CITY OF MERIDIAN
~ EAST IDAHO
MERIDIAN, ID 83642
CONTRACT CHANGE ORDER
CHANGE ORDER NO. O1
PROJECT NO. CH-06-OO1
DATE: 12!26/08
EFFECTIVE DATE:
CONTRACTOR: AXELSEN CONCRETE CONSTRUCTION
PROJECT: MERIDIAN CITY HALL - Phase V East Parking Lot
The Contractor ~ her+etry directed ~ make the following changes from the CorKract Documents and Plans.
Description: Incorporate revisions for ASI 8136, ASI #165 and ASI #164 for Misc. Work Changes
ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.
R~son for Change Order: Additional scope of revisions per listed ASI #136, ASI #166 and ASI #164
Attachments: Change Order Items Deacriptlon, dated 12126/08, with contrador quote
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price $ 28,720.00 Original ContredTlmes: Substantial Completion 12/5/08
Net changes form previous Change Orders Net changes form previous Change Orders
No. 0 to 0 No._ to _ (calendar days)
$0.00 None
Contrail Price Prior to thts Change Order. Gontrad Times prior to this Change Order.
(calen~r days or date)
$28,720.00 12/5@oos
Net Increase {decrease) of the Change Order. Net Increase (decrease) of this Change Order.
(calendar days or date)
$6,880.00 None
Contract Price with all Approved Change Orders: Contract Times with all Approved Change Orders:
(cateridar days)
$35,600.00 Sutltstafttial Completion 12/5/2008
RECOMINENDED: (CONSTRUCTION MA ACCEPTED: (CONTRACTOR)
Petra Inc. - Axelsen Concrete Constructi
By: Thomas R. Coughlin By: Paul Axelsen~
Date: ~ ~ Date: !- !o - ~
APPROVED: (CnY PU • AO
~~~ COUNCIL APPROVAL
By: Keith Watts
Date: 1 .~ 22' d Date:
APPROVED: (cn~ - ATTEST:
By: Mayor Tammy de Weerd By: City Clerk, Jaycee Holman
Date: Date:
.1097 N. ROSARIO STREET • MERIDIAN, ID 83642 • PHONE: (208) 323-4500 • FAX: (208) 323-4507
TITLE: ASI & Misc. Changes - Phase V DATE: 12/31/2008
PROaECT: Meridian City Hall )OB: 060675
TO: Attn: Paul Axelsen CONTRACT NO: 54
Axelsen Concrete Construction, LLC
4640 Hemlock Way
Nampa, ID 83687
Phone: 208-466-5620 Fax:208-466-7895
RE: To: From: Number:
DESCRIPTION OF CHANGE
**All taxes are induded in casts**
Tax Tax Net
Ism l~criiption Qu®ntity Units Unit Pr~iit:e Rate Amount Amount
00001 ASI #136 -East Parking Lot Revised Drawings (COR #06). Incorporate ACRD 1.000 LS $2,755.00 0.00% $0.00 $2,755.00
comments & requests. Axelsen Quote 12/2/08
00002 ASI #155 - RalUoad Track Paver Walkway (COR #07). Form and pour concrete 1.000 LS $4,125.00 0.00% $0.00 $4,125.00
dab, approximately 642 SF with 1000 LF of 8" W x 4° airb. Axelsen Quote
10/15J08.
00003 ASI #164 -Irrigation Bmc & Manhole (COR #09). No work required. 1.000 LS $0.00 0.00% $0.00 $0.00
Unit Cost: $6,880.00
Unit Tax: $0.00
Lump Sum: $0.00
Lump Tax: $0.00
0.0% GC mariwp: 80.00
Total: $6,880.00
The Original Contract Sum was ................................................................................................. $28,720.00
Net Change by Previously Authorized Requests and Changes ................................................ $0.00
The Contract Sum Prior to This Change Order was ...................................................... $28,720.00
The Contract Sum Will be Increased ................................................................................... $6,880.00
The New Contract Sum including This Change Order ...................................................... $35,600.00
The Contract Time {Illill Not Be Changed ................................................. ............................
The Date of Substantial Completion a$ of this Change Order Thei~ore .............................
~v~~
MERIDIAN CITY HALL
PROJECT NO: CH-06-001
AXELSEN CONCRETE (54) - Phase V East Parking Lot 12/26/08
CHANGE ORDER NO 1
1 ASI 136 East Parking Lot Revised Drwgs (COR#O6} $ 2,755
Incorporate ACHD comments & requests
Axelsen quote 12/2/08
2 ASI 155 Railroad Track Paver Walkway {COR#07) $ 4,125
Form & pour concrete slab, approx 642 SF
with 1000 LF of 8"W x 4" curb
Axe{sen quote 10/15/08
3 ASI 164 Irrigation Box 8 Manhole (COR#09) $
No work required
6,880
Page 1 of 1