HomeMy WebLinkAboutChange Order No. 4 with J.C. Constructors, Inc. for WWTP
City of Meridian
Public Works Dept.
Memo
RECEIVED
JUN 2 1 2007
City Of Meridian
City Clerk Office
To: William Berg, Jr.; Tara Green
From: Clint Dolsby, P.E., Staff Engineer
cc: Len Grady, P.E., City Engineer
Date: 06/20/2007
Re: Proposed Agenda Item for June 26, 2007 City Council Meeting
The Public Works Department respectfully requests the following item be placed on the June 26 City
Council agenda, under consent agenda, for Council's consideration:
Chanoe Order NO.4 for the Wastewater Treatment Plant Expansion Proiect. Additional work is
required for to retrofit the existing tertiary filter with the prepurchased Aquadiamond cloth media filter
equipment. This change order consists of the following work, which is 1.88% of the original contract
amount for the project. This makes the total changes from Change Order No.1, 2, 3, and 4 equal to
6.7% of the original contract amount.
. Retrofit the existing tertiary filter with the cloth media Aquadiamond filter equipment that has
been prepurchased by the City.
JC Constructors, Inc. submitted a cost for this change order as summarized below:
.
JC Constructors, Inc.
$157,019.41
Recommended Council Action: The Public Works Department recommends that City
Council approves Change Order NO.4 for the Wastewater Treatment Plant Expansion
with JC Constructors, Inc. for $157,019.41 and authorize the Mayor to sign it.
Thank you for your consideration. Please contact me if you have any questions regarding any of these
items.
. Page 1
CHANGE ORDER 4
PROJECT:
City of Meridian Wastewater Treatment Plant Expansion Project
DATE OF ISSUANCE: June 20, 2007
EFFECTIVE DATE: June 20, 2007
OWNER:
City of Meridian
CONTRACTOR: JC Constructors, Inc.,
ENGINEER: Carollo Engineers
Page 1 of2
You are directed to make the following changes in the Contract Documents.
· Retrofit the largest existing tertiary filter with the cloth media Aquadiamond filter equipment that has been
prepurchased by the City (WCD 45)
Attachments: JC Constructors Change Proposal Request - (WCD 45) - 11 June, 2007 for $157,019.41
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times
$ 8.367.500.00 Substantial Completion: 670 Days - Seotember 1. 2007
Ready for Final Payment: 730 Days - November I. 2007
days or dates
Net Changes from previous Change Orders No. ~ to No..-J Net Changes from previous Change Orders No..J.L to No. 0
$ 403.527.07
Days
Contract Price prior to this Change Order Contract Times prior to this Change order
Substantial Completion: 670 Days - September 1. 2007
$ 8.771.027.07 Ready for Final Payment:~: 730 Days - November 1. 2007
days Or dates
Net Increase (decrease of this Change Order) Net Increase (decrease of this Change Order)
$ 157.019.41 0
days
Contract Price with all approved Change Orders Contract Times with all approved Change Orders
Substantial Completion: 670 Davs - Seotember 1. 2007
$ 8.928.046.48 Ready for final payment: 730 Davs - November 1. 2007
days or dates
RECOMMENDED BY ENGINEER:
ACCEPTED BY CONTRACTOR:
By:
By:
William J. Benko, P.E., Carollo Engineers
Jim Cox, I.C. Constructors
Date:
Date:
APPROVED BY OWNER:
Clint Dolsby, P.E., Public Works
Tanuny de Weerd, Mayor
Attest:
William G. Berg, Jr., City Clerk
Date:
Date:
Date:
Approved by City Council: