HomeMy WebLinkAboutTask Order No. 2.5 with CH2M HILL for Plant Drain System DesignTASK ORDER N0.2.5
UNDER THE
MASTER AGREEMENT FOR PROFESSIONAL SERVICES
BETWEEN
CITY OF MERIDIAN AND CH2M HQ,L, INC.
This Task order is entered into by and between City of MERIDIAN (OWNER) and CH2M HILL, Inc.
(ENGINEER), according to the terms and conditions of the Master Agreement (AGREEMENT) for
Professional Services, dated January 1, 2~7.
See Attachments A and B for the Scope and Fee for Task 2.5
All other terms and conditions of the original agreement will remain in full force and effect.
IN ~VTINESS WHEREOF, the parties execute below:
For CH2M HILL,
dated.
For City of Meridian
dated this
By:
Mayor
ayccee Hoban City
Approved By City Council:
2008.
Title
2008.
,~•~
,,,,
.~
;.
~~awo~,trRo -.
.,
=_ SEAL
s .9 ,~~
-. ~ "~T 13'~ .
•, ~,
Task Order 2.5
Amendment 2
Attachment A
Plant Drain System Design
Project Understanding
During the 50% review of the Tertiary Filtration Design documents, it was noted that the
plant drain system does not operate efficiently and should be revised and included with the
filter drain system. 'This amendment authorizes CH2M HILL to revise the plant drain
system to operate more efficiently by adding a pumped system to allow complete and
positive drainage of all structures.
Scope of Work
CH2M HILL will perform the tasks for design of the Plant Drain Pump Station as outlined
below. IIectrical design will be subcontracted to DC Engineering. SCADA programming is
not part of this contract.
Task 1 Piant Drain Pump Station Design
1.1 Update Preliminary Design Report
'Ibis subtask has been deferred. We will notify 1DEQ by letter with our plan submittal that
the City will supply totes of aluminum sulfate until a permanent chemical feed strategy is
finalized.
1.2 Prepare Plans and Speclflc~ttons
Additional plans and specifications will be produced to include the Plant Drain Pump
Station. The following is the anticipated list of additional drawings:
• Plant Drain Pump Station Structural and Mechanical Plans and Details
• Plant Drain Pump Station Electrical Plan
• Plant Drain Pump Station P&IDs
Additional specifications will be required for the plant drain pumps.
1.3 Project Review M~tings
Four copies of 90% complete project documents will be provided for the owner's review and
comment. A project review meeting will be conducted for the 90% submittal. Owner's
Comments will be incorporated into the project documents.
1.4 Agency Approval
Once the 90% Owner comments are incorporated into the project documents, we will seal
the documents and submit for Agency approval.
1.5 Final Bid Documents
Agency comments will be incorporated into the final Bid documents and one set of
electronc files and 4 sets of 1 /2 -$ize printed documents will be delivered to the Owner.
Drawings will be prepared in Microstation and converted to AutoCad, and specifications in
MS Word.
Assumptions: City will provide comments on the 90% submittal documents
Design will be based on existing geotechnical information provided by the
City in the preliminary design
Deliverables:
Four sets of 90% complete sets.
Two sets of Agency submittal documents.
Four sets o#'fl size 100% complete hard copy documents and one set of electronic
foes.
Task 2-Pro)ect Management
Project management will consist of:
• Supervising project staff,
• holding consultant staff coordination meetings as required,
• documenting meeting decisions and action items,
• assigning activities to team members,
• monitor project progress, including work completed, work remaining, budget
expended, schedule, estimated cost of work remaining, and estimated cost at
completion,
• monitor project activities for potential changes, anticipate changes when poss~le, and
with Owner approval, modify project tasks, budgets, and approach,
• prepare and submit a monthly billing with backup documentation,
• perform project quality control reviews of all deliverables on this project.
Attachment 6
Compensation
Level of Effort
The task level of effort estimates are st~*n*n~ri~ed in the following table. CH2M HILL has
developed this level of effort estimate based on the work plan presented herein and
assumptions stated previously. The fees will be billed as time and material, and will not
exceed the total amount below without prior approval by the City.
Level of Effort
Task Description Total Task
1 Design $15,044
2 Project Management $1,500
Summary -All Tasks $16,544
Costs include a 5% mark-up on subcontractors. All costs will be billed as time and materials
basis not to exceed the value above. All work and billings shall be in accordance with the
Master Services Agreement dated January 1, 2007.
Schedule
Work shall be incorporated into the Tertiary Filters Resign project.