Loading...
HomeMy WebLinkAboutChange Order No. 1 with Northwest Electrical for Water Division Building 2CITY OF MERIDIAN 33 EAST IDAHO MERIDIAN, ID 83642 CONTRACT CHANGE ORDER CHANGE ORDER NO. 1 PROJECT NO. 0607a DATE: 09/13107 EFFECTIVE DATE: CONTRACTOR: Northwest Electrical PROJECT: Water Division Building The Contractor is hereby directed to make the following changes from the Contract Documents and Plans. Description: 1) Provide all labor and materials to install additional length of secondary conductors to transformer that was relocated as per RFI #4 (Add $3,700.00) 2) Provide a credit for light pole that was deleted as per ASI #6 as prepared by BRS Architects. (Deduct $885.00) 3) Provide power to existing irrigation system as per the direction of the City of Meridian and BRS Architects response to RFI #61. (Add $2,643.00) Reason for Change Order: Construction progress. Attachments: AIA Document G701/CMa - 1992 Change Order -Construction Manager-Advisor Edition Submitted by Kreizenbeck Constructors CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price $ 173,824.00 Original Contract Times: Completion Net changes form previous Change Orders Net changes form previous Change Orders No._0_ to _0_ No._ to _ (calendar days) $0.00 None Contract Price Prior to this Change Order: Contract Times prior to this Change Order: (calendar days or date) $173,824.00 Net Increase (decrease) of this Change Order: Net Increase (decrease) of this Change Order: (calendar days or date) $5,458.00 Completion by Contract Price with all Approved Change Orders: Contract Times with all Approved Change Orders: (calendar days) $179,282.00 RECOMMENDED: (CONSTRUCTION MANAGER) ACCEPTED: (CONTRACTOR) See provided AIA signed change order See provided AlA signed change order By: By: Date: Date: ,~~iiiii APPROV ITY Pl)SING AGENT) ~~~~~~9 f/// ~ ~~ ,~1 ~` ~ ~ C~QUNCtL AFP,ROVAL ~3Yf ~~i i i ' d By: K ,~, . O~~q T / ~ Date: G ~ -~ ~- ~ `~ - F d Date: 14 a~v~ APPRO (CITY) - ATTESTk.6 _ , ~ By: Mayor Tamm a Weerd ~ ~ ~ ,1q :&y: City,Clerk~Will Berg Jr. 7 `'~/ Date: %~ C ~ ~ Date: ` ~P~~~-,-~ ' i i f~+avV f ~~~fff~~rtl Ittttt~~~~~~. a` =:;-:- ~ . _ Document G701/CMa 1992 Change Order -Construction Manager-Adviser Edition PROJECT (Name and address): Meridian Water Department Building 06- 021 CHANGE ORDER NUMBER: 001 INITIATION DATE: August 03, 2007 OWNER: CONSTRUCTION MANAGER: ARCHITECT: ~ CONTRACTOR: FIELD: OTHER: ^ 2235 Northwest 8th Street Meridian, Idaho 83642 TO CONTRACTOR (Name and address): Northwest Electrical 1471 East Commercial Avenue Meridian, Idaho 83642 PROJECT NUMBERS: 06-021 / 16100 CONTRACT DATE: February 20, 2007 CONTRACT FOR: General Construction THE CONTRACT IS CHANGED AS