HomeMy WebLinkAboutJC Constructors, Inc. for WWTP Expansion ProjectCHANGE ORDER 6 PROJECT: City of Meridian -Wastewater Treatment Plant Expansion Project DATE OF ISSUANCE: May 2, 2008 OWNER: City of Meridian CONTRACTOR: JC Constructors, Inc. EFFECTIVE DATE: :May 2, 2008 ENGINEER: Carollo Engineers, P.C. Page 1 of 2 You are directed to make the following changes in the Contract Documents. • Blower Inlet Piping Modifications (WCD 33) • Increase RS 42" DIP pothole (WCD 39) • Relocate SPS Hatch Mechanism (WCD 43) • Digester No.l and 2 Chemical Feed System (WCD 46) • AB 2 handrail, ladder and grating modifications (WCD 48a) • Power for PE sampler at SPS (WCD 49) • City Trailer Power (WCD 50) • Replacement of gas cleaning valves (WCD 51) • Site paving adjustment (WCD 52) • Credit for remaining wood baffle allowance (WCD 53) • Redundant SPS level element (RFP 25) • AB No. 1 and 2 concrete and metal work rehabilitation (RFP 27) • AB No. 1 and 2 ML pipe blast and recoat (RFP 27a) • Addition blast and recoat of ML pipe (RFP 27c) Time Extension to include additional scope of work requested by the City. Attachments: JC Constructors Change Proposal Request - (WCD 33) -March 26, 2008 for $4,982.37 JC Constructors Change Proposal Request - (WCD 39) -March 28, 2008 for $5,042.67 JC Constructors Change Proposal Request - (WCD 43) -April 18, 2008 for $760.99 JC Constructors Change Proposal Request - (WCD 46) -April 18, 2008 for $3,885.23 JC Constructors Change Proposal Request - (WCD 48a) -March 7, 2008 for $4,412.99 JC Constructors Change Proposal Request - (WCD 49) -April 21, 2008 for $454.28 JC Constructors Change Proposal Request - (WCD 50) -January 2, 2008 for $2,535.72 JC Constructors Change Proposal Request - (WCD 51) -April 1, 2008 for $1,257.90 JC Constructors Change Proposal Request - (WCD 52) -January 28, 2008 for $8,787.42 JC Constructors Change Proposal Request - (WCD 53) -April 14, 2008 for $8,878.21 JC Constructors Change Proposal Request - (RFP 25) -March 27, 2008 for $4,022.59 JC Constructors Change Proposal Request - (RFP 27) -September 29, 2007 for $29,019.75 JC Constructors Change Proposal Request - (RFP 27a) -September 29, 2007 for $28,284.27 JC Constructors Change Proposal Request - (RFP 27c) -February 18, 2008 for $2,912.78 Page 2 of 2 CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price Original Contract Times Substantial Completion: 670 Davs - September 1, 2007 Ready for Final Payment: 730 Davs -November 1, 2007 p $ 8.367,SOO.OO daysordates Net Changes from previous Change Orders No. l to No. 5 Net Changes from previous Change Orders No. 0 to No. 5 $ 646,783.23 One Hundred Twenty (120) Days Contract Price prior to this Change Order Contract Times prior to this Change order Substantial Completion: 670 Davs - September I, 2007 ~ 9,014,283.23 Ready for Final Payment: 850 Davs -February 28, 2008 days or dates Net Increase (decrease of this Change Order) Net Increase (decrease of this Change Order) $ 87 48 75 Nintv three (931 , . days Contract Price with all approved Change Orders Contract Times with all approved Change Orders Substantial Completion: 670 Days - September 1, 2007 $ 9,1 ~ 1,763.98 Ready for final payment: 943 D_ys - Mav 3 I , 2008 days or dates RECOMMENDED BY ENGINEER: By: William enko, .E. Date: GS OZ ~ APPROVED BY OWNER: . ~~ Clint olsby, P.E., Public Works Date: Q'a /t~'~ ~ ACCEPTED BY CONTRACTOR: Contractor (Authorized Signature) Date: Date: Tammy de Weerd, Mayor Attest: Jay Cee Holman., City Clerk Date: CHANGE PROPOSAL REQUEST 1.PROJECT MERIDIAN WWTF 2.CONTRACTOR 3.PROJECT NO. ~4s Change Proposal # WCD #33 IMPROVEMENTS JC CONSTRUCTORS S.CONTRACT NO: 6.PROPOSAL DATE 26-Mar-08 DESCRIPTION OF CHANGE Add reducing fitting to coordinate with valve supplied by others. Supply a tight 90 due to height restrictions. ' COST SUMMARY A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Direct labor w/ labor fringes (Attach supporting detail estimates with man-hours and rates) $ 164.52 2. Insurance and Labor Taxes $ 40.26 3. Materials and Equipment. Detailed quantities attached. $ 3,105.00 4. Overhead & Fee @ 75% $ 496.47 $ - Time Extention Requested 0 working daV JC Constructors' Cost $ 3,806.24 B. For work to be performed by subcontractors, per proposals and detailed breakdowns 1. SUBCONTRACTOR NAME CATEGORY OF WORK AMOVNT Custom Electric Electrical Modifications 1050 z TOTAL SUBCONTRACTOR AMOUNT (INCLUDING SUB. OHBPi' $ 1 , OSO.OO 7 CONTRACTORS COMMISSION ON TOTAL SUBCONTRACTOR AMOUNT ~ 5 PERCENT: $ 52.50 CONTRACTORS BOND COST ~ 5.018!1000 $ 73.63 C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (A8+g5) $ 4,982.37 JC CONSTRUCTORS, INC. CONTRACTOR NAME Jim Cox PRINTED NAME ON PROPOSAL SIGNATURE 1 DA TE Page 1, JCC CHANGE PROPOSAL REQUEST 1.PROJECT MERIDIAN WWTF 2.CONTRACTOR JC CONSTRUCTORS 3.PROJECT NO. ~~ Change Proposal # WCD # 39 IMPROVEMENTS S.CONTRACT NO: 6.PROPOSAL DATE 26-Mar-08 DESCRIPTION OF CHANGE , Pothole at primary supply line to investigate for obstructions and future alignment. As requested JC performed this work on a T8~M basis. This pricing does not include removal of demo and overburden to the owners land west of the project. Maintenance of the stockpiled material is not anticipated with this pricing. COST SUMMARY A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Direct labor wl labor fringes (Attach supporting detail estimates with man-hours and rates) $ 1,872.37 2. Insurance and Labor Taxes $ 447.76 3. Materials and Equipment. Detailed quantities attached. $ 2,000.00 4. Overhead & Fee Q 15°k $ 648.02 $ - Time Extention Requested 0 wOrklllq day JC Constructors' Cost $ 4,968.15 B. For work to be performed by subcontractors, per proposals and detailed breakdowns i SUBCONTRACTOR NAME CATEGORY OF WORK AMOUNT 2 TOTAL SUBCONTRACTOR AMOUNT (INCLUDING SUB. OHBP): $ - J I CONTRACTORS COMMISSION ON TOTAL SUBCONTRACTOR AMOUNT ~ 5 PERCENT: $ - CONTRACTORS BOND COST ~ 5.078!1000 $ 74.52 C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (AS+BS) $ 5,042.67 JC CONSTRUCTORS, INC. CONTRACTOR NAME Jim Cox PRINTED NAME ON PROPOSAL SIGNATURElOATE Page 1, .fCC o ~- ~} CHANGE PROPOSAL REQUEST 1.PROJECT MERIDIAN WWTF 2.CONTRACTOR 3.PROJECT NO. 148 Change Proposal # WCD 043 IMPROVEMENTS JC CONSTRUCTORS 5.CONTRACT NO: 6.PROPOSAL DATE 18-Apr-07 DESCRIPTION OF CHANGE Revise the SPS hatch door hold open to the south side for safe operation. . COST SUMMARY A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Direct labor w/labor fringes (Attach supporting detail estimates with man-hours and rates) $ 336.90 2. Insurance and Labor Taxes $ 77.55 3. Materials and Equipment. Detailed quantities attached. $ 237.50 4. Overhead & Fee @ 15% $ 97.79 $ - Time Extention Requested 0 working day JC Constructors' Cost $ 749.74 B. For work to be performed by subcontractors, per proposals and detailed breakdowns t SUBCONTRACTOR NAME CATEGORY OF WORK AMOUNT 2 TOTAL SUBCONTRACTOR AMOUNT pNCLUDING SUB. OH&P): $ - 7 ' CONTRACTORS COMMISSION ON 70TAL SUBCONTRACTOR AMOUNT ~ 5 PERCENT-. $ - CONTRACTORS BOND COST @ 8.078/1000 $ 11.25 C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (AB+BS) $ 760.99 JC CONSTRUCTORS, INC. CONTRACTOR NAME Jim Cox PRINTED NAME ON PROPOSAL SIGNATURE: DATE Page 1, JCC ~,~ o,~ CHANGE PROPOSAL REQUEST 1.PROJECT MERIDIAN WWTF 2.CONTRACTOR JC CONSTRUCTORS 3.PROJECT NO. 1a8 Change Proposal # WCD 046 IMPROVEMENTS S.CONTRACT NO_ 6.PROPOSAL DATE 18-Apr-07 DESCRIPTION OF CHANGE . Install piping and pump for temporary Ferric injection system. COST SUMMARY A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Direct labor w/ labor fringes (Attach supporting detail estimates with man-hours and rates) $ 82.26 2. Insurance and Labor Taxes $ 20.13 3. Materials and Equipment. Detailed quantities attached. $ - 4. Overhead & Fee Q 15°~6 $ 15.36 $ - Time Extention Requested 0 working day JC Constructors' Cost $ 117.75 8. For work to be performed by subcontractors, per proposals and detailed breakdowns 1. SUBCONTRACTOR NAME CATEGORY OF WORK AMOUNT Capital Ci Plumbin Plumbin 3533.4 z TOTAL SUBCONTRACTOR AMOUNT (INCLUDING SUB. OHBP)- $ 3,533.40 3, CONTRACTORS COMMISSION ON TOTAL SUBCONTRACTOR AMOUNT Q 5 PERCENT: r $ ~ 76.67 CONTRACTORS BOND COST ~ 3.01817000 $ 57.42 C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (AS+BS) $ 3,885.23 JC CONSTRUCTORS, INC. CONTRACTOR NAME Jim Cox PRINTED NAME ON PROPOSAL SIGNATURE! DATE Page 1, JCC C~IANGE PROPOSAL REQUEST 1.PROJECT MERIDIAN WWTF 2.CONTRACTOR 3.PROJECT NO. 148 Change Proposal # ~ WCD 48a IMPROVEMENTS JC CONSTRUCTORS 5.CONTRACT NO: 6 PROPOSAL DATE 7-Mar-08 DESCRIPTION OF CHANGE Misc handrail, grating, and ladder modifications per the work change directive. COST SUMMARY A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Direct labor w! labor fringes (Attach supporting detail estimates with man-hours and rates) $ 1,978.70 2. Insurance and Labor Taxes $ 471.54 3. Materials and Equipment. Detailed quantities attached. $ 1,125.00 4. Overhead 8 Fee @ 15% $ 536.29 $ - Time Extention Requested 0 wOfking_daV JC Constructors' Cost $ 4,111.53 B. For work to be performed by subcontractors, per proposals and detailed breakdowns ~. SUBCONTRACTOR NAME CATEGORY OF WORK AMOUNT Boise sawcuttin Concrete cutting 225 z TOTAL SUBCONTRACTOR AMOUNT (INCLUDING SUB. OHBP)~ $ 225. ~O 7 CONTRACTORS COMMISSION ON TOTAL SUBCONTRACTOR