CITY OF MERIDIAN
33 EAST IDAHO
MERIDIAN, ID 83642
BUDGETED CONTRACT AMENDMENT
BUDGETED CONTRACT AMENDMENT
N0.03
PROJECT NO. CH-06-001
DATE: 11117/08
EFFECTIVE DATE:
CONTRACTOR: AXELSEN CONCRETE
PROJECT: MERIDIAN CITY HALL -Phase 4 Plaza & Site Improvement
The Contractor is hereby directed to make the following changes from the Contract Documents and Plans.
Description: Incorporate revisions per ASI's 125,137, 158 8 Misc. Changes
ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.
Reason for Budgeted Contract Amendment: Addt'I scope or revisions per listed ASI's 8 Misc. Changes
Attachments: Change Items d c tl ed 11M2/08 with contract r quotes
CHAN E IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price $296,200.00 Original Contract Times: Substantial Completion 8128/08
Net changes form previous Budgeted Contract Amerximent: Net changes form previous Budgeted Contracd Amendment:
No. 00 to 02 No._ to _ (calendar days)
$21,195.Q0 None
Contract Price Prior to this Budgeted Contract Amendment: Contract Times prior to this Budgeted Contract Amendment:
(calendar days or date)
$317,395.00 a/zarzooa
Net Increase (tle®Raase) of this Budgeted Contract Amendment: Net Increase (decrease) of this Budgeted Contract Amendment:
(calendar days or date)
$3,127.00 None
Contract Price with ell Approved Budgeted Contract Contract Times with all Approved Budgeted Contract
Amendment: Amendment:
(calendar days)
$320,522.00 Sul~tantial Completion 8/28/2008
RECOMMENDED: (CONSTRUCTION R) ACGEPTED: (CONTRACTOR)
Petra Inc. `' ~g Axelsen Concrete Construction
By: Thomas R. C gh~n By: Paul Axelsen
Date: „i Da
// / `Y OZ°1
APPROVED: (CITY P C I AGEN COUNC ROVAL
By: Keith Watts / ~~1a, ti-rttu urrrrr~~,'
~ - ~
Date: .. ~C/'O /
Date:
~.~°~ ~ ~'9 '~~'~,
? 'y
., c
-.
APPROVED: (CITY - ATTEST: ~
~
r
By: Mayor ammy de e d T~ p
~~'
By: City Clerk, JaC yc~e Hojtnan S1'~LSL
Dat@: 3 -~1- Date: 3 -tD - ' ~
~~~''~ ~t1NT`~ ~~P`~`~.
~~~~'I/rrrt r r r tt rtttN~~```
]OB: 060675
1097 N. ROSARIO STREET • MERIDIAN, ID 83fr42 • PHONE: (208) 323-4500 • FAX• (208) 323-4507 ~~"`"
PRO]ECT: Meridian City Hall
TO: Attn: Paul Axelsen
Axelsen Concrete Construction, LLC
4640 Hemlock Way
Nampa, ID 83687
Phone: 208-466-5620 Fax: 208-466-7895
RE:
To:
DESCRIPTION OF CHANGE
**All taxes are included in costs**
CONTRACT NO:
CHANGE ORDER
48
From:
Item Description
-~a 00001 ASI#125 Plaza Clock Relocation (COR#03)- Form & pour dock footing and
pedestal. Axelsen DFA dated 9/25/08
00002 ASI#137 Curb & Sidewalk Elevations- Broadway & Meridian RD. Grout two light
pale base, grades rake after pole bases poured. Axelsen DFA dated 10/16/08
,,.~. 00003 ASI#156 Water Feature Adjustments (COR#08)- Adjust weir openings per
Landscape Architect comments to Improve flow. Axelsen DFA dated
10/14-10/16/08
.:-~ 00004 Place three flagpole base f~tings. i3ases not induded in scope. Axelsen DFA
dated 10/2/08
00005 Additional sacking on building foundation walls due to grade being lowered at
city request Axel~n DFA
00006 Sack light pole bases, 28 large bases and 12 small bases, B/C Tri-State. Axel~n
DFA
00007 Replace sidewalk at SE comer of the building. Replace section damaged by
larxlsgper during construction. Axelsen DFA dated 10/17/08
00008 Replace section of plaza paving at North end of the canal due to Tight pole base
being out of plumb due to damage by eartliwork contactor. Axelsen DFA dated
10/1/08
Number:
Tax Tax Net
Quantify Uniffi Unit Price Rate Amount Amount
1.000 LS $218.00 0.00% $0.00 $218.00
1.000 LS $90.00 0.00% $0.00 $90.00
1.000 LS $766.00 O.QO% $0.00 $766.00
1.000 LS $750.00 0.00% $0.00 $750.00
1.000 LS $220.00 0.00% $0.00 $220.00
1.000 LS $400.00 0.00% $0.00 $400.00
1.000 LS $375.00 0.00% $0.00 $375.Q0
1.000 LS $308.00 0.00% $0.00 $308.00
Unit Cost: $3,127.00
Unit Tax: $0.00
Lump Sum: $0.00
Lump Tax: $0.00
0.0% GC markup: $0 00
Total: $3,127.00
The Original Contract Sum was .............................................................................................. $296,200.00
Net Change by Previously Authorized Requests and Changes ................................................ $21,195.00
The Contract Sum Prior to This Change Order was ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, $317,395.00
The Contract Sum Will be Increased ................................................................................... $3,127.00
The New Contract Sum including This Change Order ...................................................... $320,522.00
The Contract Time Will Not Be Changed .......................................................,.p........................
The Date of Substantial Completion as of this Change Order ThereLSre is ..l,A ........................
ACCEPTED:
Axelsen Concrete Co str ion, LLC Petra Incorporate LCA Ar ~tects,
Paul Axelsen T Co lin Stev / Christensen
Date: 6l~/~"Q ~" Date: ~ l ~ ~g Date: (~ l L ~ L o
TITLE: ASI & Misc Changes- Phase IV DATE: 11/12/2008
MERIDIAN CITY HALL
PROJECT NO: CH-06-001
AXELSEN CONCRETE (48} -Phase IV Plaza 11/12/08
CHANGE ORDER NO 3
CHANGE ORDER ITEMS
1 ASI 125 Plaza Clock Relocation (COR#03) $ 218
Form & pour clock footing and pedestal
Axelsen DFA dated 9/25/08
2 ASI 137 Curb & Sidewalk Elevations -Broadway & Meridian RD $ 90
Grout two light pole base, grades raise after pole bases
poured. Axelsen DFA dated 10/16/08
3 ASI 156 Water Feature Adjustments (COR#08) $ 766
Adjust weir openings per Landscape Architect comments
to improve flow. Axelsen DFA dated 10/1410/16/08
4 Place three flagpole base footings, Bases not included in scope $ 750
Axelsen DFA dated 10/2/08
5 Additional sacking on building foundation walls due to grade $ 220
being lowered at city request. Axelsen DFA
6 Sack light pole bases, 28 large bases and 12 small bases, $ 400
B/C Tri-state. Axelsen DFA
7 Replace sidewalk at SE comer of the building. Replace $ 375
section damaged by by landscaper during construction
Axetsen DFA dated 10/17/08
8 Replace section of plaza paving at North end of the canal $ 308
due to light pole base being out of plumb due to damage by
earthwork contractor. Axelsen DFA dated 10/1/08
$ 3,127
Page 1 of 1