
902
74
....
The Contract Sum Prior to This Change Order was ...................................................... ,
.
$2
891
797
74
The Contract Sum Will be Decreased .... ,
,
.
...............................................................................
The New Contract Sum Including This Change Order ...................................................... ($1,026.00)
$2
890
771
74
The Contract Time Will Not Be Changed ................................................. ,
,
.
................................
The Date of Substantial Completion as of this Change Order erefore ..............................
ACCEPTED:
Tri State EI t ~'c Petra Incorpora LCA Ar hitects, P
By' ~ ~ W~ BY• By.
Jay Goo`den Tom ou Steve Christensen ~
Date: ~'tD~ 1 Date: ~ ~ ~ ~ Date: t~ ~ ~i` o
Expedition