HomeMy WebLinkAboutBudgeted Contract Amendment No. 3 with Alpha Masonry for Phase 4 Plaza and Site Improvement New City HallVt71Il.V~ 1 {ti/ v ~ CITY OF MERIDIAN 33 EAST IDAHO MERIDIAN, ID 83642 BUDGETED CONTRACT AMENDMENT BUDGETED CONTRACT AMENDMENT N0.03 PROJECT NO. CH-06-001 DATE: 12@9!08 EFFECTIVE DATE: CONTRACTOR: ALPHA MASONRY PROJECT: MERIDIAN CITY HALL -Phase 4 Plaza & Site Improvement The Contractor is hereby directed to make the following changes from the Contract Documents and Plans. Descrlptfon: lncarporate revisions per ASI #164 ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME. Reason for Budgeted Contract Amendment: Additional scope or revlslons per listed ASI Attachments: Change Items descrlptlon, dated!!/10/08, with contractor quotes CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Or)glnaf Contract Price $194,585.00 Original Contract Timms: Substantial Completion 6/28108 Net changes form previous Budgeted Contract Amendmer~ Net changes form previous Budgeted Contrail Amendment: No. 00 to 01 No._ to _ (calendar days) $11,596.00 None Contrail Price Prior to this Budgeted Contrail Amendment: Contrail Times prior to this Budgeted Gontrail Amendment: {calerMar days or date) $206,181.00 6/2$/2006 Net Increase (derlaace} of this Budgeted Contract Amendment: Net Increa~ (decrease) of this Budgeted Contrail Amendment: {calendar days ar date) $520.00 None Contract Price with all Approved Budgeted Contrail Contract Times with all Approved Budgeted Contrail Amendment: Amendment: (calendar days) $206,701.00 Suf>~tantia! Completion 8/28/2008 RECOMMENDED: {CON3TRUCTIO 'ACCEPTED: (CONTRACTOR) Petra Inc. `' ~ ~?..--~ Alpha Masonry /J By: Thomas R. Coughlin ~~2 By: Daryl Coleman ,~j/ Date: ! Date: ~~ ~ APPROVED: (CITY PU C G~ COUNCIL APPROVAL / ~ urttirr~ ` By: Keith Watts Date: ,. 2 - o I Z ,`r'' 2 y ~ Dam: / ~~~ ~~+/ '~~~i ~ ~ . . . , APP ~gN~ Gt2l~~~ i/ A ST: By: Mayor Tammy de acrd By: City Clerk, Jaye Homan s~~ _ Date: - Date: ~.'a- ,``a .. .~~~ 9~ r is~ `;: ., y ~ ,