FOLLOWS: 1) Provide all labor and materials to install additional length of secondary conductors to transformer that was relocated as per RFI #4. $ 3,700.00 2) Provide a credit for light pole that was deleted as per ASI #6 as prepared by BRS Architects. Deduct <$885.00> 3. Provide power to existing irrigation system as per the direction of The City of Meridian and BRS Architests response to RFI #61. $2,643.00 The original Contract Sum was S 173;824.00 Net change by previously authorized Change Orders $ 0.00 The Contract Sum prior to this Change Order was $ 173;824.00 The Contract Sum will be increased by this Change Order in the amount of $ 5,458.00 The new Contract Sum including this Change Order will be $ 179;282.00 The Contract Time will be unchanged by Zero (0) days. The date of Substantial Completion as of the date of this Change Order therefore is NOTE: This summazy does not reflect changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized by Construction Change Directive. NOT VALID UNTIL SIGNED BY THE OWNER, CONSTRUCTION MANAGER, ARCHITECT AND CONTRACTOR. I4eizenbeck, LLC DBA Kreizenbeck Constructors CONSTRUCTION MANAGER (Firm name) 251 East Front Street, Suite 110, Boise, Idaho 83702 ADD , BY (Signature) G~t,~~ Michael J. Berard ,O ~7 (Typed name) DA E: Northwest Electrical CONTRACTOR (Firm name) 1471 East Commercial Avenue, Meri ' ,Idaho 83642 ADDRESS BY (Signature) "~~~tr ~ytCt-~ nM `~~~ ~0~ (Typed name) ~ DATE: BRS Architects ARCHITECT (Firm name) 1010 S. All to Street, Suite 100, Boise, ID 83709 ADDR ~ ~~ BY (Signature) Clinton Yaks (Typed name) DATE: Citv of Meridian OWNER (Firm name) \ `~ ~ ~ t i t i i t f i l r r~ 660 East Waterto r, Suite 200, Meridian, 0 316a „~ . ~ ~~~i~~ ADDR `\\~~~ ~.` ''~.~ ~~ii BY (Signature) - ~ ~ (TYPed name)` II r _ TE: ~ O_ ~~ ) Y'l;U~a` ` d'~• 1. ~ni ~ \~~`~ ~~ AIA Document G701/CMaTM-1992. Copyright ©1992 byThe American Institute of ArchHects. All rights reserved. ®ARNING: This dP~/ Do i ~`~~~~~ protected by U.S. Copyright Law and International Treaties. Unauthorized reproduction ar distribution of this AIA Document, or any ~6kiprtgft¢;1 t ' may result In severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 16:32:20 on 08106!2007 under Order No.1000280013_1 which expires on 1/17/2008, and is not far resale. UserNotes: (2634603652) _ _. _ .. ... ., ' _ .. .. . ~. - ~ G .;.. ,., .. . .. ~ _ .. t. ~ - Yy~. ~/.~a ~qu~~~ / ~ ~~~,A 5. ~r®pc~a~;~ w 5 ~ ~, . a M ~~ Y~ v Change request number ' :1003 - n.Wate~ Dwision ; _ end~ 07104 /_ ~' ,- , Pro)2ct: ~ . • . : ; wn~ Oe ~ Reloc~ted:Transformer ! ' ; ' := (name and;y 2235 NW Sth Stte t , , su~pt - , address) Meridian 1D 83642 + ` ~ '•. ~'' - 'Status ~ ~ _ - ' .-. .: :.