HomeMy WebLinkAboutChange Order No. 1 with Civil Survey Consultants, Inc. for Well 27 DesignCITY OF MERIDIAN
33 EAST IDAHO
MERIDIAN, ID 83642
CONTRACT CHANGE ORDER
Survey Consultants
27 Design
Change Order No.: 1
Project Number: 06700
Date: 1112012008
Effective Date:
Contractor is hereby directed to make the following changes from the Contract Documents and Plans.
1J Additional Design and Construction Staking.
2) Artesian flow well head Design.
3) SCADA programming.
4) NMID License Agreement Update.
5) Rate Adjustments for design fees and construction services.
6) Change in Subcontractor
Reason for Change Order:
Change in Scope of work.
/'\\\4V I II 11011 W .
Letter of Request from Civil Survey Consultants
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price: $26,500.00 Original Contract Completion Date:
Original Contract Completion Days:
Net changes from previous C.O.'s.: .Net Days change form previous C.O.'s:
No. 0 to 0 No. 0 to 0
$0.00
Contract Price Prior to this C.O.: Contract Completion Date before this C.O.:
Increase (decrease) of this C.O.:
Days Increase (decrease) of this C.O.:
Contract Price with all Approved C.O.'s: Contract Completion Date with all Approved C.O.'s:
$41,564.00
RECOMMENDED: (CONSTRUCT O MANAGER)' ACCEP NT CTOR)
~-~ A~ ~~~ ~~ ~~~ Pff
Dater Date. ~~ _ z~ O ~t
//- Z 5 - ZA~~
APPROVED: (CITY PU CH ING AG ) COUNCIL APPROVAL
By: Keith Watts '~ ~~~
Date: 1 ~ ~2~ 'd~ Date: ~~` (~' r •~
Tammy de We~fd
°b~J = SEAL
City Clerk, Jaycee Holman ' O~
~aNrr ,,
~--J~riirit net\~~`
Glenn K. Bennett, P.LS.
Pnesident
Timothy A. Burgess, P.E.
Vice President
Kyle Radek, PE
City of Meridian
33 East Broadway Avenue
Meridian, Idaho 83642
Civil Survey Consultants, Inc.
1400 E. Watertower St.
Suite 100
Meridian, Idaho 83642
Re: City of Meridian -Well No. 27
Dear Kyle:
(Z08)888~312
Fex 888-0323
November 5, 2008
Our Agreement for Professional Services for the Well 27 project was executed in November 2004.
Since then, the project has changed adding additional work effort not anticipated when the original scope
of services was prepared. I am requesting a supplement to the original agreement to cover this additional
work and adjust for the four year delay in completion of this project.
I have enclosed a~copy of the original executed agreement for your reference. I have also attached a
summary of all billings as of 11/4/08.. As of November 4, 2008 we have billed a total of 18,474 for
design fees. This number is $900 higher than shown on my November 4 billing due to the fact that I had
not included my March 5, 2006 billing in my budget summary. I will correct this during the next billing
cycle.
Work that I consider a change in scope is as follows:
1. The Cherry Lane Christian Church needed to install landscaping along the northerly edge of their
property in Apri12006. This required that the by-pass/flushing pipeline from the well lot to Ten
Mile Creek be constructed as a separate project. The separate project added design effort and
construction staking that was not originally included in the scope of services. I estimate the fees
for additional work associated with this change aze one half of Bills No. 2 and 3 and all of Bill
No. 4 for a total of $2,185.00.
2. When We1127 was actually constructed it was found to be a flowing artesian well. This required
that we prepaze a special separate detail for a well head capable of diverting the artesian flow
during development and test pumping. Since you still planned to postpone design and
construction of the pumping facilities, Ed Squires recommended that you have the ability to flush
the well to preserve water quality until the pumping facilities are installed. This required that we
prepare a separate set of design plans for improvements to handle the artesian flow until the
pumping facilities are constructed. I estimate the fees for additional work associated with this
change are all of Bill No. 6 and one half of Bills No. 9, 10 and all of Bills No. 11 and 12 for a
total of $5,036.50.
Radek
November 5; 2008
Page 2 of 3
3. When the original scope of services was prepared city policy was that the contractors install a
SCADA panel and antenna furnished by Meridian. All SCADA start-up and prograrrvning was
performed by Meridian once the well was completed and accepted. This policy has now changed
so that the equipment will be furnished by the contractor as part of the construction contract and
SCADA programming will be provided under the design services contract. DC Engineering's
fee proposal for the SCADA programming is $2,500.00.
4. You have requested the new pumping facilities include the ability to by-pass flows whenever the
well starts after remaining idle. This requirement was not included in the original project. The
License Agreement with the Nampa Meridian Irrigation District allowing for flows to be by-
passed to Ten Mile Creek was obtained prior to this new requirement and does not allow for this
type of discharge. A modification to the existing agreement will be required. Since Ten Mile
______ ____,_ Creek s_a drain rather_than a canalLanticipate_that_obtaining this.modification will be_possible,
but I have not approached NN1ID regarding this issue at this time. Assuming everything goes
smoothly, I estimate approximately 8 hours of Project Engineer time will be required to update
the license agreement, which will add approximately $760.00. This does not include any direct
expenses for charges by NMID's attorney, which I will pass through at cost.
5. Originally We1127 was to be constructed in 2005. Construction was delayed due to water quality
issues discovered when the test well was constructed, and due to changes in anticipated demands
in the area. Billings submitted to date have been made at the current hourly rate at the time of
billing. There are some original budgeted hours that are not currently billed, or included in
another supplement item, for which I am requesting an increase to adjust to current rates. I have
attached two spreadsheets to support this request, one for the design fees and one for the
construction services fees. The combined total for this item is $4282.50.
6. I originally planned to use Mulder Engineering for electrical design and Kartchner Engineering
for mechanical design. On my recent projects I have been using the services of DC Engineering
for both electrical and mechanical design. It is my understanding that DC Engineering is also
providing most of the SCADA programming for Meridian making them a good choice for this
project. I have enclosed a copy of their proposed scope of services and fee estimate. This
proposal includes $5,000 for electrical and mechanical design, which is $300.00 over the original
budget.
The following summarizes the fee adjustments requested above by item number:
Change No. 1 = $ 2,185.00
Change No. 2 = $ 5,036.50
Change No, 3 = $ 2,500.00
Change No. 4 = $ 760.00
Change No. 5 = $ 4,282.50
Change No. 6 = $ 300.00
Total Fee Increase = $15,064.00
Radek
November 5, 2U08
Page 3 of 3
I spoke to Ed Squires this morning regarding the well. He indicated that his proposal to restrict portions
of the well screens for water quality purposes should not affect the selection or design of the pumping
equipment. Ed is not finished with this design, but indicated he would have well capacity and drawdown
information to me by next week. For purposed of this supplement I have assumed we will have a
standard vertical turbine pump configured for the artesian well.
Please let me know if you need any additional information to support this request.
_/