HomeMy WebLinkAboutChange Order No. 2 with NW Electric for Water Division BuildingRECEIVED
Memo
To: Will Berg; Tara Green
From: Max Jensen, Engineering Technician
CC: Len Grady, P.E., City Engineer
Clint Dolsby, P.E., Assistant City Engineer
Kyle Radek, P.E., Assistant City Engineer
Rick Clinton, Water Department Superintendent
Date: 11 /27/2007
Re: Proposed Agenda Item for December 4, 2007 City Council Meeting
NOV 2 7 2007
City Of Meridian
City Clerk Office
The Public Works Department respectfully requests the following item be placed on the
December 4, 2007 City Council agenda, under Consent Agenda, for Council's consideration:
Change Order No. 2 for the Water Division Building proiect (construction -Northwest
Electrical). Additional electrical work is required for the completion of the new Water Division
Building. This change order consists of the following work and amounts to 0.03% of the
construction contract:
followingwork pertaining to SCADA and electrical modifications made by to the buildings
original responses to Request for Information from the design architects, BRS
• Provide additional labor and materials to install raceways and rough-in for SCADA
equipment.
• Provide additional labor and materials for electrical modifications by BRS (Design
Architects).
Kreizenbeck Constructors (The City of Meridians' project construction managers) prepared
and submitted the change order.
Recommended Council Action: The Public Works Department recommends
that City Council approves Change Order No. 2 for the Water Division Building
project (construction -Northwest Electrical) for $9,349.00 and authorize the
Mayor to sign it.
Thank you for your consideration. Please contact me if you have any questions regarding
this item.
From the desk of...
Max Jensen
Engineering Technician
Meridian Public Works Department
660 E. Watertower, Suite 200
Meridian, Idaho 83642
Phone: (208) 898-5500
Fax: (208) 898-9551
jensenm@meridianciry.org
• Page 1
CITY OF MERIDIAN
33 EAST IDAHO
MERIDIAN, ID 83642
CONTRACT CHANGE ORDER
CHANGE ORDER NO. 2
PROJECT NO. 0607a
DATE: 11 /27107
EFFECTIVE DATE:
CONTRACTOR: .Northwest Electrical
PROJECT: Water Division Buildin
Plans.
Description:
1) Provide all labor and materials to install raceways and rough-in for SCADA antennas per ASI #10 as
prepared by BRS. (Add $1,725:00)
2) Provide all labor and materials to relocate fire bell to the location required per the Fire Marshall.
(Add $1,750.00)
3) Provide all labor and materials to install electrical connection to CU #8, which was relocated per BRS
Architects response to RFI #59. (Add $1,393.00)
4) Provide all labor and materials to install additional raceways and rough-in for SCADA antennas per
BRS Architects reponse to RFI #69B. (Add $3,761.000)
5) Provide all labor and materials to replace existing receptacles with TVSS receptacles in Room 119 as
per BRS Architects reponse to RFI #72. (Add $720.000)
Reason for Change Order: Construction progress.
Attachments: AIA Document G701/CMa - 1992
Change Order -Construction Manager-Advisor Edition
Submitted by Kreizenbeck Constructors
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price $ 173,824.00 .Original Contract Times: Completion
.Net changes from previous Change Orders Net changes form previous Change Orders
No._0_ to _1_ No._ to _ (calendar days)
$5,458.00 None
.Contract Price Prior to this Change Order: Contract Times prior to this Change Order:
(calendar days or date)
$179,282.00
Net Increase (decrease) of this Change Order: Net Increase (decrease) of this Change Order:
(calendar days or date)
$9,349.00 Completion by
Contract Price with all Approved Change Orders: Contract Times with all Approved Change Orders:
(calendar days)
.$188,631.00
RECOMMENDED: (CONSTRUCTION MANAGER) ACCEPTED: (CONTRACTOR)
See provided AIA signed change order See provided AIA signed change order
By: By:
Date: Date:
APPROVED: (CITY PURCHASING AGENT) COUNCIL APPROVAL
By: Keith Watts
.Date: Date:
APPROVED: (CITY) - ATTEST:
By: Mayor Tammy de Weerd By: City Clerk, Will Berg Jr.
Date: Date: