HomeMy WebLinkAboutChange Order No. 3 with Rule Steel for Settlement of Liquidated Damages New City HallCITY OF MERIDIAN 33 EAST IDAHO MERIDIAN, ID 83642 CONTRACT CHANGE ORDER CHANGE ORDER NO. 03 PROJECT NO. CH-06-001 DATE: 2/4/2009 EFFECTIVE DATE: CONTRACTOR: RULE STEEL PROJECT: MERIDIAN CITY HALL -Settlement of Liquidated Damages The Contractor Is hereby directed to make the following changes from the Contract Documents and Plans. Description: Settlement of all issues related to liquidated damages and contractor requested time extension, painting back charges and remedial work on sunshade frames . ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME. Reason for Change Order: Settlement of liquidated damages Attachments: Change order items description, dated 3/11/09, with contractor quotes CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price $1,847,000.00 Original Contract Times: Substantial Completion 10/5/07 Net changes form previous Change Orders Net changes form previous Change Orders No. 0 to 01 No._ to _ (calendar days) $79,485.00 None Contract Price Prior to this Change Order. Contract Times prior to this Change Order. (calendar days or date) $1,926,485.00 1o/5i2oo7 Net lnsrease (decrease) of this Change Order. Net Increase (decrease) of this Change Order. (glendar days or date) ($15,750.00} 97 Calendar Days Contract Price with all Approved Change Orders: Contract Times with all Approved Change Orders: (glendar days) $1,910,735.00 ~ ~g Substantial Completion 1/11/08 RECOMMENDED: (CONSTRUCTION R ~ AC~EPTED: (CO OR) Petra Inc. ule Steel '- By: Thomas R. Co ghlin By: Ron Allen g Date: ~ ~ ~ ~ Date: ~ I ' G _ 6 APPROVED: (cnY PuRCliASwG AGENT) COUNCIL APPROVAL By: Keith Watts Date: Date: APPROVED: (Cn'Y) - ATTEST: By: Mayor Tammy de Weerd By: City Clerk, Jaycee Holman Date: Date: , ANGE ORDER 1097 N. ROSARIO STREET • MERIDIAN, ID 83642 • PHONE: (208) 323-4500 • FAX: (208) 323-4507 TITLE: Settle of Outstanding Liq. Damages DATE: 2/4/2009 PROJECT: Meridian City Hall JOB: 060675 TO: Attn: Steve Norquist CONTRACT NO: Rule Steel 21986 Middleton Road Caldwell, ID 83605 Phone: 208 585-3031 Fax: 208-585-2506 RE: To: DESC~1>TICV O~ CH~If~GE___ ____-._.. * * All taxes are included in costs From: Number: ~; ..... :: Ta>ir`~- Tax _INet T}pm pp~.-r~ _._Q~~t~tlf Unit. 4tl+~t:~r gate. A4riQSInt~=~ ~AttfS~~uRlt::.._. 00001 _ Settlement of all iswed related to Contractors time extert~on requests and the 1.000 Is ($14,000.00: 0.00% $0.00 ($14,000.00) assessment of liquidated damages for delays in completing the project by tine oontrada~al substantial completion date. Contrad~r is granted a time exter~on equal to 97 calendar days for the ASTs -7,8,13,18,23,52,54,RFI-74 Bent Plate and weather delays. The 97 calendar days would. extend the contract substantial completion date from Odnber 5, 2007 to ]anuary li, 20.08. The 97 calendar days is to be considered full and final setiiement of aU requests and daims for additional tame and costs related to ' the project This would include all n~uests related to weather delays and delays bo the original sd~eduled Start date. No time extensions are grented for ASPs 13 & 19, RFTs -.73,74, 93 & 94. The Contractor:was deemed Substantial Complete as of February 8, 2008. The difference between the new propo~d conbadual substantial wmpletion date of 7anuary 11, 2008 and the ada~al substantial completion date of February 8, 2008 i5 28 calendar days. . Unit Cost: ($15,750.00) Unit Tax: $0.00 . Lump Sum: $0.00 Lump Tax: $0:00 • OA% GC markup: $0.00 Total: ($15,750.00) The Original Contrract Sum was ................................................................................................. $1,847,000.00 Net~Change by Previousf~/ Authorized Requests and Changes ................................................ $79,485.00 The Contract Sum Prior to This Change Order was ...................................................... $1,926,485.00 The Contract Sum Wi11 be Decreased ................................................................................... ($15,750.00) The New Contract Sum Including This Change Order ............... ..................................... $1,910,735.00 The Contract Ti me• Will be'Increased ........................................ ............. ......................... 97 days The Date of S4tistanttal Compie,~ion as of this Change Order The ore is .~ .......................... 2/11/08 ACCEPTED: Rnle Steel ~ • .. Date: Expedition Petra lay: Date: LCA Arc rtects, P Bn 1x0 ~"Q Qp,Q,~~„~- Steve Christensen Date: _ ~, ~'zi• dG - ,,,~- CHANGE ORDER - - ~°~ No. 00003 -. 323-4500 BOISE, IDAIiO RCE-1875 n, 1097 N. ROSARIO STREET • MERIDIAN, ID 83642 • PHONE: (208) 323500 • FAX: (208) 323-4507 TITLE: Settle of Outstanding Liq. Damages DATE: 2/4/2009 PROJECT: Meridian City Hall .JOB: 060675 TO: Attn: Steve Norquist CONTRACT NO: 6 Rule Steel 21986 Middleton Road Caldwell, ID 83605 Phone: 208 585-3031 Fax: 208-585-2506 RE: To: From: _.r x ~ ~: ~PTIQ_.A1 4F CH~~E; The Contractor is to be assessed liquidated .damages for.the 28 plendar days their work extended beyond the contfactual sut~stantial completlon date. Per the • contract liquidated damages are assessed at a rate of $500/day. 'fie total cost th Fx assessed against the centrador for the 28 calendar days at $500/Day is $14,000. For further details reference attad~ed Petra memo to Keith Watts, City of Meridian, dated 11/19/08; Re: Rule Steel -Time Exten~on & Uquidated Damages -Meridian City Hall. 00002 Sunshade Remedial Work - Latmr and equipment to tondo 8< smooth rolls marks and seams in sunshade steel members. Roll marks and seams are normal for struda~ral st~l unless spedfically noted as arrhitecturel exposed. Rule Steel quote 8/28/08. 00003 Badccharge for additronai painting work done on sunshade steel after misplace dips had to be rep-looted. Commerdal Painting invoices #290275, dated 10/1/08 & #290277, dated 10/3/08 00004 -Qada~arge for.removing sunshade panels installed & removed when it was determined that the dip location was wrong and had to tie re-done. Custom Glass irnoice #12255, dated 9/30/08 00005 Badccharge for fan rental for stairway ventilation when stair handrail returns were be reworked: Tates invoice~l0/3 Number: 1.000 LS $2,943.00 0.00% $0.00 $2,943.00 1.000 LS ($1,105.00) 0.00% $0.00 ($1,105.00) 1.000 LS ($1,000.00) 0.00% $0.00 ($1,000.00) 1.000 LS ($176.00) 0.00% $0.00 ($176.00) Unit Cost: ($15,750.00) Unit Tax: $0.00 . Lump Sum: $0.00 . Lump Tax: $0.00 0.0% GC markup: $Q.00 Total: ($15,750.00) The Original Contract Sum was ...............................:................................................................. $1,847,000:00 Net Chafi~ge by Previously Authorized Requests and Changes ................................................ $79,485.00 The Contract Sum Prior to~This Change Order was ...................................................... $1,926,485.00 The Contract Sum. Will be Decreased ................................................................................... ($15,750.00) The New Contract Sum:Including This Change Order ...................................................... $1,910,735-.00 The Contract Time Will be Increased .:.............................:................................................ 97 days The Date of Substantiar Completion as of this Change Order Therefore is .............................. 2/11/08 ACCEPTED: ' . ~ .~ Rule Steel Petra Incorporated ~ ~ LCA Architects, PA By; . ~ ~ By: ~ sy: Steve rquist ~ ~ T oughlin Steve sen . Date: ' - Date: Date: Fxpedidoa ®. ~ Page 2 of 3 . ~ ~ CHANGE ORDER ~~ ~ No. 00003 323-4500 BC}ISE, IDAHO RCE-1875 1097 N. ROSARIO STREET • MERIDIAN, ID 83642 • PHONE: (208) 323-4500 • FAX: (208) 323-4507 TITLE: Settle of Outstanding Liq. Damages DATE: 2/4/2009 PR07ECT: Meridian City Hall 70B: 060675 TO: Attn: Steve Norquist CONTRACT NO: 6 Rule Steel 21986 Middleton Road Caldwell, ID -83605 Phone: 208 585-3031 Fax: 208-585-2506 RE: To: From: Number: DEI~TTON OF Cfsh~lG~~ T _ __ Tax T~'1t _ ;Net . I___,_IiQtion Q,utY--.Units U~Pri+.~e Rite Am_o~tl~ 1nChuln~=.: 00006 Badcd~arge for additional painting & prep work on the stair rail returns that 1.000 LS ($2,412.00) 0.00°/a $0.00 ($2,412.00) were revi~d to meet Code. The additlonal work was done on Rule Steels request and behalf by Commerdal Painting. Commercial Painting invoice #3391, dated 10/10/08 Unit Cost: ($15,750.00) Unit Tax: $0.00 Lump Sum: $0.00 . Lump Tax: $0.00 0.0% GC markup: $0.00 Total: ($1.5,750.00) The Original Contract Sum was ................................................................................................. $1,847,000.00 Net Change by Previously Authorized Requests and Changes ................................................ $79,485.00 The Contract Sum Prior to This Change Order was ...................................................... $1,926,485.00 The Contract Sum Will be Decreased ................................................................................... ($15,750.00). The New Contract Sum Including This Change Order ...................................................... $1,910,755.00 The Contract Time Will be Increased ................................................................................. 97 days The Date of Substantial Completion as of this Change Order Therefore is .............................. 2/11/08 ACCEPTED: Rule Steel Petra Incorporated LCA Architects, PA By: By: sy: Steve Norquist Date: Expedition Tom Coughlin Date: Steve C tensen Date: Page 3 of 3 MERIDIAN CITY HALL PROJECT NO: CH-06-001 RULE STEEL -Phase 2 (06) CHANGE ORDER NO 3 03/11/09 CHANGE ORDER ITEMS Settlement of all issued related to Contractors time extension (14,000.00) requests and the assessment of liquidated damages for delays in completing the project by the contractual substantial completion date. Contractor is granted a time extension equal to 97 calendar days for the ASI's -7,8,13,18,23,52,54,RFI-74 Bent Plate and weather delays. The 97 calendar days would extend the contract substantial completion date from October 5, 2007 to January 11, 2008. The 97 calendar days is to be considered full and final settlement of all requests and claims for additional time and costs related to the project. This would include all requests related to weather delays and delays to the original scheduled start date. No time extensions are granted for ASI's 13 8~ 19, RFI's - 73, 74, 93 & 94. The Contractor was deemed Substantial Complete as of February 8, 2008. The difference between the new proposed contractual substantial completion date of January 11, 2008 and the actual substantial completion date of February 8, 2008 is 28 calendar days. The Contractor is to be assessed liquidated damages for the 28 calendar days their work extended beyond the contractual substantial completion date. Per the contract liquidated damages are assessed at a rate of $500/day. The total cost to be assessed against the contractor for the 28 calendar days at $500/Day is $14,000. For further details reference attached Petra memo to Keith Watts, City of Meridian, dated 11/19/08; Re: Rule Steel -Time Extension & Liquidated Damages -Meridian City Hall. 2 Sunshade Remedial Work -Labor and equipment to 2,943.00 bondo & smooth rolls marks and seams in sunshade steel members. Roll marks and seams are normal for structural unless specifically noted as architectural exposed. Rule Steel quote 8/28/08. 3 Backcharge for additional painting work done on sunshade (1,105.00} steel after misplaced clips had to be re-located. Commercial Painting invoices #290275, dated 10/1/08 & #290277, dated 10/3/08 4 Backcharge for removing sunshade panels installed & removed (1,000.00} when if was determined that the clip location was wrong and had to be re-done. Custom Glass invoice #12255, dated 9/30/08 5 Backcharge for fan rental for stairway ventilation when stair (176.00) handrail returns were be reworked. Tates invoice 10/3 6 Backcharge for additional painting & prep work for the stair rail (2,412.00) returns that were revised to meet code. The additional work was done on Rule Steels request and behalf by Commercial Painting. Commercial Painting invoice #3391, dated 10/10/08 (15,750.00} Page 1 of 1