HomeMy WebLinkAboutChange Orders 6, 7, 8 with Brown Construction, Inc. for North Black Cat Trunk SewerRECEIV= "~ APR 1 '1 200' 'City' Cif Mexidia~, City Clerk 0f~a.c~ Memo To; Jaycee Holman; Tara Green From: Clint Dolsby, P.E., Acting City Engineer CC: Thomas Barry, Public Works Director Date: 04/17/2008 Re: Proposed Agenda Items for April 22, 2008 City Council Meeting The Public Works Department respectfully requests the following item be placed on the April 22 City Council agenda, under consent agenda, for Council's consideration: Change Orders No. 6 7 and 8 for the North Black Cat Trunk Sevuer. Additional work is required for the North Black Cat Trunk Sewer. This change order consists of the following work. This makes the total changes from Change Order No.1 through 8 equal to 3.28% of the original contract amount • Due to unforeseen conditions Brown Construction imported an additional 9,069 cubic yards in Mare. • Three additional manholes were added to the North Black Cat Trunk Sewer. • A time extension of 23 days was requested by Brown Construction far hauling in Import backfill material. Brown Construction, Inc, has submitted cost estimates for these change orders as summarized below: • Change Order Na. 6 $0.00 • Change Order No. 7 $24,721.00 • Change Order No. 8 $13,166.00 • Summary of Change Orders 6, 7 and 8 $37,887.00 Recommended Council Action: The Public Works bepartment recommends that City Council approves Change Orders No. 6, 7 and 8 for the North Black Cat Trunk Sewer with Brown Construction, Inc. for $37,887.00 and authorize the Mayor to sign them. Thank you for your consideration. Please contact me if you have any questions regarding any of these items. • Page 1 CHANGE ORDER 6 PROJECT: North Black Cat Trunk Sewer DATE OF ISSUANCE: 3/27/08 EFFECTIVE DATE: OWNER: Primeland Development Co. I1.P CONTRACTOR: Brown Construction, Inc. ENGINEER: JUB Engineers Page I of 2 You are directed to make the following changes in the Contract Documents. • Attachments: Explanation of additional costs. CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price Original Contract Times 1 717 487.31 Substantial Completion: 168 Davs - Mav 1, 2008 R d f i ea y or F nal Payment: 2) 3 Davs -June 15. 2008 days or datcx Net Changes from previous Change Orders No. I to No.~ Net Changes from previous Change Orders No. 1 to No. 5 $ 2U 334 UU 2.5 , . _ - pays Contract Price prior to this Change Order Contract Times prior to this Change order Substantial Completion: _1_68.5 1]ays - Mav 1.2008 1 73 821.31 Ready for Final Payment:. 21.5 Days -June 15.2008 days or dates Net Increase (decrease of this Change Order) Net Increase (decrease of this Change Order) ~ 23 day. Contract Price with all approved Change Orders Contract Times with all approved Change Orders Substantial Completion: Da - 197.5 Ma 24 2 O8 1 737 821.31 Ready for final payment: Days - 242.5 July 8.2008 days or dates RECOMMENDED BY OWNER: B: Date: 3 /0 APPROVED BY OWNER: Date: Date: ACCEPTED BY CONTRACTOR: By: Date_ ~ ~~ ~ ~' Tammy de Weerd, Mayor A[test: William G. Berg, Jr., City Clerk Date: Approved by City Council: Mar 24 08 12:ASp Todd M 2Q8 d66 dB81 p2 Brawn ~nnstruction, Inc. 6881 Bennett Road Mampa, ID 83686 Phone: {~08) 465-Q~74 Fax: (2q$y 465-3532 Prirneiar~ 1]evelvpment 3 x.20 W. l3elitower Drnre Suitt 1130 Meridian, ID $3646 Attn: Glenn Fltrh ADb117ONAL HAUL IN TlMEFQR 1ME~RTED M~,.~RI~{ • (Z~, 656 CY IMPORTED MATERIAL/ ~.