Memo
To: Jaycee Holman; Tara+Green
From: Kyle Radek, P.E., Staff Engineer
CC: File
RECEIVE
APR 0 3 200
City ®f Meridian
City Clerk Office
Date: 4/3/08
Re: Proposed Agenda Item for April 15, 2008 City Council Meeting
The Public Works Department respectfully requests the following item be placed on the
March City Council agenda, under Consent Agenda, for Council's consideration:
~:
Change Order Number 2, of Contract with Treasure Valley Drilling for Construction of Well 27
for: additional well. development, test pumping, and mud-weighting material.
Recommended Council Action: The Public Works Department recommends that City
Council approves Change Order Number 1, of Contract with Treasure Valley Drilling
for Construction of Well 27 for additional well development, test pumping, and
additional cost for mud-weighting material for a cost not to exceed $27,000 and
authorizes the Mayor to sign it.
Thank you for your consideration. Please contact me if you have any questions regarding
this item.
• Page 1
t
~_
~"
,, , ~~
;;
,i
;; ~~
;" I
,,
,~
:r
CITY OF MERIDIAN
33 EAST IDAHO
MERIDIAN, ID 83;642
i
CONTRACT CHANGE ORDER
;~
Change Order No~ 2
Project Number: , 0670b
Date: , 4/3/2008
Effective Date:
CONTRACTOR: ,Treasure Valley Drilling
PROJECT: /Well 27 Construction
The Contractor is hereby directed to make the following changes from the Contract Documents and Plans.
Desciption:
1) Additional well development
2) Test pumping- not in original contract
3) Higher total cost of mud-weighting material
4)
5)
.4
Reason for Change Order: j
Additional well development required due to flow that was not consistent with the expected specific
capacity of well. Test pumping was not in original contract.
Attachments:
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price: , $251,300.00 Original Contract Completion Date:
i
~ Original Contract Completion Days:
Net changes form previous C.O.'s.: ~ Net Days change form previous C.O.'s:
No. 0 to 1 ~ No. 0 to 0
$35,000.00
Contract Price Prior to this C.O.: ~. Contract Completion Date before this C.O.:
,~ $286,300.00 Contract Completion Days before this C.0 0
Net Increase (decrease) of this C.O.: ~ Net Days Increase (decrease) of this C.O.~'
$27,000.0
Contract Price with all Approved C.O.'s: ~ Contract Completion Date with all Approved C.O.'s:
t $313,300.00 Contract Completion Days with all Approve 0
'RECOMMENDED: (CONSTRUCTION MANAGER)
I
By:
I
.Date: ~
i
COUNCIL APPROVAL
~ Date:
APPROVED: (CITY) - ~~, ATTEST:
By: Mayor Tammy de Weerd ~ By: City Clerk, Jaycee Holman
Date: ~ Date: