HomeMy WebLinkAboutChange Order No. 2 with Brown Construction, Inc. for Black Cat Trunk Sewer Phase 4 (2)CHANGE ORDER 2
PROJECT: North Black Cat Trunk Sewer
DATE OF ISSUANCE: 1/24/08 EFFECTIVE DATE:
OWNER: Primeland Development Co. LLP
CONTRACTOR: Brown Construction, Inc. ENGINEER: JUB Engineers
Page 1 of 3
You are directed to make the following changes in the Contract Documents.
Attachments:
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times
$ 1,717,487.31 Substantial Completion: 168 Davs - Mav 1, 2008
Ready for Final Payment: 213 Davs -June 15, 2008
days or dates
Net Changes from previous Change Orders No. 1 to No. Net Changes from previous Change Orders No. 1 to No. 1
$ (23
198.00) o
, Days
Contract Price prior to this Change Order Contract Times prior to this Change order
Substantial Completion: 168 Davs -Mav 1.2008
$ 1,694,289.31 Ready for Final Payment: _ 213 Days -June 15.2008
days or dates
Net Increase (decrease of this Change Order) Net Increase (decrease of this Change Order)
$ 400
00 o.s
. says
Contract Price with all approved Change Orders Contract Times with all approved Change Orders
Substantial Completion: Days -168.5
$ 1,694,689.31 Ready for final payment: Days -213.5
days or dates
RECOMMENDED BY OWNER:
B.
Date: ~'~ /Q~I
APPROVED BY OWNER:
Date: __Z I19~ob'
ACCEPTED BY C AC OR:
By:
Date: ~ ^ ~ / ~ ~ "
~~z
~~~
Tam~rtiy d eerd, Mayor
i~ G (~
Date: ~ ~ f/ % ' D d"
Approved by City Council: Z~
\\\`\\\\\~,~t~,~ll 11 nllrrlJ~~``a~P,,',
~~
~ r~~ ,'
Attest: _
~, Cit r~L _
~a.~CQrE Nd~wta~n
1
Date: r 1~ • ~~
~ ®~.
~ `q`a
~'/,`~IIIIIf PI 11 tIV1141,`0
W
.+~
North Black Cat Sewer Proiect Change Order #2
Brown Construction was required to remove concrete from the connection point at
manhole # lA in order to make their connection to this manhole. This required 2 men for
4 hours each utilizing hammers and pry bars.
No one seemed to know why this connection point was sealed off.
The labor rate for this work is $50.00 per hour as is identified in the attached rate sheet as
provided by Brown Construction.
Glenn Fitch
Project Manager
Primeland Development Co. LLP
Y
t
.'(~ f ~ 3rf,' -fig ~ `~ °-~ 'z'-
mfa y~ 77 ~ F _ e•..
'::.r
EQUII'MENT RENTAL PRICE LYS~':
325 EXCAVATOR 140.00
320 EXCAVATOR 125 ~
330 EXCAVATOR 155.00
350 EXCAVATOR 175 00
410 BACKHOE 70 ~
- 936 LOADER 85.00
938G WHEEL LOADER 95.04
~~ 95.00
SWEEPER 55.00
LABOR/MAN 50.00
FOREIVIA~1 W/TRUCK 70.00
DUMP TRUCK 70.00
END DUMP ~.~
345 EXCAVATOR 175.00
950 LOADER 105.00
966 LOADER 115.00
375 EXCAVATOR 190.00
MOXIE TRUCK 140A0
WATER TRUCK 95.00
R®'~D GRADER 110.E
330 EX. W/FL~IMIVJER 390.00
~~~ ~~ '0~~~12'/
~ ~~~ ~y