HomeMy WebLinkAboutChange Order No. 11 with Owyhee Construction for Utilities Broadway Avenue Meridian to 5thCITY OF MERIDIAN 33 EAST IDAHO MERIDIAN, ID 83642 CONTRACT CHANGE ORDER Change Order No.: 11 Project Number: 601 Date: 10/15/2007 Effective Date: 10/15/2007 CONTRACTOR: Owyhee Construction, Inc. PROJECT: Broadway Avenue, Meridian Road to Fifth Street Utility Replacement Project The Contractor Is hereby directed to make the following changes from the Contract Documents and Plans. Desciptlon: 1) Additional Type "P" permanent asphalt repair 2) 3) 4) 5) Reason for Change Order: ACHD requires full width patches on roadway. Attachements: October 3, 2007 Change Order signed by the Contractor CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price: $817,576.50 Original Contract Completion Date: Original Contract Completion Days: Net changes form previous C.O.'s.: ~ Net Days change form previous C.O.'s: No. 0 to 0 ~ Np.~ 0 to 0 ,l~~ Contract Price Prior to this C.O.: ~°~,/ ~/ s~~ ~, Co~ct Completion Date before this C.O.: ntract Completion Days before this C.O.: Net Increase (decrease) of this C.O.: Net Days Increase (decrease) of this C.O.: $106,725.00 Contract Price with all Approved ~eO 's: T ~ ~~ ~®1. ~'~ Co~tract Completion Date with all Approved C.O: s: ~ Contract Completion Days with all Approved C.O.'s: RECOMMENDED: (CONSTRUCTION MANAGER) ACCEPTED: (CONTRACTOR) See Attached Change Order signed by the Contractor By: By: Date: ~d Z ~ 0 -7 Date: APPROVED: (CITY PURCHASING AGENT) COUNCIL APPROVAL By: Keith Watts ~~ .~~~ ,~~(~ ~i,. Date: Date: ~ ~' ~ ~ `o, ~ ~ ~". APPRO TY) - ~ ~ TTEST: ~_ ' ~ ~~ t By. ayor Tam de eerd D t ~ By: City C erk, Will Berg Jr. y a J e: 17 ~ ~ _ v Date: ~ ~o ~ ,9 ~ 0 29 ~ . 4 '~ ~----° ~~. .~ 'e''~//~~~~~~tl-~1 ir~e~ti~~~~~~~``~~ 10/03!2007 16:01 2083760324 OWVHEE CONSTRUCTION PAGE 02/02 CHANGE ORDER NUIVIBER: 1 I PRQ7ECT; BROADWAY AVENUE 1~IERIDIAN, iD CONTR.A.CTOR'S PROTECT NO: 074003 CONTRACT DATE: January 24, 2007 CONTRACT FOR: Water & Sewer The Contract is changed as follows: Additional Type "P" pErmanet~t asphalt repair T4TA)C, The original Contract Sum was .................................................................................... $1317,576,50 Net change by prcviousiy authorized Change Orders .................................................. $ 13,258.9 ] The Contract Sum prior to this Change Order was ............................--•......,.........,.... $830,835.4] Th¢ Contract Sum wilt be (increased) {~eerea9e~1) {-~-~sled) by this Change Order in the amount of ................................... $106,725.00 T'he new Contract Sum including this Change Order will be ....................................... $937,560.41 N1~T13: This summary does not reflect changes in the Contract Sum, Contract Time or Gu&rantccd Ivtaximum Ptico which have been authorized by Coristructitm GhRrtgc Directive cH~~r~E ors©~~ DATE: October 3, 2007 TO CONTRACTOR: OWY.~IE$ CONSTRUCTION, INC. 6434 W GOWEN ROAD BOISE, IDAHO 83709 2,546 SY 37.50 106,725.00 >IiD6,725.00 _Ky_le Radek, Sta,~' Etagineer ENC*1NE.ER (if required) BY DATE ~®~3r~ Ovwhee Construction. Inc. CONTRACTOR ' .~ --_ ~. BY ~, _ City of IVleridian O1~VNER BY "ice bA'fE