CONTRACT CHANGE ORDER
CHANGE ORDER NO. 01
PROJECT NO. CH-06-001
DATE: 12/28/07
EFFECTIVE DATE:
CONTRACTOR: BUSS MECHANICAL
PROJECT: MERIDIAN CITY HALL -Phase 3 Tenant Improvements $ MEP
The Contractor is hereby directed to make the following changes from the Contract Documents and Plans.
Description: Provide additional cast iron piping for sanitary sewer main to re-route it along west wall of the
basement to allow the sanitary sewer service to e~dt the building to thru the north wall to Broadway St in
lieu of west to Meridian Rd
ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.
Reason for Change Order: Sewer realigned per RFI-022 to avoid ACHD right-of-way in
Meridian RD
Attachments:
~~' CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
~rlglnal Contract PrICe $ 953,385.00 Original Contrail Times: Substantial Completion 8/28/08
Net changes form previous Change Orders Net changes form previous Change Orders
No._ to _ No._ to _ (calendar days)
$ - 0 _ None
Contract Price Prior to this Change Order. Contrail Times prior to this Change Order..
(calendar days or date)
$953,385.00 8/28noo8
Net Increase (decrease) of this Change Order. Net Increase (decrease) of this Change Order.
(calendar days or date)
$4,922.00 None
Contrail Price with alt Approved Change Orders: Contract Times with all Approved Change Orders:
(calendar days)
$958,307.00 Substantial Completion 8/28/2008
RECOMMENDED: (CONSTRUCTIO GER
PETRA INC ~ ACCEPTED: (CONTRALTO
BUSS MECHANIC ~~,~~
By: Tom Coughlin /~
By: John Qu
Date: OJ~~t7 ~~' 7~ ~
Date: l`/~ 'U
APPROVE (C PURC~I~NT) COUNCIL APP VAL .
By: Ke Watts ~
~
Date: f _ ~~ _ b~ .
Date: _ -~ ~~`
'OVED: (CITY) - ATTEST: _ ~~
By: Mayor Tammy de Weerd
D
t By: City Clerk, V~iFB~t+g-a'fr: - ~ ~ g
Date: .~ a ~ctc 'fi'b l a^ .
a
e: L, _ r ~ p ,~ ~
asp
s~,
o®
~~
4
1097 N. ROSARIO STREET • MERIDIAN, ID 83642 • PHONE: (208) 323-4500 • FAX: (208 323-4507
TITLE: RFI 22 - Re-route Sanitary Sewer DATE: 11/20/2007
PR07ECT: Meridian City Hall )OB: 060675
TO: Attn: John Buss CONTRACT NO: 32
Buss Mechanical
PO BOX 190476
phys: 4471 S. Henry
Boise, ID 83719
Phone:208-562-0600 Fax:208-562-0555
RE: To: From: Number:
DFSCR~PaD~f ~7~`~H#N~E: - _ -
To save money in the overall contract, delete the need for a weekend Meridian Rd closure and road cut, per RFI # 22, the
Contractor was directed to re-route the waste main piping from exiting the building to the West and instead run inside the
basement along the West wall and exit to Broadway St through the tVorth basement wall. This requires additional cast piping
graded to the sewer main in Broadway St.
Unit Cost: $0.00
Unit Tax: $0.00
Lump Sum: $4,922.00
Lump Tax: $0.00
0.0% GC markup: $0.00
Toil: $4,922.00
The Original Contract Sum was ...... ......................................................................................... $953,385.00
Net Change by Previously Authorized Requests and Changes ................................................ $0.00
The Contract Sum Prior to This Change Order was ...................................................... $953,385.00
The Contract Sum Will be Increased ................................................................................... $4,922.00
The New Contract Sum Including This Change Order ...................................................... $958,307.00
7'~e Contract Time Will Not Be Changed .................................................................................
. Date of Substantial Completion as of this Change Order Therefore is ..............................
ACCEPT
Buss c ani 1 City of Meridian
By: By: By:
John Buss Keith Watts
Dat . //7 /~ 8-' Date: Date:
~cped;cion
Dec 19 O?"~03:~F7p Huss Mechanibal Services (20.81562-0555 p.9
,. "
Proposal Request
BUSS Mechanical Services lnc.
P.Q. Box 990476
Boiise, Idaho 837!9-0476
9912/2007
Petra Construction
aa: Adam
Re: CHANGE PROP03AL REQUEST
#1
JOB: Meridian Clay Hall
JOB ~ 07932 ~-~
suss # s
GCIJItRCH. CP#
DESCRIPTION
R-route san""Mary sewer as per RFI #22
"
Material i valved tittin s $ 2.612.95
E ui ent $ -
ables 2°/.of labor $ 27.30
Tools
Tax $ 156.78
InsNallation 32 hrs $ 1,365.12
Material mana emerrt $ -
Su rvision 0 hrs $ -
Pro" Mana ement 0.2 hrs $ 9.00
Subsistenc8 $ -
Cleanu $ -
Waman lAsbuitts $ -
Safe
total $ 4,171.15
PERMIT $ 145.99
TOTAL $ 4,317.14
SUBCONTRACTORS Insulation Tempca Sheetmetal Other
$
-
TOTAL $ 4,317.14
BOND
OVERHEAD & PROFIT
12°!0
TOTAL PRICE $
$
$ 86.34
518.06
4,821.54
TOTAL REQUEST $ 4,g~
EXCLUSIONS
Paint,concrete,plumbing with in the building to 5' outside
PROPOSAL BY John Buss
ROPOSAL GOOD FOR 30 DAYS