` _ ate: Origination, d• 07/24!07 t _ r ~ Customer .Kreiienbeck Constructors _ -- ~ ~ ~ _ - ' - t " .~.; i :. _ Notice'to Proceed - ___ Quot2bon' _ _- - - Submitted date ~ ~ n - ~ ~~~~ubmitted date:- ' 07!24'/07 - - ; _... -_ `Received date; .. - - .'Due date: - ~ _ 07/31/07_ ~ _ • Rough order of magnitude: 0.00 ,. ,S,utimitted.amount: -3,700:00 -- .- _ _ - Requested days delay: 1 -- No4es . _ ~ _ - .. - _ .. 1. Price reflects the revised location ofi the Transformer as set on _ ~ - _ ~ - _ _ ~- ~ . - site (moved East). - ~ _ ^ _ •:_ -- ' RevenueDatail 7 I' -.. . ~ .. ". - • Billing Item 'Description' ~ - - • ' Revenue . - - _ 3, 700.00 ~. Totai Revenue: 3,700.00 Contractor Pricing - - _ - • -_ _ - ~ Phase Code /Description • Cost Type ~ - y ~ Quantity UM Amount - ... 99-1000 Change Orders M MATERIAL • ' -- - 2,056.04: - _ - 99-1000. , ~ Change Orders _ ' L LABOR - . ~ _ ~ Y,032.44' 99-1D00 Change Orders ~- O OVH~D & OTHER - - 275.00 - Contractor Pricing Tota l _Y - ~ .3.363.48 . -. . • - _. Total.. .. _ - 3,363,48 •-- • Mark-up; •. -- - : _ _ •. 336.52 _ - ... .._ _ - - Total Contractor Price for CR'1003 ~ ' 3,700.00 - _ - Approvals .. ~. Customer. Kreizenbeck Constructors ~ Contractor: Northwest Electri cal, Inc. _ ~ - ' Authorized P.epresentativet" - r"' ~ - _ _ Date: -_ Date: . .. . .. - .. _. ._ _ +. .. - t I.~~n .. . - - - t _ ' . . _ ~ - :- ~J . .. v.- ~ '.:~ ~ _} ' •~ 1 ` ` r `Print r7ate. 07/24!0; . ~. - . - ._-~ ..~ - _ . . ' ' - ..~ ~ . Page 1 of 1 ` •.~., ' ~ ,, , s~ - .. _ ., .. t ~ i i P t a ~z , ~ ; . ~ ~ ~ ~. ~ ~,_Pr~o ect~; r ~ p71pq~/ iNendian .Water Division Change rnquest number 1002 ~ . j ~ 2235 NW.8th Sue's, t-__ Descnption: _ A51 #6 -Site Ughtirig Mod. ~` ~"~ address=Meridian, ID 83642;. Status:. ~ ~ - ~ ;,~~. ~~ ,~ r <^" _ Q/iginatian date: .07/12!07 - - ~ _ . `Cu'stomer ~' KreizenbecfCGon5tructors - - - .. _ _ . ~ ~ .. - :- ~ tY - _ } ~ ~: ~ - • ~,~ _ Quotation . ._ ,. . s NoUCe to Proceed ~ - . _ .. _ - 4 -. ... -. -•. .. - ._ .. ~_ Submitted dzte: - ~ Submitted data: 07/12/07 _ _ ~ . ' rReeenred dale:. _. - _ Due date: ... - 07/1810T - - __ -Rough osier of magnitude: O.l?0 5ubinitted amount; X85,21 _ . z - .{ - - _ ~ RzGuested days delay: -~4 - ~ Wotes ~~ - . _ -- -. - _ - _. _ - - - - .. .- 1. ~ Price reflec#s changes as Proposad.in AS- No: 6 -- .._ Reversue Detail ~ - - F~IHing Rent ~ DQSCriastion ~ ~ ~ Revenue . _ _ _ _ .. - ~_ ~. -885.21 • ~ Tcita! Revenue: _ ' -- - .. .: _ ~ -885:24 . . Contractor Prieirtg • ~ ~ .~` Phase CodQ / ®escripaacrt - . - Cast 3ype Qtsantety, U~;, Arnourt4 _.. .. . 217:00 99-1000- ~ Change Order's` . ~ , :,. 'L' LABOR . ~ ' ; . 99-1000 ~ Change Orders ~ M RAATERtAL ' - -. -269 85 ~ - ' 99=1000 '•Changa Orders = E EQUIPMENT _ 6 w _398 56".