HomeMy WebLinkAboutChange Order No. 2 with Rule Steel for Phase 2 Core and Shell New City HallCITY OF MERIDIAN 33 EAST IDAHO MERIDIAN, ID 83642 CONTRACT CHANGE ORDER CHANGE ORDER NO. 02 PROJECT NO. CH-06-001 DATE: 06/10/08 EFFECTIVE DATE: CONTRACTOR:. RULE STEEL PROJECT: MERIDIAN CITY HALL -Phase 2 Core 8~ Shell The Contractor Is hereby directed to make the following changes from the Contract Documents and Plans. Description: Incorporate revisions per ASI's 13, 52, 54 and RFI's 73, 74, 93 per attached PCO#2, dated 4/7/08 ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME. Reason for Change Order: Additional scope or revisions per listed ASI AND RFI Attachments: Change order items description, dated 4/6/08, with contractor quotes CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price $1,847,000.00 Original Contract Times: Substantial Completion 10/5107 Net changes form previous Change Orders Net changes form previous Change Orders No. 0 to 01 $35 766 00 No._ to _ (calendar days) , . None Contract Price Prior to this Change Order: Contract Times prior to this Change Order. $1 882 766 00 (calendar days or date) , , . 10/5/2007 Net Increase (decrease) of this Change Order. Net Increase (decrease) of this Change Order: $43 719 00 (calendar days or date) , . None Contract Price with all Approved Change Orders: Contract Times with all Approved Change Orders: $1,926,485.00 (Calendar days) Substantial Completion 10/5/07 a RECOMMENDED: (CONSTRUCTtoN R~ j' CCEPTED: (CON OR) T Petra Inc. .~~ ~° Rule Steel By: Thomas R. Coughlin~A By: Ron Allen Date: j~/'~ ~ Date: ~ ~ ~ ~ ~ G7 APPROVED: (CITY PURCHASING AGENT) COUNCIL APPROVAL By: Keith Watts Date: Date: APPROVED: (CITY) - ATTEST: By: Mayor Tammy de Weerd By: City Clerk, Jaycee Holman Date: Date: PRO ~ rHaNGF O~ ER ~~~ D ~C~~Q~~~ 323-4500 MAR 2 4 2009 BOISE, IDAHO RCE-1875 ,,, Rv ~ I~ il/l~u /1 1097 N. ROSARIO STREET • MERIDIAN, ID 83642 • PHONE: (208) 323-4500 • FAX: (208) 323-4507 TITLE: ASI & RFI Revisions DATE: PROJECT: Meridian Ci Hall 4/7/2008 ~ JOB: 060675 TO: qty; gill Byerly CONTRACT NO: Rule Steel 6 21986 Middleton Road Caldwell, ID 83605 Phone: 208.585-3031 Fax:208-585-2506 RE: To: From: blE:SCF~`IIb`N O% PROPO1i_ **AII taxes are included in costs** Itenp Q~craptid!rt: :. - ~d~n~itY 00001 ASI#13 Elevator Rails- Tube Columns (COR#8)- 1.000 Furnish & install 12 additional elevator tube columns. Replace original 4 with heavier wall tub. Rule Steel quote 1/17/08 00002 ASI#52 Elevator PH Beams (COR#2)- Add 4 1.000 beams at elevator penthouse and provide additional deck supports. Revised existing framing. Rule Steel quote 1/22/08 00003 ASI#54 Adj Roof Elevation & Add TS Support 1.000 (COR#3)- Provide tube steel at stair tower to adjust roof elevation. Rule Steel quote 12/18/07 00004 RFI#73 Sun Sa~een Attachment Revision (COR#4)- 1.000 Modify top attachment for sun screen hangers. Rule Steel quote 1/22/08 00005 RFI#74 Angel Gips @ Slab Edge (COR#5)- Add 1.000 angle clips for additignal support at studs to support wall that doesn't bear fully on slab. Rule Steel quote 1/22/08 & 11/13/07 00006 RFI#93 Relief Angle @ Stair Towers (COR#6)- 1,000 Furnish relief angle at stair towers. Rule Steel quote 2/26/08 Number: ';Units ' . Unit Price:. Tax Date :;7ax Amriunit tV~et Anti nt ~ $18,883 00 . 0.00% $0.00 ou $18,883.00 ~ $3,284.00 0.00% $0.00 $3,284.00 "~ ~ $1,351.00 0.00% $0.00 $1,351.00 ~ ~ $2,894.00 0.00% $0.00 $2,894.00 ~ $9,094.00 0.00% $0.00 $9,094.00 ~ $2,939.00 0.00% $0.00 $2,939.00 Unit Cost: $43,719.00 Unit Tax: $0.00 Lump Sum: $0.00 Lump Tax: $0.00 0% GC Markup: $0.00 Total: $43,719.00 APPRt)VAL: By: ~,~ ~' -- sy: By. Petra co rated le Steel Lombard Conrad Architects Date: ~ ~ ~ Date: ~ ® Date: Damon ® ~ ~ ~ 8 ~j PROPOSED CHANGE ORDER No. 00002 323-4500 BOISE IDAHO RCE-1875 1097 N. ROSARIO STREET • MERIDIAN, ID 83642 • PHONE: 208) 323-4500 • FAX: (208) 323-4507. TITLE: ASI & RFI Revisions PRO]ECT: Meridian City Hall TO: Attn: Bill Byerly Rule Steel 21986 Middleton Road Caldwell, ID 83605 Phone: 208 585-3031 ~~ To: Fax:208-585-2506 From: bESC1~'t~1V ~F P[tOPOiSAL ~ _ . Item Descr{~~jgn Qlual~tty 00007 RFI#94 Chiller Support i3eams (COR#7)- Furnish 1.000 and install 2 beams on the chiller support stub columns to support the chiller unit Rule Steel quote 2/26/08 00008 Time extension for ASI & RFI's issued to date: 1.000 number of days to be determined->cost to be determined DATE: 4/72008 SOB: 060675 CONTRACT NO: Number: 6 Units Unit.Pri~ Tax Rate: `T~c Ambu~tit Net Amount ~ $5,274.00 0.00% $0.00 $5,274.00 ~ $0.00 0% 0.00% $0.00 $0.00 Unit Cost: $43,719.00 Unit Tax: $0.00 Lump Sum: $0.00 Lump Tax: $0.00 GC Markup: $0.00 Total: $43 719 00 APPROVAL: By: By. By. Petra I rporated Ru teel Lombard rad Architects Date: Date: . Date: Expedition Page 2 of 2 MERIDIAN CITY HALL PETRAINC PENDING CO ITEMS Rule Steel -Phase 2 (06) PCO #02 -ASI &RFI Revisions 1 ASI 13 Elevator Rails -Tube Cols (COR#08) Furnish i;< install 12 additional elevator tube columns. Replace orig 4 with heavier wall tub. Rulr Stl quote 1/17/08 2 ASI 52 Elevator PH Beams (COR#02) Add 4 beams at elevator penthouse and provide add'I deck supports. Revised existing framing Rule Stl quote 1/22/08 Rev 3 ASI 54 Adj Roof Elev & Add TS Support (COR#03) Provide tube steel at stair tower to adjust roof elevation. Rule Stl quote 12/18/07. 4 RFI 73 Sun Screen Attachment Rev (COR#04) Modify top attachment for sun screen hangers. Rule Stl quote 1/22/08 5 RFI 74 Angle Clips @Slab Edge (COR#05) Add angle clips for additional support at studs to support wall that doesn't bear fully on slab. Rule Stl quote 1/22/08 & 11/13/07 6 RFI 93 Relief Angle @ Stair Twrs (COR#06) Fumish relief angle at stair towers. Rule Stl quote 2/26/08 7 RFI 94 Chiller Support Beams (COR#07) Fumish and install 2 beams on the chiller support stub columns to support the chiller unit Rule Stl quote 2/26/08 8 Time Extension for ASI 8~ RFI's issued to date Number of days to be determined 18,883.00 3,284.00 1,351.00 2,894.00 9,094.00 2,939.00 5,274.00 ~8.~9" 43,719.00 04/06/08 Comments/Remarks Page 1 of 1