HomeMy WebLinkAboutChange Order No. 2 with Ideal Demolition for New City Hall Asbestos Abatement CITY OF MERIDIAN 33 EAST IDAHO MERIDIAN, 10 83642 CONTRACT CHANGE ORDER CHANGE ORDER NO. 2 PROJECT NO. CH-06-001 DATE: 2/27/07 EFFECTIVE DATE: 2/27/07 CONTRACTOR: IDEAL DEMOLITION SERVICES, LLC PROJECT: ASBESTOS ABATEMENT & DEMOLITION The Contractor is hereby directed to make the following changes from the Contract Documents and Plans. Desciption: Excavation, loading covering, hauling & abatement of contaminated soil at the Meridian Creanery site. Price is $82.00/CY per proposal by David Aparicio dated 11/9/2006 with a Not-To-Exceed amount of $83,000.00. ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME. Reason for Change Order: Contaminated soil discovered that was not on original Haz-Mat Survey. Attachements: Proposal by Ideal Demolition CHANGE IN CONTRACT PRICE: Original Contract Price $ 390,800.00 Net changes form previous Change Orders No._ to_ $35,556.30 Contract Price Prior to this Change Order: $426,356.30 Net Increase (decrease) of this Change Order: $83,000.00 Contract Price with all Approved Change Orders: $509,356.30 RECOMMENDED: (CONSTRUCTION MANAGER) A CHANGE IN CONTRACT TIMES: Original Contract Times: Completion 1/12/06 Net changes form previous Change Orders No._ to _ (calendar days) None Contract Times prior to this Change Order: (calendar days or date) 1/12/2007 Net Increase (decrease) of this Change Order: (calendar days or date) Completion by 4/5/2007 Contract Times with all Approved Change Orders: (calendar days) 4/5/2007 ACCEPTED: (CIONTRACTOR) "'" , . " \ \ : ; ; t ; : I , : / -~ ; Date: ~ e~ .;:. ,-;,.;:", };.:.;~~~: ':~:~'~~L "'::;:" C:f/,:,,;QJ.:::?,;:;:.,.. <:r;l /; "\.. !' '> ATTEST: - ......~'-: L~~~l-i=jJ. . .~-~:.~.. \\, . ~ /r'" t ..~ .:: { (..... .> '+:~ l .- By: City Clerk, Will Berg J . fjk:.i.~ :.l-l;,-~I ~ Date: J -/~T.tJ ~ l;j~ ~~ ~ ,f..I& { 1 S~ · J;rr f:.ct~:.' :~::- -:-.... .i'Y ~ ..'\)'(. ~,>" , /<.. / . Cd"\l u. I~"'; '-i. ,< "