HomeMy WebLinkAboutCC - Engineer Statement km
E N G I N E E R I N G
August 5,2025
Project No.24-296
City of Meridian
33 E Broadway Ave.,Ste.210
Meridian, Idaho 83642
RE: Pollard North Subdivision No.2
Meridian,Idaho
To Whom It May Concern:
Please accept this letter as certification that the centerline elevations of the proposed streets within Pollard
North Subdivision No. 2 are designed a minimum of three (3) feet above the seasonal high ground water
elevation. The geotechnical engineering report, "Pollard Lane Realignment", prepared by Materials Testing&
Inspection and dated August 31,2016,was used to determine the approximate groundwater elevations relative
to the street centerline elevations.
Please feel free to contact me at 208.639.6939 should you have questions or require any additional information.
Sincerely,
KM Engineering,LLP
Sc,\ONAL fNc
ENSF
Digitally signed by
6860 Lachlin Kinsella, P.E.
U�, 8/5/25 Q Date: 2025.08.05
�0 qTF OF \oP 17:53:04-06'00'
Lachlin Kinsella, P.E.
Project Manger
5725 North Discovery Way • Boise,Idaho 83713 208.639.6939 kmengllp.com
From: Zach Meyers
Sent: Wednesday, October 15, 2025 5:17 PM
To: Eli Benski
Subject: Fw: [EXTERNAL] Pollard North and Alden Ridge
Zach Meyers I Director I Brighton Development
Brighton.co
From:Warren Stewart<wstewart@meridiancitV.org>
Sent:Tuesday, November 5, 2024 2:23 PM
To:Zach Meyers<zmeyers@brightoncorp.com>
Cc:Vicki Ly<vly@meridiancity.org>; Clint Dolsby<cdolsby@meridiancity.org>
Subject: RE: [EXTERNAL] Pollard North and Alden Ridge
Zach
After further review of this and similar situations, I will not require that you build the sewer
extension in Pollard Lane north of W. Flat Rock St. Please work with Vicki to ensure that the sewer
main extension in Woodhead Ave is deep enough to serve the balance of the sewer shed north of
your project.
Have a great day,
Warren Stewart, P.E.I City Engineer
�E III7�
From: Zach Meyers<zmeyers@brightoncorp.com>
Sent: Monday, November 4, 2024 10:42 AM
To:Warren Stewart<wstewart@meridiancity.org>
Subject: RE: [EXTERNAL] Pollard North and Alden Ridge
External Sender-Please use caution with links or attachments.
Warren,
appreciate the consideration.
Thankyou,
Zach Meyers I Director I Brighton Development
Brighton.co
From: Warren Stewart<wstewart@meridiancity.org>
Sent: Friday, November 1, 2024 4:11 PM
To:Zach Meyers<zmeyers@brightoncorp.com>
Subject: RE: [EXTERNAL] Pollard North and Alden Ridge
have been giving this some thought and I'm giving your request some serious consideration. I will
get back to you next week with a final answer.
Warren Stewart, P.E.I City Engineer
C��fE ID
From: Zach Meyers<zmeyers@brightoncorp.com>
Sent:Tuesday, October 29, 2024 8:32 AM
To:Warren Stewart<wstewart@meridiancity.org>
Subject: Pollard North and Alden Ridge
External Sender-Please use caution with links or attachments.
Warren,
I've been looking Pollard North a little bit more and had a follow up. Obviously,we don't want to
extend more sewer than is needed.There's additional cost to us to install, and if it is never utilized
there is additional cost to the city to maintain.With the removal of property served west of Hwy 16
from the master sewer plan, one stub is adequate to feed the property north currently pre-platted
as Alden Ridge.We discussed the sewer stub already shown at the Woodhead Ave. stub street
which is located at the midpoint of the Alden Ridge project.
think what I struggle with is why are we not building the system for what is approved today? I
understand that your concern is the lack of movement from the Alden Ridge project, but diving into
approval and document processing, it appears that they have a history of waiting until the last
minute. I believe your concern,though unlikely, can be addressed with the stub that is located
within the public right of way in Pollard Ln. Is there a reason that this existing stub provided would
not be considered accessible to the western most parcel?
I appreciate you taking the time last Tuesday to talk and your time looking at this again.
Thankyou,
**On a side note,the easement you and I talked about after. Looks like there was confusion during
the submittal and review and it was never processed. It was never intended to be a vacation of
easement nor did that ever happen.We've officially submitted the easement to extend and cover
what is needed per the record drawings out at Ten Mile.**
EP E¢— _P •EP •EP—
d3 a: EP
- - ii sii
I LL
FC3
SSMH 15 ( 6—INGFt}
RIM;2528.3-
DEPTLi:8.2' I 8"hh1-
1+130 $ 2+00
INS IN;2520,51 a' (N) �
INV OUT;25MA8 8" (E)
MERIDIAN RESEARCH — SEWERALIGfJMENT'C" 400.0' of S" PVG i
PARK LLC REFER TO PP3.2 FOR PROFILE
r
• - -
SSMH #1 Q (48—I1411CH)
RIM;2578-98 . .
DEPTH:8,3' +
y 1+00 - Q '�2s2t00 3+00 y
INV IN:2521.06 4- (N) � '
INV I1%1;2521.06 4" (S)
IM11V OUT:2520.73 8" (E) — — — — — — —
v I' J16 �f 46 46 A
SEWER ALI-,NMENT'R'-
ty
EXISTING SSCO #29 '� �� REFER TOPP3.LFOR PROFILE 352-5, pf e_ PVC 0 0.50%
RI M;2530.80
DEPTH:20.6' 49 40
INV OUT;2510.22 5" (S)
CONNEOt 1-0 EXI — —— —— — — — —
PRESSURE IRRIGATION SSTs i a
63.0' of 8" PVC 0 0.63 "9 347.0' Qf 5- PVC Ik 0.4396 ra
fi
12 12 12-W 12-W 12''+—�-12-w t
z LLJi
Z3 i
(A{
m EXISTING SSWA 02 (60—INCH)—aros #ems +�S r a�as— i
64.2' of 8" PVC 0 G.45 4 RIM:2531.07
DEPTH;21.3'
m INV IN: 509-82 8- (N) -
-T—— — 18B—INCH c
INV IN:25C9.82 8" Q SSMH � ( ) r�
I l.ni ni.r.'9Gnn 'M e" erl RIM;2534.57
Zach Meyers I Director I Brighton Development
2929 W. Navigator Dr. Suite 400 Meridian ID 83642
Direct: 208-901-4264 1 Main: 208-378-4000 1 Website: Brighton.co
BRIGHTON
NOTICE: Please update your records with my new email address and website(brighton.co).
This message was sent by someone outside the organization. Please do not click links or open attachments
unless you recognize the source of this email and know the content is safe.
This message was sent by someone outside the organization. Please do not click links or open attachments
unless you recognize the source of this email and know the content is safe.