AMOUNT @ 5 PERCENT: I $ 11.25 CONTRACTORS BOND COST @ 5.018/7000 $ 65.22 C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (A8+g5) $ 4,412.99 JC CONSTRUCTORS, INC. CONTRACTOR NAME Jim Cox PRINTED NAME ON PROPOSAL SIGNAT 'JRE /DATE Page 1, JCC CHANGE PROPOSAL REQUEST 1.PROJECT MERIDIAN WWTF 2.CONTRACTOR JC CONSTRUCTORS 3.PROJECT NO. 148 Change Proposal # WCD # 49 IMPROVEMENTS S.CONTRACT NO' 6.PROPOSAL DATE 21-Apr-08 DESCRIPTION OF CHANGE . Add power to the relocated sampler at the north side of the SPS COST SUMMARY A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Direct labor wl labor fringes (Attach supporting detail estimates with man-hours and rates) $ - 2. Insurance and Labor Taxes $ - 3. Materials and Equipment. Detailed quantities attached. $ - 4. Overhead & Fee @ 15% $ - $ - Time Extention Requested 0 working day JC Constructors' Cost $ - B. For work to be performed by subcontractors, per proposals and detailed breakdowns t. SUBCONTRACTOR NAME CATEGORY OF WORK AMOUNT Custom electric Electrical 426.25 2 TOTAL SUBCONTRACTOR AMOUNT (INCLUDING SUB. OHBP): $ 426.25 a CONTRAC70RS COMMISSION ON TOTAL SUBCONTRACTOR AMOUNT Q 5 PERCENT: $ 2 ~ . 3 CONTRACTORS BOND COST (83 5.018n000 $ 6.7 C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (A8+BS) $ 454.28 JC CONSTRUCTORS, INC. CONTRACTOR NAME Jim Cox PRINTED NAME ON PROPOSAL SIGNATURE i DAi 5 Page 1, JCC /. CHANGE PROPOSAL REQUEST 1.PROJECT MERIDIAN WWTF 2.CONTRACTOR 3.PROJECT NO. 148 Change Proposal # WCD 050 IMPROVEMENTS JC CONSTRUCTORS S.CONTRACT NO: 6.PROPOSAL DATE 2,Jan-08 DESCRIPTION OF CHANGE Add power for the Owners temp trailer after JC removed their temp power pole. COST SUMMARY A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Direct labor wJ labor fringes (Attach supporting detail estimates with man-hours and rates) $ 158.30 2. Insurance and Labor Taxes $ 37.72 3. Materials and Equipment. Detailed quantities attached. $ 200.00 4. Overhead 8 Fee Q 1596 $ 59.40 $ - Time Extenton Requested 0 WOfkIrIQ daV JC Constructors' Cost $ 455.42 B. For work to be performed by subcontractors, per proposals and detailed breakdowns SUBCONTRACTOR~NAME CATEGORY OF WORK AMOUNT Custom Electric Electrical 1945.55 70TAL SUBCONTRACTOR AMOUNT pNCLUOING SUB. OH8P} $ 1,945.55 3 CONTRACTORS COMMISSKMI ON TOTAL SUBCONTRACTOR AMOUNT ~ 5 PERCENT: $ 97.28 coNTRACTORS eoNO cosy ~ s.oieriooo $ 37.47 C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (AB+B'~ $ 2,535.72 JC CONSTRUCTORS, INC. CONTRACTOR NAME Jim Cox PRfNTED NAME ON PROPOSAL SIGNATURE /DATE Page 1, JCG CHANGE PROPOSAL REQUEST 1.PROJECT MERIDIAN WWTF 2.CONTRACTOR JC CONSTRUCTORS 3.PROJECT N0. X48 Change Proposal # WCD # 51 IMPROVEMENTS S.CONTRACT NO: 6.PROPOSAL DATE ~~ / 1 Zo~~ DESCRIPTION OF CHANGE 3 of the existing HCL valves where leaking. Capital City Plumbing isolated the leaks, replaced three monel three way valves, and re-tested system. COST SUMMARY A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Direct labor w/ labor fringes (Attach supporting detail estimates with man-hours and rates) $ - 2. Insurance and Labor Taxes $ - 3. Materials and Equipment. Detailed quantities attached. $ - 4. Overhead 8 Fee @ 15% $ - $ - Time Extention Requested 0 WOrkinq dam/ JC Constructors' Cost $ - B. For work to be performed by subcontractors, per proposals and detailed breakdowns i SUBCONTRACTOR NAME CATEGORY OF WORK ~ AMOUNT Capital Cit Plumbing Plumbing 1180.3 z 7pTAL SUBCONTRACTOR AMOUNT (INCLUDING SUB. OHSP): $ 1 , 1 80.30 3 CONTRACTORS COMMISSION ON TOTAL SUBCONTRACTOR AMOUNT ~ 5 PERCENT. , $ 59.02 CONTRACTORS BOND COST @ 3.018/1000 $ 18.59 C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (A8+g~) $ 1,257.90 JC CONSTRUCTORS, INC. CONTRACTOR NAME Jim Cox P.R:NTeC NAME ON P.40POSAL S7GNArURE %CA 7c Page 1, JCC CHANGE PROPOSAL REQUEST 1.PROJECT 2.CONTRACTOR 3.PROJECT NO. Change Proposal # MERIDIAN WWTF JC CONSTRUCTORS ~a8 WCD 52 IMPROVEMENTS S.CONTRACT NO: 6.PROPOSAL DATE 28-Jan-08 DESCRIPTION OF CHANGE Final Asphalt rconciliation. Asphalt at the north of the plant was eliminated from JC contract due to coordination issues with the contractor at the north side of the site. JC is providing credit for this area. Additional costs are for; Overlay of drying bed Inflation cost of asphalt oil JC grade coordination, sawcut and removal of asphalt at admin building patch COST SUMMARY A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Direct labor wl labor fiinges (Attach supporting detail estimates with man-hours and rates) $ 2,544.92 2. Insurance and Labor Taxes $ 49$.17 3. Materials and Equipment. Detailed quantities attached. $ 550.00 4. Overhead & Fee @ 15% $ 538.96 $ - Time Extention Requested 0 working day JC Constructors' Cost $ 4,132.05 B. For work to be performed by subcontractors, per proposals and detailed breakdowns ~. SUBCONTRACTOR NAME CATEGORY OF WORK AMOUNT CAA As halt Credit for avin at north of plant $ (9,600.00) C8~A Asphalt As halt oil inflation $ 7,160.00 C8~A Asphalt D in bed overla $ 6,750.00 z TOTAL SUBCONTRACTOR AMOUNT (INCLUDING SUB. OHdP): $ 4,31 O.OO CONTRACTORS COMMISSION ON TOTAL SUBCONTRACTOR AMOUNT ~ 5 PERCENT $ 215, 5O CONTRACTORS BOND COST ~ $.078/1000 $ 129.86 C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (AS+BS) $ $7$7.42 JC CONSTRUCTORS, INC. CONTRACTOR NAME Jim Cox PRINTED NAME ON PROPOSAL S/GNATURE /DATE Page 1, JCC CHANGE PROPOSAL REQUEST ..PROJECT MERIDIAN WWTF 2.CONTRACTOR JC CO T 3.PROJECT NO 1as Change Proposal ~ WCD # 53 IMPROVEMENTS NSTRUC ORS 5.CONTRACT NO: 6.PROPOSAL DATE 14-Apr-08 DESCRIPTION OF CHANGE Contract deduct to credit the unspent portion of the wood allowance COST SUMMARY A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Direct labor w! labor fringes (Attach supporting detail estimates with man-hours and rates) $ - 2. Insurance and Labor Taxes $ - 3. Materials and Equipment. Detailed quantities attached. $ (8,747.00) 4. Ovefiead 8, Fee @ 15°k $ - $ - Time Extension Requested 0 working dax JC Constructors' Cost $ (8,747.00) For work to be performed by subcontractors, per proposals and detailed breakdowns 1. SUBCONTRACTOR NAME CATEGORY OF WORK AMOUNT 2 TOTAL SUBCONTRACTOR AMOUNT (INCLUDING SUB. OHBPj: $ - 3 CONTRACTORS COMMISSION ON TOTAL SUBCONTRACTOR AMOUNT ~ 5 PERCENT' $ - CONTRACTORS BOND COST (d 5.01811000 ~ $ (~ 3 ~ .21 ) C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (A8+65) $ (8 878 21) JC CONSTRUCTORS, INC. CONTRACTOR NAME Jim Cox PRINTED NAME ON PP.OPOSAL SIGNATURE: GATE Page 1, JCC CHANGE PROPOSAL REQUEST .PROJECT MERIDIAN WWTF 2.CONTRACTOR 3.PROJECT NO. ~`~ Change Proposal r RFP # 25 _.IMPROVEMENT`S JC CONSTRUCTORS S.CONTRACT NO: 6_PROPOSAL DATE- 28-Nov-07 DESCRIPTION OF CHANGE Add new level sensor at the SPS. COST SUMMARY a FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Direct labor w/ labor finges {Attach supporting detail estimates with man-hours and rates) $ 593.61 2. Insurance and Labor Taxes $ 141.46 3. Materials and Equipment. Detailed quantities attached. $ 910.00 4. Overhead 8 Fee @ 1596 $ 246.76 $ - Time Exteriflon Requested 0 working day Jc Constructors• cos: $ 1,891.83 -, For work to be perronmed by subcontractors, per proposals and detailed breakdowns SUBCONTRACTOR NAME ~ ~ CATEGORY OF WORK Custom electric ElectricaUControl 1972.68 2 TOTAL suecoNrnACroR AMOUNT Ia+ctuoiNC srJe- oNaPl- $ 1, 972.68 3 CONTRACTORS COMMISSKTN ON TOTAL~SUBCONTRACTOR AMOUNT @ 5 PERCENT' $ 98.63 coNTRACTORS BoNO cosT ~ ao~errooo $ 59.45 C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (A8+B5) $ 4,022.59 JC CONSTRUCTORS, INC. cavTRacTOnNM~ Jim Cox Page 1, JCC IC~iANGE PROPOSAL REQUEST 1.PROJECT MERIDIAN WWTF 2.CONTRACTOR JC CONSTRUCTORS 3.PROJECT NO. ~ 148 Change ProDOSaI ~ RFP # 27 IMPROVEMENTS 5_CONTRACT NO: 6.PROPOSAL DATE 29Se -07 DESCRIPTION OF CHANGE ' Final costs for the patching of holes and the verticai joint between the original AB structure and the 1997 addition. This proposal request combines the earlier estimates of RFP # 27 and RFP # 27b. COST SUMMARY A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Diced labor vA labor fringes (Attach supporting detai estimates with man-hours and rates) $ 13,455.19 2 Insurance and Labor Taxes $ 3,206.46 3. Materials and Equipment Detaied quantities attactled. $ 8,200.00 4. Overhead 8 Fee @ 15% $ 3,729.25 $ - 7ime Extention Requested 0 working day JC Constructors' Cost $ 28,590.89 B. For work to be performed by subcontredors, per proposals and detailed breakdowns 1. SUBCONTRACTOR NAME CATEGORY OF YMORK AMOUNT 2 TOTAL SUBCONTRACTOR AMOUNT (INCLUDING SUB. OMdP): $ - J CONTRACTORS COMMISSION ON TOTAL 3UBC.ONTRACTOR AMOUNT ~ 5 PERCENF: $ - coNrnACrorts eoNO cosy ~ s.o+aneoo $ 428.86 C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (AB+BS) $ 29,019.75 JC CONSTRUCTORS, INC. coMRSCroR nwMr= Jim Cox PRIMED NAME ON PROPOSAL SIGNATURE /DATE Page 1, JCC CHANGE PROPOSAL REQUEST 1.PROJECT MERIDIAN WWTF 2CONTRACTOR JC CONSTRUCTORS 3.PROJECT NO. ~a8 Change Proposal # RFP # 27a IMPROVEMENTS S.CONTRACT NO: 6.PROPOSAL DATE 29-Sep-07 DESCRIPTION OF CHANGE Blast and coat ML pipe, and remove old penetration cover plates in the AB 18L2. Misc metal coating includes sand blasting and 12 mil coating of two part epoxy. COST SUMMARY A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Direct labor w/ labor finges (Attach supporting detail estimates with man-hours and rates) $ 12,663.70 2. Insurance and labor Taxes $ 3,017.84 3. Materials and Equipment. Detailed quantities attached. $ 8,550.00 4. Overhead & Fee @ 15°k $ 3,634.73 $ - Time Extention Requested D working day JC Constructors' Cost $ 27,866.28 e. For work to be performed by subcontractors, per proposals and detailed breakdowns 1. SUBCONTRACTOR NAME CATEGORY OF WORK AMOUNT 2 TOTAL SUBCONTRACTOR AMOUNT (INCLUDING SUB_ OH3P1 ~ $ - J CONTRACTORS COMMISSION ON TOTAL SUBCONTRACTOR AMOUNT @ S PERCENT: $ - CONTRACTORS BONG COST (off 5.01&1000 $ 417.99 C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (AB+BS) $ 28 284 27 JC CONSTRUCTORS, INC. CONTRACTOR NAME Jim Cox PRINTED NAME ON PROPOSAL SIGNATURE /DA TE Page 1, JCC ~~ o,~~. CHANGE PROPOSAL. REQUEST 1.PROJEC7 MERIDIAN WWTF 18-Feb-08 JC CONST UC 3.PROJECT NO. 148 Change Proposal # RFP 27c IMPROVEMENTS R TORS S.CONTRACT NO: 6.PROPOSAL DATE 18-Feb-08 DESCRIPTION OF CHANGE , Repair existing leaking wall joint between AB's 182. Joint was prepared and caulked with a polyuria caulking and primer. Grind and patch previously repaired areas by others that where beginning to teak. COST SUMMARY A. FOR CHANGE WORK DIRECTLY PERFORMED BY THE UNDERSIGNED CONTRACTOR 1. Direct labor w/ labor fringes (Attach supporting detail estimates with man-hours and rates) $ 1,418.53 2. Insurance and Labor Taxes $ 326.51 3. Materials and Equipment. Detailed quantities attached. $ 750.38 4. Overhead & Fee @ 15% $ 374.31 $ - Time Extention Requested 0 working day JC Constructors' Cost $ 2,869.73 B. For work to be peAormed by subcontractors, per proposals and detailed breakdowns 1. SUBCONTRACTOR NAME CATEGORY OF WORK AMOUNT 2 TOTAL SUBCONTRACTOR AMOUNT (INCLUDING SUB. OH8PI: $ - ~ ~ CONTRACTORS COMMISSION ON TOTAL SUBCONTRACTOR AMOUNT 3~ 5 PERCENT. $ - CONTRACTORS BOND COS7 @ 5 018/1000 $ 43.05 C. TOTAL INCREASE OR DECREASE OF CONTRACT PRICE - (AB+BS) $ 2 912 78 JC CONSTRUCTORS, INC. CONTRACTOR NAME Jim Cox PRINTED NAME ON PP,OPOSAL SIGNATURE.'OATc Page ~ . JCC Fags 2 of 2 CHANtR~ W C~DavTPRACT PB[CE: C9ANCE IN CONTRACP TIMES: Origiosl Contract Friae Oagioal C~ttact Tina Subee~t Camplatioa: 0 Daps - S~6a 1.2007 Novan~bar 1.2U07 Rca~r fay Heal Pay~nmt T30 Davs - $ 8.3b7.500 QO ~ Nat C6aoges From p[eviona (:6emgeOriwae iJu 1 >b 1Vo.~ Nat t'[om pceriWS C~ageOidas No. ~ to No.~ $ 646.7$x.23 one l;o~a T~aty (lam) owe Contras Peioepaor m f>da ~ Oi+dar Contma7~ psiaato ~ ~ ~ Sa6e1 Canplatiaac B70 Davs - September 1.2007 ~ 9 alaz8~.z3 Readyt~a?anal Faymeot acso aa~ - Fa,~-z~ 20~ Net Increme (daaeaavof~av~ A~geOlde<) Nd Ia~se(deaaaaeoYtl>fs ( Ordd- $ 87.480.75 Nmwthree(931 ~+ Cemtr~t Prioe ~ all appiovad ~ l)edms (~ll$itd Z"tmE3 Wtt~i 8ll approved Change O[dtl3 Su»l Compldiam: f10 Dasrs - 3mtamber 1.2007 $ 9 I01.763.98 Ready fa~ 6ea1 payment 943 Davs - Mav 31. X08 agsar0eees RTCO~iDF~D BY ~1TGII~: ACCBPTF.D HY COIVTRACISOR: BY- ~~^ W ' J Benin , P.E I?atie: APPROVED 13Y OWNER: Clint IabT, F.B., Pabhe or)oa race: shz ~~8 Conttacta~ Date: 9 - 1\ • ~~ woad, l~r Ja}- con Date: - ~ p~ Dales _ ~wcd by trr7 ~;1: I~,j 13, ~p ,~~ ~' .•`