HomeMy WebLinkAboutChange Order No. 1 with MR Miller for Phase 4 Plaza and Site Improvement New City HallCITY OF MERIDIAN
33 EAST IDAHO
MERIDIAN, ID 83642
CONTRACT CHANGE ORDER
CHANGE ORDER NO. 01
PROJECT NO. CH-06-001
DATE: 8/11 /08
EFFECTIVE DATE:
CONTRACTOR: MR Miller, Inc.
PROJECT: MERIDIAN CITY HALL -Phase 4 Plaza & Site Improvement
The Contractor is hereby directed to make the following changes from the Contract Documents and Plans.
Description: Incorporate revisions per ASI 88, RFI#110, 8 Drain Valves for Pools & Stream Feature
ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.
Reason for Change Order: Additional scope or revisions per Ilsted ASI, RFI, 8~ Drain Valves
Attachments: Change order items description, dated 7/23/08, with contractor quotes
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price $216,775.00 Original Contract Times: Substantial Completion 8/28/08
Net changes form previous Change Orders Net changes form previous Change Orders
No. 0 to 0 No._ to _ (calendar days)
$0.00 None
Contract Price Prior to this Change Order: Contract Times prior to this Change Order:
(calendar days or date)
$216,775.00 8/28/2008
Net Increase (deareas~) of this Change Order: Net Increase (decrease) of this Change Order:
(calendar days or date)
$23,015.00 None
Contract Price with all Approved Change Orders: Contract Times with all Approved Change Orders:
(calendar days)
$239,790.00 ubstantial Completion 8/28/2008
RECOMMENDED: (CONSTRUCTION ACCEPTED: (CONTRALTO
Petra Inc. p
'° MR Miller, Inc.
By: Thomas R. Coughlin ~ By: Michael R. Miller
Date: ~ ~ ~~ Date: ~ f ~~
APPROVED: (CITY PURCHASING AGENT) COUNCIL APPROVAL
By: Kefth Watts
Date: Date:
APPROVED: (CITY) - ATTEST:
By: Mayor Tammy de Weerd By: City Clerk, Jaycee Holman
Date: Date:
J
CHANGE ORDER
No. 00001
323-4500
BOISE, IDAHO
RCE-1875
C~AAT- COIVTRACT~RS
1097 N. ROSARIO STREET • MERIDIAN, ID 83642 • PHONE: (208) 323-4500 • FAX: (208) 323-4507
TITLE: ASI & RFI Pricing- Phase IV
PR07ECT: Meridian City Hall
TO: Attn: Michael R. Miller
MR Miller, Inc.
P.O. Box 5423
2661 Federal Way
Boise, ID 83705
Phone: 208-344-1387 Fax: 208-344-3329
RE:
To:
DESCRIPTION OF CHANGE
**All taxes are included in costs**
DATE: 7/23/2008
70B: 060675
CONTRACT NO:
49
From: Number:
Item Description
00001 ASI#88 Modification to Water Feature Equipment (COR#01)- Revise water
feature equipment and layout per ASI#88 & Bulletin #22 from Petra Inc., dated
4/30/08. MR Miller quote dated 5/19/08
00002 Drain Valves for Pools & Stream Feature (COR#02)- Add 6" gate valves to the
existing 6" drain lines. Valve box to be 30" CMP with grade rings and 24"
diameter cast iron flush mount lid in the pavers or sidewalk as directed by the
CM. MR Miller quote 7/9/08
00003 RFI#110 Retum Line Layout & Flow Rates
Tax Tax Net
Quantity Units Unit Price Rate Amount Amount
1.000 LS $16,910.00 0.00% $0.00 $16,910.00
1.000 LS $6,105.00 0.00% $0.00 $6,105.00
1.000 LS $0.00 0.00% $0.00 $0.00
~~~~C~~ nor
AUG 2 p008 IU
Unit Cost: $23,015.00
Unit Tax: $0.00
Lump Sum: $0.00
Lump Tax: $0.00
0.0% GC markup: _ $0.00
Total: $23,015.00
The Original Contract Sum was ................................................................................................. $216,775.00
Net Change by Previously Authorized Requests and Changes ................................................ $0.00
The Contract Sum Prior to This Change Order was ...................................................... $216,775.00
The Contract Sum Will be Increased ................................................................................... $23,015.00
The New Contract Sum Including This Change Order ,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, $239,790.00
The Contract Time Will Not Be Changed .................................................................................
The Date of Substantial Completion as of this Change Order Therefore is .,~ ...........................
ACCEPTED:
B R MiUe~
Petra Incorporated
sy:
1/CA Arctgitects, P
sy: ~~
'~ Michae~~ G .Tom Coughli>~ ~ Steve Christensen
Date: ~~cov8 ~ Date: 7,~g ~ Date: ~ ~~
~ U 7/2 ~
Expedition
MERIDIAN CITY HALL
PROJECT NO: CH-06-001
MR MILLER, INC -Phase 4
CHANGE ORDER NO 1
07/23/08
CHANGE ORDER ITEMS
1 ASI 88 Modification to Water Feature Equipment (COR#01) 16,910.00
Revise water feature equipment and layout
per ASI-88 & Bulletin #22 from Petra Inc,
dated 4/30/08. MR Miller quote dated 5/19/08
2 -- Drain Valves for Pools & Stream Feature (COR#2) 6,105.00
Add 6"gate valves to the existing 6" drain lines
Valve box to be 30" CMP with grade rings and
24" diameter cast iron flush mount lid in the
pavers or sidewalk as directed by the CM.
MR Miller quote 7/9/08
3 RFI 110 Retum Line Layout & Flow Rates
0.00
23,015.00
Page 1 of 1