$ CY pER TRIP = 7Q3 WALL TRIPS 703 HAUL TRIPS J 10 MQUIi WO#iKING L7AY = %p V~RKING DAY(S) ^ 70 WORKING DAY{5) f 31'RUCKS PAR DAY:- 23 pAY{5) QF HAIJL-IN ^ TOTAL TIME FOR HAUL-tIY OF IAAPORI'ED MAT6RIpL ~ ?3 OAY(5) Thank }/ou. Sincerelyf _~~ ',,5~ r ~f~~. r''~ ~ Richard Brown Brawn Construction, Inc. CHANGE ORDER 7 PR07ECT: North Black Cat Trunk Sewer DATE OF ISSUANCE: 3/28/08 OWNER: Primeland Development Co. I_I_P EFFECTIVE DATE: CONTRACTOR: Brown Construction, Inc. ENGINEER: IUB Engineers Page I of 2 You are directed to make the following changes in the Contract Documents. • Attachments: Explanation of additional costs. CHANGE liN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price Original Contract Times 1 717 487.31 Substantial Completion: 168 Davs - Mav I, 2008 _ ne 15 2008 f al P e t 213 Da s -J R d Fi n : u ea y or n aym days or dales Net Changes from previous Change Orders Nn. I to No. 6 Net Changes from previous Change Orders No. l to No. 5 20 34 00 2s. $ . 3 pays Contract Price prior to this Change Order Contract Times prior to this Change order Substantial Completion: 168.5 Davs - Mav 1.2008 1 737 821.31 Ready for Final Paymcnt: _ 213 a s -June 5 2 days or dattx Nct Increase (decrease of this Change Order) Net Increase (decrease of this Change Order) 21 00 3 . ,.,_ ,~ $ 24,7 - ._. ~y~ Contract Price with all approved Change Orders Contract Times with all approved Change Orders Substantial Completion: Davs - 200.E M~7,2008 1 762 542.31 Ready for final payment: Da - 245.5 Jul 1 120 dayz or date. RECOMMENDED BY OWNER: BC~ Date: /28/08 APPROVED BY OWNER: Date: ACCEPTED BY CON TOR: By: Date: ~~~. _~~ Tammy de Weerd, Mayor Date: Atlesl: William G. Berg, Jr., City Clerk Date: Approved by City Council: roKlfl o~rsfractco~ MG. PRIMELAND DEVF.L,O.PMENT 3120 W. BELLTOWERDR. SUITE I QO Mi~RIDIAN, IDAHO 8364b fi881 Benn®tt Rd. -Nampa, ID 83888 Ana (208) 465-0274 -~ Fax (208) 4655 I17VOIC@ PATE INVOICE NO. 3/27/2008 08-881 TERMS PROJECT 301 -1vORTH BLACK C'AT TRIO SEWER ITEM QTY DESCRIPTION RATE AMOUNT CHANGE ORDER FUR PAY REQUEST: 1 9,069 IMPORTEU'1'RENCH BACKFILL 2.D0 18,138.00 CALCULATION BREAKDOWN: LINEAR Fi?.ET OF SEWER TRENCH-I6I i LF AVERAGE DEPTH OF SEWER TRENCH~25.0 FT SUBTRACT 3 F-f =PIPE ZgNE (I'1PE AND BEDDING) SUBTRACT 3 FT = RQAD BA5E (PIT RUN SECTION, 3i4 Rn MIx, ASPHALT) TOTAL ~ 19 FT AVERAGE DEP"T"H OF 1MPQRTEU TRENCH BACKFILL (19.0 FT X 8 FT WIDE X 161 I LF1/27 - 9,069 CY C1iANG>; URUER MANHOLE: 1 1 MANHOLE 17A1 6,583.00 6,583.00 Total $24,721.00 ~•d eLZ=60 BD GZ ~eW CHANGE ORDER 8 PROJECT: North Black Cat Trunk Sewer DATE OF ISSUANCE: 4/2/08 EFFECTIVE DATE: OWNER: Primeland Development Co. LLP CONTRACTOR: Brown Construction, Inc. ENGINEER: JUB Engineers Page 1 of 3 You are directed to make the following changes in the Contract Documents. • Attachments: Work Change Directives # 2 and 3 CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price $ 1,717,487,31 _ Original Contract Times Substantial Completion: 168 Da s - Ma 12008 2008 t: 213 Davs -June 15 R d f Fi l Pa m , ea y or na y en _ - days qr dares Net Changes from previous Change Orders No. I to No. 6 Net Changes from previous Change Orders No. I tq No. 6 45 055 00 zz.s $ . pays Contract Price prior to this Change Order Contract Times prior to this Change order Substantial Completion: 168.5 Davs - Mav 1, 2008_ $ 1,752 542.31 Ready for Final Payment: _ 2135 Days -June 15.2008 days or dates Net Increase (decrease of this Change Order) Net Increase (decrease of this Change Order) 13166 00 6 $ . dayn Contract Price with all approved Change Orders Contract Times with all approved Change Orders Suhstantial Completion: Days - 206.5 May 3Q.20U8 $ 1.773,708.31 Ready For final payment: Davs - 251.5 July l6 2008 ' days or dare. RECOMMENDED BY OWNER: Date: 4/2/08 APPROVED BY OWNER: Date: ACCEPTED BY CO TOR: By: Date: 4/2/OR Date: Tammy de Weerd, Mayor Attest: William G. Berg, Jr., City Clerk Date: Approved by City Council: qTY OF MERiD1AN ORTH B1J1QC G4T TRUNK S~IVEli FDA (:C1UN7Y, IDAHO i woRS CxA1vGE nutEC~vE No. 002 DATE OF ISSUANCE 03/31/08 FFFECTTVI~ DATE _.03/3,[/08. O~~ r _ _ Cites of Meridian CONTRACTOR ~~, ,_ ,_ _ _. _ Srgwn C~gns lion Contract: Project: __ North Black Trunk ewer OWNER's Contract No. ENGINEER's Project No, .10-05-026 _ _ You are directed to proceed promptly with the following change(s): Description: A 60"Type "B" "Through" manhole shall he added at Station 136 + 13.1 I _ Critical elevations shall be as follows: Rim =2541.30, 21" IE In = 21" lE out = 251b.80, 8" lE in (E) ~ 2517.72, Northing = 724783.57, Fasting =2438892.69. 291inear feet of 8" sewer shall be installed east from the new 60" "Through" manhole at a 3.30 slope.. The 8" stub shall be at a 90 degree angle to the 21" sewer trunk. The end of the stub shall be capped and marked to the surface and shall be located as follows: Northing w 724783.29, Fasting = 243$923.37. Purpose of Work Change Directive: To accommodate sewer flows from the Bellhaven Subdivision: Attachments: (List documents supporting change) Lf OWNER or CONTRACTOR believe that the above change has affected Contract Price any Claim for a Change Order based thereon will "involve one or more of the following methods as defined in the Contract Documents. Method of deternnining change in Contract Price: ^ Unit Prices ^ Lump Sum ®~. ^ Cost of the Work Estimated increase (decrease) in Contract Price: Estimated increase (decrease) in Contract if the change involves an increase, the estimated Substantial Completion: -~ days; amount is not to be exceeded without further Ready for final payment: ~ days. authorization. RECOMMENDED: - AUTHORl7~D: ENGiNFF12 OWNER By: $y• gJCDC No. 1910-8-F (1996 gdition) Pleparad by the Gogiaeers Join Coutraet pacwtetax Cooaeirn+e anA eedattead by The ASeaeiaced general ConoaQOrs of Aa+erica and d,e Coion 5px'dicetions Insuttttc. Ct7Y OF MERIDIAN NORTH BLACK CAT' TRUNK SEWER ADA COUIYIY, IDAHO WURK CHANGE DIRECTIVE No. 003 ,_„ DATE OF ISSUANCE 03/3 /0 EFFECTIVE DATE 03/3.1/08 , O~ ~ _ ~ _ _ City o_f meridian CONTRACTOR ro C nsttuction Contract: Project: ._._, North Bak C~ Trunk Sewer OWNER's Contract No. ENGIIVEER's I7roject No. 10-05-026 You are directed to proceed promptly with the following change(s): Description: A SO" Type "B" "'Through" manhole shall be added at Station 149 + 96.72_ Critical elevations shall be as follows: Rim = 2S41.t54, 2l" IE In = 2l" IE out = 2518.67, 8" IE Block-Out In (W) = 2519.75, Northing = 726167.11, Fasting =2438906.89. Propose of Work Change Directive: To accommodate sewer flows from the Coleman Subdivision. Attachments: (List dacutnents supporting change) if OWNER or CONTRACTOR believe that the above change has afFected Contract Frice any Claim for a Change Order based thereon will involve one or more of the following methods as defined in the Contract Documents. Method of determining change in Contract Price: ^ Unit Prices ^ Lump Sum _ ~ evD ~[ Cvst of the Work ~.~~ ~r !Estimated increase (decrease) in Gantract Price: Estimated increase (decrease) in Contract $_ ~ , ~ ~~ •~ Times: If the change involves an increase, the estimated Substantial Completion: „~,_ days; amount is not to lie exceeded without further Ready for final payment: ~~ days_ authorization. RECOMMENDED: AUTHORIZED: F.NG[NEER owNe~ By: By: FJCI]C No. 1910-8-F (t996 Edition) Pteper~ed by dz EntiioxB Join Cauda~K Documents Commitlee aed eodo~sed by'n~e Aaavriaad Gtneral Cantracro~s of Afaerica and the Co~truaion Spocit~eeons Instnnte.