CONTRACT CHANGE ORDER
CHANGE ORDER NO. 01
PROJECT NO. CH-06-001
DATE: 12/28/07
EFFECTIVE DATE:
CONTRACTOR: SEAL CO.
PROJECT: MERIDIAN CITY HALL -Phase 2 Cold Core & Shell
The Contractor is hereby directed to make the following changes from the Contract Documents and Plans.
Description: Add the Phase 3 Bid Package No. 5 to the Contractors original contract. The scope of work will
pertomted in acxordance with all contractual conditions in place for Phase 2 and for all work detailed in Phase
3 per the associated contract documents for the caulking, sealing and waterproofing scope of work.
ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.
Reason for Change Order: Add scope for Phase 3 Tenant Improvements to existing contract
Attachments:
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Or1g1f1al Contract Price $ 67,182.00 Original Contract Times: Substantial Completion 8/28/08
Net changes form previous Change Orders Net changes form previous Change Orders
No._ to _ No._ to _ (calendar days)
$ - 0 - None
Contract Price Prior to this Change Order. Contract Times prior to this Change Order.
(calendar days or date)
$67,182.00 8~2$l2oos
Net Increase (decrease) of this Change Order: Net Increase (decrease) of this Change Order.
(calendar days or date)
$22,388.00 None
Contract Price with all Approved Change Orders: Contract Times with alt Approved Change Orders:
(calendar days)
$89,570.00 Substantial Completion 8/28/2008
RECOMMENDED: (CONSTRUCTION R) ACCEPTED: (CONTRACTOR)
PETRA INC
By: Tom Coughlin SEAL CO
By: Mike Devaney
Date: ~~~~8 a~ Date: ~, L~ O~
APPROVED: (C URCHASIN AGENT) COUNCIL APPR AL
°
e ~i
By: Keith ,~,, ~ ii s a a u a a P
Date: ~~ ~ .- ®~ ``
Date: l '~ ~ S '~ ~ ~ ~`~
APPROVED: (CITY) - ATTEST
By: Mayor Tammy de Weerd By: City Clerk,lMftl-13etg~
Date: ~,,. ! ~ v ~ Date: Jl4yt;,e~ ~S~rw.atn.? ~,
PPjdJ
/~~a.c
~~ ~A
~ g,~.Q
• ~ 8 ~ 5 ~ 4~
0
PP/lae~ n silt
CHANGE ORDER
No. 00001
323-4500
BOISE, IDAHO
RCE-1875
1097 N. ROSARIO STREET • MERIDIAN, ID 83642 • PHONE: (208) 323-4500 • FAX: (208) 323-4507
TITLE: Phase III Sealing & Caulking
PROJECT: Meridian City Hall
TO: Attn: Mike Devaney
Seal Co.
P.O. Box 887, Meridian 83680
223 W Broadway
Meridian, ID 83680-0887
Phone:208-887-3646 Fax:208-887-3882
RE: To: From:
DE5~R7~fiM;;~~ CkNG~' -
DATE: 11/28/2007
706: 060675
CONTRACT NO: 12
Number:
This change is to add the Phase III Bid Package No. 5 to the original contract with Seal Co. The scope of work will be
performed in accordance with all contractual conditions in place for Phase II and for all work detailed in Phase III per the
associated contract documents for the caulking, sealing and waterproofing scope of work.
Unit Cost: $0.00
Unit Tax: $0.00
Lump Sum: $22,388.00
Lump Tax: $0.00
0.0% GC markup: $0.00
Total: $22,388.00
The Original Contract Sum was ................................................................................................. $67,182.00
Net Change by Previously Authorized Requests and Changes ................................................ $0.00
The Contract Sum Prior to This Change Order was ...................................................... $67,182.00
The Contract Sum Will be Increased ................................................................................... $22,388.00
The New Contract Sum Including This Change Order ...................................................... $89,570.00
The Contract Time Will Not Be Changed .................................................................................
Date of Substantial Completion as of this Change Order Therefore is ..............................
ACCEPTED:
Seal Co. City of Meridian
By: By: isy:
Mike Devaney
Keith Watts
Date: Date: Date: