Memo
To: Will Berg; Tara Green
From: Kyle Radek, P.E., Staff Engineer
CC: File
Date: 11 /1 /07
Re: Proposed Agenda Item for November 7, 2007 City Council Meeting
The Public Works Department respectfully requests the following item be placed on the
November 7 City Council agenda, under Consent Agenda, for Council's consideration:
Change Order #1 to agreement for Professional Services with Civil Survey Consultants Inc.
for design of Lanark /Commercial Water Line Connections
Recommended Council Action: The Public Works Department recommends
that City Council approves Change Order#1 to the Agreement for Professional
Services with Civil Survey Consultants, Inc. for design of Lanark / Commericial
Water Line Connections for a cost not to exceed $6500.
Thank you for your consideration. Please contact me if you have any questions regarding
this item.
• Page 1
CITY OF MERIDIAN CHANGE ORDER NO. 1
33 EAST IDAHO PROJECT NO. 615
MERIDIAN, ID 83642 DATE: 11/1/2007
EFFECTIVE DATE: 11/1/2007
CONTRACT CHANGE ORDER
,CONTRACTOR: Civil Survey Consultants
PROJECT: Lanark /Commercial Water Line Connections
The Contractor is hereby directed to make the following changes from the Contract Documents and
Plans.
Desciption:
Additional design services.
Reason for Change Order: Unanticipated rework due to easement and UPRR issues.
Attachements: None
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Ori final Contract Price $ 23,915.00 Ori final Contract Time: na
Net changes form previous Change Orders Net changes form previous Change Orders
No._ to _ (calendar days)
$ -
Contract Price Prior to this Change Order: Contract Times prior to this Change Order:
(calendar Days or date)
$ 23,915.00
Net Increase (decrease) of this Change Order: Net Increase (decrease) of this Change Order:
(calendar days or date)
$ 6, 500.00
Contract Price with all Approved Change Orders: Contract Times with all Approved Change Orders:
(calendar days)
$ 30,415.00 na
RECOMMENDED: (CONSTRUCTION MANAGER) ACCEPTED: (CONTRACTOR)
By: By:
Date: Date:
APPROVED: (CITY PURCHASING AGENT) COUNCIL APPROVAL
By: Keith Watts
Date: Date:
APPROVED: (CITY) - ATTEST:
By: Mayor Tammy de Weerd By: City Clerk, Will Berg Jr.
Date: Date: