To: Will Berg; Tara Green
From: Kyle Radek, P.E., Staff Engineer
CC: File I ,e ~ d7f /,,'/hrr
Date: 8/13/07
Re: Proposed Agenda Item for July 24 City Council Meeting
The Public Works Department respectfully requests the following item be placed on the
August 21 City Council agenda, under Consent Agenda, for Council's consideration:
ChanCle Order Number 2, Water and Sewer Improvements in Coniunction with ACHD West
1st Street. WashinClton to Chenv Road Proiect: This change order adds an additional hot tap,
additional pipe sleeve material, valves, 2 hydrants, and other items not included or
anticipated on the original bid or the first change order.
Recommended Council Action: The Public Works Department recommends
that City Council approves Change Order Number 2 for Water and Sewer
Improvements in Conjunction with ACHe West 1st Street, Washington to
Cherry Road Project for a cost of $33,235 and authorizes the Mayor to sign it.
Thank you for your consideration. Please contact me if you have any questions regarding
this item.
. Page 1
CITY OF MERIDIAN
33 EAST IDAHO
MERIDIAN, 10 83642
CHANGE ORDER NO.
PROJECT NO.
DATE:
EFFECTIVE DATE:
CONTRACT CHANGE ORDER
2
0668b
8/13/2007
8/13/2007
CONTRACTOR: King Excavation
PROJECT: West First Street, Washington to Cherry
The Contractor is hereby directed to make the following changes from the Contract Documents and
Plans.
Desciption:
Price includes additional hot tap on Washington, 500 cyof bedding material excluded from CO #1. additional
pipe sleeving material needed. 8 additional water services not included in original bid. 3 additional valves, 2 fire
hydrants, and 2 bollards.
Reason for Change Order: Items needed and not included in original bid or CO #1.
Attachments:
Bids from King Excavation
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
IOriginal Contract Price $ 18,042.50 IOriginal Contract Time: 1201
Net changes form previous Change Orders Net changes form previous Change Orders
No._1_ to _1_ No,_ to _ (calendar days)
$
88.800.00
o
Contract Price Prior to this Change Order:
Contract Times prior to this Change Order:
l calendar days or date)
$
106,842.50
120
Net Increase (decrease) of this Change Order: Net Increase (decrease) of this Change Order:
Ilcalendar days or date)
$ 33,235.00 0
Contract Price with all Approved Change Orders:
Contract Times with all Approved Change Orders:
lcalendar days)
$ 140,077.50
UCTION MANAGER) ACCEPTED: (CONTRACTOR)
120
By:
Date:
p;~-0'7
By:
Date:
APPROVED: (CITY PURCHASING AGENT)
COUNCIL APPROVAL
By: Keith Watts
Date:
Date:
APPROVED: (CITY) -
ATTEST:
By: Mayor Tammy de Weerd
Date:
By: City Clerk. Will Berg Jr.
Date: