City of Meridian
Public Works Dept.
RECEIVED
AUG 0 S 2007
City Of Meridian
City Clerk Office
Memo
To: Will Berg; Tara Green
From: Max Jensen. Engineering Technician
CC: Len Grady, PE. City Engineer
Date: 8/0812007
Re: Proposed Agenda Item for August 14, 2007 City Council Meeting
The Public Works Department respectfully requests the following item be placed on the
August 14, 2007 City Council agenda, under Consent Agenda, for Council's consideration:
ChanQe Order No. 1 for McMillan Water Line - Wild Goose to Palatine (construction).
Additional work is required for the completion of the McMillan Water Line - Wild Goose to
Palatine project (design). This change order consists of the following work and amounts to
0.06% of the oonstruction oontract:
· Additional asphalt paving per ACHD requirements and larger size blow off.
Recommended Council Action: The Public Works Department recommends
that City Council approves Change Order No.1 for the McMillan Water Line -
Wild Goose to_Palatine project (construction) with Star Construction, LLC, for
$3,436.21 and authorize the Mayor to sign it.
Thank you for your consideration. Please contact me if you have any questions regarding
this item. Originals will be sent for signature upon review.
From the desk of...
Max Jensen
Engineering TedlOician
Meridian Public Works Department
660 E. Watertower, Suite 200
Meridian, Idaho 83642
Phone:(208)8~5500
Fax: (208) 8~9551
jensenm@meridiancity.otg
. Page 1
.........__........ii:..-;.
CITY OF MERIDIAN
33 EAST IDAHO
MERIDIAN, 10 83642
CONTRACT CHANGE ORDER
CHANGE ORDER NO. 1
PROJECT NO. 0645
DATE: 8/08/07
EFFECTive DATE: 8/08/07
CONTRACTOR: STAR CONSTRUCTION, LLC
PROJECT: McMILLAN WATER LINE - WILD GOOSE TO PALATINE
The Contractor is hereby directed to make the following changes from the Contract Documents and
Plans.
Desclption: Additional asphalt paving per ACHD and larger size blow off.
ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME.
Reason for Change Order: Additional asphalt paving per ACHD requirements and larger
size blow off.
Attachements: Invoice from Star Construction with additional cost invoices.
CHANGE IN CONTRACT PRICE:
Original Contracl Price $ 56,280.80
Net changes form previous Change Orders
No._O_ to _0_
$0.00
Contract Price Prior to this Change Order:
$56,280.80
Net Increase (decrease) of this Change Order:
$3,436.21
Contract Price with all Approved Change Orders:
$59,717.01
RECOMMENDED: (CONSTRUCTION MANAGER)
By: /V(~~
Date: 8/8/07
APPROVED: (CITY PURCHASING AGENT)
By: Keith Watts
Date:
APPROVED: (CITY) -
By: Mayor Tammy de Weerd
Date:
CHANGE IN CONTRACT TIMES:
Original Contract Times:
Nel changes form previous Change Orders
No._ to ~ (calendar days)
None
Contract Times prior to this Change Order:
(calendar daY5 or date)
Net Increase (decrease) of this Change Order:
(calendar days or dale)
Contracl Times wilh all Approved Change Orders:
(calendar daY5)
-
By: Ancil Irminger
Dale: 818107
COUNCIL APPROVAL
Date:
ATTEST:
By: City Clerk, Will Berg Jr.
Date;
i
08/00/2007 10:10 2082867947
STAR CONSTRUCTION
PAGE 01
Star Construction, L.L. C.
P.o. Box 157 Star, IV 83669
(208) 286-9198
Invoice
( DATE) ( 8I8nOO1 )
( INVOICE # )( 1092 )
( BILL TO J
city. of Mericl.iaa
660 E. Watertower Lau, Sake 100
Meri4iH, JD ~2
..
P.o. NO. TERMS JOB
Net 10 me M.:lll'co.'" w.+--cr L:"c. - W ~ \d) Goo~c...\::. ~\" ,,:~
DESCRIPTION QTY UNIT RATE AMOUNT
otJiMl aJIItr8ct ~.280.80 56,280.80
.~aspbaIt pcrGldcrpcr ACIID A~ 2.768.28 2,761.28
J......M 2- JD1D8DCDl tap per city n::q'ldt 667.93 667.93
.' .
Total $59,711.01
_.-..c