HomeMy WebLinkAboutChange Order No. 5 with Hobson Fabricating for Phase 3 Tenant Improvements New City HallC`~ 1 -~ ot~ - C1 `I
~~ ~'Q~
CITY OF MERIDIAN
33 EAST IDAHO
MERIDIAN, ID 83642
CONTRACT CHANGE ORDER
CHANGE ORDER NO. 05
PROJECT NO. CH-06-001
DATE: 1 /20/09
EFFECTIVE DATE:
CONTRACTOR: HOBSON FABRICATING
PROJECT: MERIDIAN CITY HALL -Phase 3 Tenant Improvements
The Contractor is hereby directed to make the following changes from the Contract Documents and Plans.
Description: Incorporate revisions for Misc. ASI's & backcharge
ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.
Reason for Change Order: Additional scope or revisions per listed ASI's and RFI's
Attachments: Change order items description, dated 1/20/09, with contractor quotes
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price $2,060,000.00 Original Contract Times: Substantial Completion 8/28/08
Net changes orm previous Change Orders Net changes form previous Change Orders
No. 01 to 0
No._ to _ (calendar days)
$95, 921.0 None
Contract Price Prior to this Change Order: Contract Times prior to this Change Order:
(calendar days or date)
$2,155,921.00 8/2e/2oos
Net Increase (decease) of this Change Order: Net Increase (decrease) of this Change Order:
(plendar days or date)
$2,725.00 None
Contract Price with all Approved Change Orders: Contract Times with all Approved Change Orders:
(calendar days)
$2,158,646.00 Substantial Completion 8/28/2008
RECOMMENDED: (CONSTRUCTION MANAGER) ACCEPTED: (CONTRACTOR)
Petra Inc. _ _ ~- Hobson Fabricating'~'~ ~ ~~
By: Thomas R. Cough in ~
By: Ted Frisbee, Jr.
Date: Date: ~ ~ ~
APPROVED: (CITY PURCHASING AGENT) COUNCI APP OVAL
By: Keith Watts
Date: Date:
APPROVED: (CITY) - ATTEST:
By: Mayor Tammy de Weerd By: City Clerk, Jaycee Holman
Date: Date:
TITLE: ASI 166 & 166R
PROJECT: Meridian City Hall
TO: Attn: Ted Frisbee, Jr.
Hobson Fabricating Corp.
6428 Business Way
Boise, ID 83716
Phone: 343-5423 Fax: 343-5446
RE: To:
DESCRIPTION OF CHANGE
DATE: 1/20/2009
7OB: 060675
CONTRACT NO:
33
From: Number:
It~irrit ;Description
00001 ASI 166 & 166R -Glycol & Feed Pump Connection for Hydronic Heating Loop
(COR # 47 & 48) Provide 30% glycol solution in the hydronic healing loop and
connect the heating hydronic system to glycol feed pump. Connect e:asting
glycol low fluid alarm contact to DDC system alarm. Hobson quote 1/16/09 &
e-mail 1/19/09. Design Lssue.
00002 Backcharge for painting work by others. Prep and paint access door added after
initial painting work was completed. Commerdal Painting invoice #290262
dated 9/08. Construction Issue.
Tax Tax Met,
Quantity Units unit Price Rate Amount Amount
1.000 LS $2,760.00 0.00% $0.00 $2,760.00
1.000 LS ($35.00) 0.00% $0.00 ($35.00)
Unit Cost: $2,725.00
Unit Tax: $0.00
Lump Sum: $0.00
Lump Tax: $0.00
0.0% GC markup: $0.00
Total: $2,725.00
The Original Contract Sum was ................................................................................................. $2,060,000.00
Net Change by Previously Authorized Requests and Changes ................................................ $95,921.00
The Contract Sum Prior to This Change Order was ...................................................... $2,155,921.00
The Contract Sum Will be Increased ................................................................................... $2,725.00
The New Contract Sum Including This Change Order ...................................................... $2,158,646.00
The Contract Time Will Not Be Changed .................................................................................
The Date of Substantial Completion as of this Change Order Therefore is ..............................
ACCEPTED:
Hobso~ri ti C Petra I porated LCA Arc itects, P
~~ ~
By; ~~ ~ ~~.~/ Vim' By; By; ~ q
~ .nn
T d Frisbe Jr. om Coughlin Steve Christensen
Date: ~ ~ Date: Date: ' 1 ~-~ ~ C
Expediflon ® ~i
1097 N. ROSARIO STREET • MERIDIAN, ID 83642 • PHONE: (208) 323-4500 • FAX: (208) 323-4507
MERIDIAN CITY HALL
PROJECT NO: CH-06-001
HOBSON FABRICATING -Phase 3 (33)
CHANGE ORDER NO 5
01 /20/09
CHANGE ORDER ITEMS
1 ASI 166 & 166R Glycol & Feed Pump Connection for Hydronic Heating 2,760.00
Loop (COR#47 i~ 48)
Provide 30% glycol solution in the hydronic heating loop
and connect the heating hydronic system to glycol
feed pump. Connect existing glycol low fluid alarm
contact to DDC system alarm.
Hobson quote 1/16/09 & email 1/19/08.
2 Backcharge for painting work by others. (35.00}
Prep and paint access door added after initial
painting work was completed. Commercial
Painting invoice #290262, dated 9/08
2,725.00
Page 1 of 1