- '.,.. ,;. ... - - _ ~ Contractor Piicing Total: • -885 21- . _ ~ - ~ .. Total - • . ' .885.21 s .. - ~ _ ~flai-k-up: 0:00 885.21 - ~ ~ Total Cortf'actar Pace for;,GR 1003 - _,.. , - . _. _~~ ~ Approvals ~ - - Customer. Kreizenbeck Constructors Contractor. NorthwesK~Electrical, Inc '~ ~,~ Authorized Repressntatfve: - - -- ~ - ri} . ay: - ~ _ - ay: - ~ _ Date: Dale: .. - _ ~ - - -; . _ - _ - ... - _ zT y ~' ~ .. ~ - ~. ~. ut _ - -:. ~ ~ t _ _ _ r ~ Print Date 07/12,/07 ~ _ .. .- s 'Page 1 of 1 i .. ~ ~' +rrt, f ~'~ ' _ 1. t r 4.~' -I - .. .., .nr 7.- -IS.. , L 3 n _ ._., . ~ r .~ .~, ¢ ~y ~ ~ ue~f P'rt~p®~a1 e Re ~ ~? ~ha~ , q g _ ~ -~._ 4,.. :. is .. ..., ~.tr. .... .~.: :, .-..:.. Water Division Project ` 07104 / Meridian .~1004 : ~. request number : . Change ~, ;;.''~ ;~' h. •~ . . (name'and 2235 NW 8th Street. ` ~ .. ~ ~ _ -- - - DescnpUon . ' " RFI #&1 ~ Imgapon Control `" ° ~ ~ ~ ,,, ;~ address) . .Meriiiian, ID, 83642, _ Status 04 x ~' ° _ ~,~ ,' 4 ' ~ '•''_ R - - - ~ ~~ " ~- ~ ~ .,~ • E ~' .-0ngmahon date t 07!28!07 , _ Customer'.• ~ KreizenbeUc.Constrrrctors ~ } _ -- ~ ''-~ ~~ -.~."-'`l` ~ ~ '`'' 4~ _ ..,.. . _. e d - ~ • No ic :to P g : Quotation - - r v ;a _ . e- , •. , e r c t . - ~' x : `Sutimit+ed date . ~ - ~ ~ J y .. Submitted date: 07/28/07 - ~ ~ ,s . • Received date : ~ ~ - - Due date _ , . 08!06%07 ~ a' _ Rough order of magnitude: 0.00 ~ -- .Submitted amount ~ 2643.00 _ .. - - .:Requested days delay. _ 0 _ -. ,- .- a Notes - :' _. .- : .. .. - - .. ' -~ 1•.' Pncmq'reflects 8dditional worst as proposed in,KCl •RFI-#61: _ - - ~ ~ - ~ ~t. - 2.:Price excludes cutting and patctiinq. :: ~---' ~ - - - ' Revenue'Detail--. . -. -__ . - Billinc item; Descrigtioti ~ .Revenue _.•. - _. . - •: . , .2,643:00 . • .To4at Revenue: •..2,643.00 - Contractor: Pricing ~ - ~ _ • • .• • -=Phase Code I Descriptipn • -- . _ Gost Tvpe _,_ __ . _ ,. _: " Quantity', UM -. . • ~ Amount ~ ~,"~ _ _ ,_ - "• 99-1000 = ~ :; Ghange_Orders •• 1 044 12 , .N1, MATERIAL r : .. .. -,r 99-1000 ~" - .Ghange Orders -- . • . ; ..:', 7 259 58 L . LABfl,R - _ ~ w"' ~. -99-1:000` Ghange•Orders O' OVND & OTHER? . - 100 Opp ';:~ • - ~. •~Contcactor Pricing TotaL• • ~ ~ - ~ "2 40370,• :c -. ~ ~~ • _ ~ - •Totat .. . -- •„. _ _.. 2 403 Ttl. ,.~.., ~ _ -. _. ,, - - - - .:.. a .: - Mark up -• - 239 30 ..: .... ,. .. :- ' T ~ _ 2,643 D0 otal Contractor Price for CR 1004 ,. . ` - Approvals ' - • -Customer: Kreizenbeck Constructors ~ _ -Contractor. Northwest fle Fical, inc. ,/• - ,. .• Authorized RepresentatiJe: •.. - .. . _ ~~ Dafe: ~ - _. f Dater .. _ - -~ w~ l - PrintCate: 07/31/07 ,- : ~ ~` ~ . . -..- - ~ Page..1 of 1 •~ ~ ._ _ .. - - s , :, ..: ... - ,: ... - -